Loading...
HomeMy WebLinkAbout20260818 NOI Barnstable DPW Craigville Beach Road Bridge Repair Craigville Beach Road Bridge Repair Project Barnstable, Massachusetts Notice of Intent Town of Barnstable July 2026 88 Route 6A Sandwich, MA 02563 T 508.255.6511 B0633-020 July 30, 2026 Edwin Hoopes, Conservation Administrator Barnstable Conservation Commission 230 Main Street Hyannis, MA 02601 Re: Notice of Intent – Craigville Beach Road Bridge Repair Project 1134 Craigville Beach Road, Centerville, Massachusetts Dear Administrator Hoopes and Members of the Commission: On behalf of the Town of Barnstable (the Town), Tighe & Bond respectfully submits this Notice of Intent for the proposed repair/rehabilitation of the Craigville Beach Road Bridge over the Centerville River in Barnstable, Massachusetts. These bridge repairs are intended to address deficiencies observed during a comprehensive visual inspection conducted by Tighe & Bond in November 2022 and recorded in the most recent Massachusetts Department of Transportation (MassDOT) inspection report (dated July 2024). These inspections identified multiple issues in need of repair, including structural deficiencies (e.g. cracks, spalling), scour, vegetation overgrowth, failed bank channel protection, guard rail damage , and sidewalk deficiencies. The Craigville Beach Road Bridge was most recently reconstructed in 2002 and has not undergone rehabilitation since that date. The proposed work seeks to correct the reported deficiencies and reestablish the 2002 footprint of the bridge. This work will result in some fill to wetland resource areas to meet MassDOT minimum design standards as portions of the embankment have become dislodged overtime from scour and other environmental factors, which has enabled the migration of wetland resources into the former bridge footprint. The work is necessary to repair the stability of the pre-existing embankment. An NOI is required for this project as work will occur within areas subject to jurisdiction under the Massachusetts Wetlands Protection Act (MAWPA; M.G.L. c. 131§40) and the Town of Barnstable Wetlands Protection Bylaw (Chapter 237). These areas include Salt Marsh, Coastal Bank, Coastal Dune, Barrier Beach, Land Under Ocean, Land Containing Shellfish, Fish Run, and Land Subject to Coastal Storm Flowage. 2 Enclosed with this submittal is a completed Notice of Intent form (WPA Form 3), detailed project narrative, figures, project drawings, and other supporting materials. Should you have any questions regarding this application or require any additional information, please contact me at (508) 304 -6354 or via email at AJHoule@tighebond.com. Respectfully yours, Tighe & Bond, Inc. Amanda J. Houle, PWS, CERP PRINCIPAL ENVIRONMENTAL SCIENTIST Attachments: A - Site Location Map B - Photo Log C - Project Plans D –1998 Project Plans for 2002 Bridge Reconstruction E – Abutter Notification Information F – Historical and Archeological Resources Information Copy: Paul Graves, PE, Senior Project Manager, Town of Barnstable Department of Public Works Notice of Intent Table of Contents WPA Form 3 Wetland Fee Transmittal Form Town of Barnstable NOI Checklist Town of Barnstable Form PA Project Narrative SECTION 1 | Project Background ................................................................................................. 1-1 1.1 Project Location ............................................................................................................................................... 1-1 1.2 Project Need .................................................................................................................................................... 1-1 1.3 MAWPA and Barnstable Conservation Commission Jurisdiction .............................................................. 1-1 1.4 Summary of Anticipated Permits ................................................................................................................... 1-2 SECTION 2 | Existing Environment ............................................................................................... 2-3 2.1 Wetland and Watercourse Delineation ......................................................................................................... 2-3 2.1.1 Methodology of Resource Area Investigations ....................................................................................... 2-3 2.1.2 Jurisdictional Wetland Resource Areas .................................................................................................... 2-3 2.2 Rare Species .................................................................................................................................................... 2-6 2.2.1 State-Listed Species ................................................................................................................................... 2-6 2.3 Historic and Archaeological Resources ........................................................................................................ 2-6 SECTION 3 | Project Description .................................................................................................. 3-7 3.1 Bridge Repair Activities .................................................................................................................................. 3-7 3.1.1 Bridge Work ................................................................................................................................................ 3-7 3.1.2 Embankment Work ..................................................................................................................................... 3-7 3.1.3 Roadway Work ............................................................................................................................................ 3-7 3.1.4 Vegetation Work ......................................................................................................................................... 3-7 3.2 Anticipated Construction Sequence ............................................................................................................. 3-8 3.3 Construction Period Protective Measures ..................................................................................................... 3-8 3.3.1 Erosion Control Barriers ............................................................................................................................. 3-8 3.3.2 Water Control Measures ............................................................................................................................ 3-9 3.3.3 Dewatering .................................................................................................................................................. 3-9 3.3.4 Soil and Stockpile Management ............................................................................................................... 3-9 3.3.5 Sediment Management ............................................................................................................................. 3-9 Project Narrative Notice of Intent 3.3.6 Construction Period Access and Staging ................................................................................................. 3-9 3.3.7 Other Protective Measures ...................................................................................................................... 3-10 3.4 Post-Construction Site Restoration .............................................................................................................. 3-10 3.5 Mitigation Measures ..................................................................................................................................... 3-10 SECTION 4 | Alternatives Analysis .............................................................................................. 4-11 4.1 Alternatives Considered ............................................................................................................................... 4-11 4.1.1 Alternative 1 – No Action ......................................................................................................................... 4-11 4.1.2 Alternative 2 – Bridge Repairs (Preferred Alternative) .......................................................................... 4-11 4.1.3 Alternative 3 – Bridge Rehabilitation (Major Reconstruction) .............................................................. 4-11 4.1.4 Alternative 4 – Bridge Replacement ....................................................................................................... 4-11 4.2 Alternatives Impacts and Beneflts Comparison. ........................................................................................ 4-12 SECTION 5 | MAWPA and Barnstable Wetlands By-Law Regulatory Compliance ............... 5-14 5.1 Limited Project ............................................................................................................................................... 5-14 5.2 Environmental Impacts ................................................................................................................................. 5-14 5.3 MAWPA Performance Standards ................................................................................................................. 5-15 5.3.1 Salt Marsh .................................................................................................................................................. 5-15 5.3.2 Coastal Bank ............................................................................................................................................. 5-16 5.3.3 Barrier Beach ............................................................................................................................................. 5-16 5.3.4 Coastal Dune ............................................................................................................................................. 5-17 5.3.5 Land Under the Ocean ............................................................................................................................. 5-17 5.3.6 Land Containing Shellflsh ........................................................................................................................ 5-19 5.3.7 Fish Run ..................................................................................................................................................... 5-20 5.3.8 Riverfront Area .......................................................................................................................................... 5-20 5.4 Abutter Notiflcations ..................................................................................................................................... 5-22 SECTION 6 | Other Regulatory Compliance ............................................................................. 6-23 6.1 State Permits .................................................................................................................................................. 6-23 6.1.1 Massachusetts Historical Commission (MHC) / Section 106 Compliance .......................................... 6-23 6.1.2 MassDEP Individual 401 Water Quality Certiflcation ............................................................................ 6-23 6.1.3 Massachusetts Environmental Policy Act (MEPA) .................................................................................. 6-23 6.1.4 MassDEP Chapter 91 Minor Project Modiflcation ................................................................................. 6-23 6.2 Federal Permits .............................................................................................................................................. 6-23 6.2.1 Coastal Zone Management Act ............................................................................................................... 6-23 6.2.2 U.S. Coast Guard Bridge Permit .............................................................................................................. 6-24 6.2.3 U.S. Army Corps of Engineers Section 404 Clean Water Act ............................................................... 6-24 Project Narrative Notice of Intent Tables TABLE 1-1 Summary of permits, reviews, and approvals required by Municipal, State, and Federal Agencies 1-2 TABLE 2-1 Summary of Wetland Resource Areas by Flag Series ............................................................................ 2-3 TABLE 4-1 Alternatives Analysis Summary Table .................................................................................................... 4-12 TABLE 5-1 Summary of Anticipated Wetland Impacts ........................................................................................... 5-14 Appendices Appendix A: Site Figures Appendix B: Photo Log Appendix C: Project Drawings Appendix D: 1998 Project Drawings for 2002 Bridge Reconstruction Appendix E: Abutter Notiflcation Information Appendix F: Historical and Archeological Resources Information J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Permitting\NOI\Draft\Craigville Beach NOI Narrative_draft.docx WPA Form 3 Notice of Intent wpaform3.doc • rev. 12/4/2023 Page 1 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use the return key. Note: Before completing this form consult your local Conservation Commission regarding any municipal bylaw or ordinance. A. General Information 1. Project Location (Note: electronic filers will click on button to locate project site): a. Street Address b. City/Town c. Zip Code Latitude and Longitude: d. Latitude e. Longitude f. Assessors Map/Plat Number g. Parcel /Lot Number 2. Applicant: a. First Name b. Last Name c. Organization d. Street Address e. City/Town f. State g. Zip Code h. Phone Number i. Fax Number j. Email Address 3. Property owner (required if different from applicant): Check if more than one owner a. First Name b. Last Name c. Organization d. Street Address e. City/Town f. State g. Zip Code h. Phone Number i. Fax Number j. Email address 4. Representative (if any): a. First Name b. Last Name c. Company d. Street Address e. City/Town f. State g. Zip Code h. Phone Number i. Fax Number j. Email address 5. Total WPA Fee Paid (from NOI Wetland Fee Transmittal Form): a. Total Fee Paid b. State Fee Paid c. City/Town Fee Paid wpaform3.doc • rev. 12/4/2023 Page 2 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town A. General Information (continued) 6.General Project Description: 7a. Project Type Checklist: (Limited Project Types see Section A. 7b.) 1. Single Family Home 2. Residential Subdivision 3. Commercial/Industrial 4. Dock/Pier 5. Utilities 6. Coastal engineering Structure 7. Agriculture (e.g., cranberries, forestry) 8. Transportation 9. Other 7b. Is any portion of the proposed activity eligible to be treated as a limited project (including Ecological Restoration Limited Project) subject to 310 CMR 10.24 (coastal) or 310 CMR 10.53 (inland)? 1. Yes No If yes, describe which limited project applies to this project. (See 310 CMR 10.24 and 10.53 for a complete list and description of limited project types) 2. Limited Project Type If the proposed activity is eligible to be treated as an Ecological Restoration Limited Project (310 CMR10.24(8), 310 CMR 10.53(4)), complete and attach Appendix A: Ecological Restoration Limited Project Checklist and Signed Certification. 8.Property recorded at the Registry of Deeds for: a. County b. Certificate # (if registered land) c. Book d. Page Number B. Buffer Zone & Resource Area Impacts (temporary & permanent) 1. Buffer Zone Only – Check if the project is located only in the Buffer Zone of a Bordering Vegetated Wetland, Inland Bank, or Coastal Resource Area. 2. Inland Resource Areas (see 310 CMR 10.54-10.58; if not applicable, go to Section B.3, Coastal Resource Areas). Check all that apply below. Attach narrative and any supporting documentation describing how the project will meet all performance standards for each of the resource areas altered, including standards requiring consideration of alternative project design or location. wpaform3.doc • rev. 12/4/2023 Page 3 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town B. Buffer Zone & Resource Area Impacts (temporary & permanent) (cont’d) For all projects affecting other Resource Areas, please attach a narrative explaining how the resource area was delineated. Resource Area Size of Proposed Alteration Proposed Replacement (if any) a. Bank 1. linear feet 2. linear feet b. Bordering Vegetated Wetland 1. square feet 2. square feet c. Land Under Waterbodies and Waterways 1. square feet 2. square feet 3. cubic yards dredged Resource Area Size of Proposed Alteration Proposed Replacement (if any) d. Bordering Land Subject to Flooding 1. square feet 2. square feet 3. cubic feet of flood storage lost 4. cubic feet replaced e. Isolated Land Subject to Flooding 1. square feet 2. cubic feet of flood storage lost 3. cubic feet replaced f. Riverfront Area 1. Name of Waterway (if available) - specify coastal or inland 2. Width of Riverfront Area (check one): 25 ft. - Designated Densely Developed Areas only 100 ft. - New agricultural projects only 200 ft. - All other projects 3. Total area of Riverfront Area on the site of the proposed project: square feet 4. Proposed alteration of the Riverfront Area: a. total square feet b. square feet within 100 ft. c. square feet between 100 ft. and 200 ft. 5. Has an alternatives analysis been done and is it attached to this NOI? Yes No 6. Was the lot where the activity is proposed created prior to August 1, 1996? Yes No 3. Coastal Resource Areas: (See 310 CMR 10.25-10.35) Note: for coastal riverfront areas, please complete Section B.2.f. above. wpaform3.doc • rev. 12/4/2023 Page 4 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town B.Buffer Zone & Resource Area Impacts (temporary & permanent) (cont’d) Check all that apply below. Attach narrative and supporting documentation describing how the project will meet all performance standards for each of the resource areas altered, including standards requiring consideration of alternative project design or location. Online Users: Include your document transaction number (provided on your receipt page) with all supplementary information you submit to the Department. Resource Area Size of Proposed Alteration Proposed Replacement (if any) a. Designated Port Areas Indicate size under Land Under the Ocean, below b.Land Under the Ocean 1. square feet 2. cubic yards dredged c.Barrier Beach Indicate size under Coastal Beaches and/or Coastal Dunes below d.Coastal Beaches 1. square feet 2. cubic yards beach nourishment e.Coastal Dunes 1. square feet 2. cubic yards dune nourishment Size of Proposed Alteration Proposed Replacement (if any) f.Coastal Banks 1. linear feet g.Rocky Intertidal Shores 1. square feet h. Salt Marshes 1. square feet 2. sq ft restoration, rehab., creation i.Land Under Salt Ponds 1. square feet 2. cubic yards dredged j. Land Containing Shellfish 1. square feet k.Fish Runs Indicate size under Coastal Banks, inland Bank, Land Under the Ocean, and/or inland Land Under Waterbodies and Waterways, above 1. cubic yards dredged l.Land Subject to Coastal Storm Flowage 1. square feet 4. Restoration/Enhancement If the project is for the purpose of restoring or enhancing a wetland resource area in addition to the square footage that has been entered in Section B.2.b or B.3.h above, please enter the additional amount here. a. square feet of BVW b. square feet of Salt Marsh 5. Project Involves Stream Crossings a. number of new stream crossings b. number of replacement stream crossings wpaform3.doc • rev. 12/4/2023 Page 5 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town C.Other Applicable Standards and Requirements This is a proposal for an Ecological Restoration Limited Project. Skip Section C and complete Appendix A: Ecological Restoration Limited Project Checklists – Required Actions (310 CMR 10.11). Streamlined Massachusetts Endangered Species Act/Wetlands Protection Act Review 1.Is any portion of the proposed project located in Estimated Habitat of Rare Wildlife as indicated on the most recent Estimated Habitat Map of State-Listed Rare Wetland Wildlife published by the Natural Heritage and Endangered Species Program (NHESP)? To view habitat maps, see the Massachusetts Natural Heritage Atlas or go to http://maps.massgis.state.ma.us/PRI_EST_HAB/viewer.htm. a. Yes No If yes, include proof of mailing or hand delivery of NOI to: Natural Heritage and Endangered Species Program Division of Fisheries and Wildlife 1 Rabbit Hill Road Westborough, MA 01581 b. Date of map If yes, the project is also subject to Massachusetts Endangered Species Act (MESA) review (321 CMR 10.18). To qualify for a streamlined, 30-day, MESA/Wetlands Protection Act review, please complete Section C.1.c, and include requested materials with this Notice of Intent (NOI); OR complete Section C.2.f, if applicable. If MESA supplemental information is not included with the NOI, by completing Section 1 of this form, the NHESP will require a separate MESA filing which may take up to 90 days to review (unless noted exceptions in Section 2 apply, see below). c.Submit Supplemental Information for Endangered Species Review∗ 1. Percentage/acreage of property to be altered: (a)within wetland Resource Area percentage/acreage (b)outside Resource Area percentage/acreage 2. Assessor’s Map or right-of-way plan of site 2. Project plans for entire project site, including wetland resource areas and areas outside of wetlands jurisdiction, showing existing and proposed conditions, existing and proposed tree/vegetation clearing line, and clearly demarcated limits of work ∗∗ (a) Project description (including description of impacts outside of wetland resource area & buffer zone) (b)Photographs representative of the site ∗ Some projects not in Estimated Habitat may be located in Priority Habitat, and require NHESP review (see https://www.mass.gov/ma- endangered-species-act-mesa-regulatory-review). Priority Habitat includes habitat for state-listed plants and strictly upland species not protected by the Wetlands Protection Act. ∗∗ MESA projects may not be segmented (321 CMR 10.16). The applicant must disclose full development plans even if such plans are not required as part of the Notice of Intent process. wpaform3.doc • rev. 12/4/2023 Page 6 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town C. Other Applicable Standards and Requirements (cont’d) (c) MESA filing fee (fee information available at https://www.mass.gov/how-to/how-to-file-for- a-mesa-project-review). Make check payable to “Commonwealth of Massachusetts - NHESP” and mail to NHESP at above address Projects altering 10 or more acres of land, also submit: (d) Vegetation cover type map of site (e) Project plans showing Priority & Estimated Habitat boundaries (f) OR Check One of the Following 1. Project is exempt from MESA review. Attach applicant letter indicating which MESA exemption applies. (See 321 CMR 10.14, https://www.mass.gov/service-details/exemptions-from-review-for-projectsactivities-in- priority-habitat; the NOI must still be sent to NHESP if the project is within estimated habitat pursuant to 310 CMR 10.37 and 10.59.) 2. Separate MESA review ongoing. a. NHESP Tracking # b. Date submitted to NHESP 3. Separate MESA review completed. Include copy of NHESP “no Take” determination or valid Conservation & Management Permit with approved plan. 3. For coastal projects only, is any portion of the proposed project located below the mean high water line or in a fish run? a. Not applicable – project is in inland resource area only b. Yes No If yes, include proof of mailing, hand delivery, or electronic delivery of NOI to either: South Shore - Bourne to Rhode Island border, and the Cape & Islands: Division of Marine Fisheries - Southeast Marine Fisheries Station Attn: Environmental Reviewer 836 South Rodney French Blvd. New Bedford, MA 02744 Email: dmf.envreview-south@mass.gov North Shore - Plymouth to New Hampshire border: Division of Marine Fisheries - North Shore Office Attn: Environmental Reviewer 30 Emerson Avenue Gloucester, MA 01930 Email: dmf.envreview-north@mass.gov Also if yes, the project may require a Chapter 91 license. For coastal towns in the Northeast Region, please contact MassDEP’s Boston Office. For coastal towns in the Southeast Region, please contact MassDEP’s Southeast Regional Office. c. Is this an aquaculture project? d. Yes No If yes, include a copy of the Division of Marine Fisheries Certification Letter (M.G.L. c. 130, § 57). wpaform3.doc • rev. 12/4/2023 Page 7 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town C. Other Applicable Standards and Requirements (cont’d) Online Users: Include your document transaction number (provided on your receipt page) with all supplementary information you submit to the Department. 4. Is any portion of the proposed project within an Area of Critical Environmental Concern (ACEC)? a. Yes No If yes, provide name of ACEC (see instructions to WPA Form 3 or MassDEP Website for ACEC locations). Note: electronic filers click on Website. b. ACEC 5. Is any portion of the proposed project within an area designated as an Outstanding Resource Water (ORW) as designated in the Massachusetts Surface Water Quality Standards, 314 CMR 4.00? a. Yes No 6. Is any portion of the site subject to a Wetlands Restriction Order under the Inland Wetlands Restriction Act (M.G.L. c. 131, § 40A) or the Coastal Wetlands Restriction Act (M.G.L. c. 130, § 105)? a. Yes No 7. Is this project subject to provisions of the MassDEP Stormwater Management Standards? a. Yes. Attach a copy of the Stormwater Report as required by the Stormwater Management Standards per 310 CMR 10.05(6)(k)-(q) and check if: 1. Applying for Low Impact Development (LID) site design credits (as described in Stormwater Management Handbook Vol. 2, Chapter 3) 2. A portion of the site constitutes redevelopment 3. Proprietary BMPs are included in the Stormwater Management System. b. No. Check why the project is exempt: 1. Single-family house 2. Emergency road repair 3. Small Residential Subdivision (less than or equal to 4 single-family houses or less than or equal to 4 units in multi-family housing project) with no discharge to Critical Areas. D. Additional Information This is a proposal for an Ecological Restoration Limited Project. Skip Section D and complete Appendix A: Ecological Restoration Notice of Intent – Minimum Required Documents (310 CMR 10.12). Applicants must include the following with this Notice of Intent (NOI). See instructions for details. Online Users: Attach the document transaction number (provided on your receipt page) for any of the following information you submit to the Department. 1. USGS or other map of the area (along with a narrative description, if necessary) containing sufficient information for the Conservation Commission and the Department to locate the site. (Electronic filers may omit this item.) 2. Plans identifying the location of proposed activities (including activities proposed to serve as a Bordering Vegetated Wetland [BVW] replication area or other mitigating measure) relative to the boundaries of each affected resource area. wpaform3.doc • rev. 12/4/2023 Page 8 of 9 4 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 3 – Notice of Intent Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by MassDEP: MassDEP File Number Document Transaction Number City/Town D. Additional Information (cont’d) 3. Identify the method for BVW and other resource area boundary delineations (MassDEP BVW Field Data Form(s), Determination of Applicability, Order of Resource Area Delineation, etc.), and attach documentation of the methodology. 4. List the titles and dates for all plans and other materials submitted with this NOI. a. Plan Title b. Prepared By c. Signed and Stamped by d. Final Revision Date e. Scale f. Additional Plan or Document Title g. Date 5. If there is more than one property owner, please attach a list of these property owners not listed on this form. 6. Attach proof of mailing for Natural Heritage and Endangered Species Program, if needed. 7. Attach proof of mailing for Massachusetts Division of Marine Fisheries, if needed. 8. Attach NOI Wetland Fee Transmittal Form 9. Attach Stormwater Report, if needed. E. Fees 1. Fee Exempt: No filing fee shall be assessed for projects of any city, town, county, or district of the Commonwealth, federally recognized Indian tribe housing authority, municipal housing authority, or the Massachusetts Bay Transportation Authority. Applicants must submit the following information (in addition to pages 1 and 2 of the NOI Wetland Fee Transmittal Form) to confirm fee payment: 2. Municipal Check Number 3. Check date 4. State Check Number 5. Check date 6. Payor name on check: First Name 7. Payor name on check: Last Name noifeetf.doc • Wetland Fee Transmittal Form • rev. 10/11 Page 1 of 2 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands NOI Wetland Fee Transmittal Form Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use the return key. A. Applicant Information 1. Location of Project: a. Street Address b. City/Town c. Check number d. Fee amount 2. Applicant Mailing Address: a. First Name b. Last Name c. Organization d. Mailing Address e. City/Town f. State g. Zip Code h. Phone Number i. Fax Number j. Email Address 3. Property Owner (if different): a. First Name b. Last Name c. Organization d. Mailing Address e. City/Town f. State g. Zip Code h. Phone Number i. Fax Number j. Email Address To calculate filing fees, refer to the category fee list and examples in the instructions for filling out WPA Form 3 (Notice of Intent). B. Fees Fee should be calculated using the following process & worksheet. Please see Instructions before filling out worksheet. Step 1/Type of Activity: Describe each type of activity that will occur in wetland resource area and buffer zone. Step 2/Number of Activities: Identify the number of each type of activity. Step 3/Individual Activity Fee: Identify each activity fee from the six project categories listed in the instructions. Step 4/Subtotal Activity Fee: Multiply the number of activities (identified in Step 2) times the fee per category (identified in Step 3) to reach a subtotal fee amount. Note: If any of these activities are in a Riverfront Area in addition to another Resource Area or the Buffer Zone, the fee per activity should be multiplied by 1.5 and then added to the subtotal amount. Step 5/Total Project Fee: Determine the total project fee by adding the subtotal amounts from Step 4. Step 6/Fee Payments: To calculate the state share of the fee, divide the total fee in half and subtract $12.50. To calculate the city/town share of the fee, divide the total fee in half and add $12.50. noifeetf.doc • Wetland Fee Transmittal Form • rev. 10/11 Page 2 of 2 Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands NOI Wetland Fee Transmittal Form Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 B. Fees (continued) Step 1/Type of Activity Step 2/Number of Activities Step 3/Individual Activity Fee Step 4/Subtotal Activity Fee Step 5/Total Project Fee: Step 6/Fee Payments: Total Project Fee: a. Total Fee from Step 5 State share of filing Fee: b. 1/2 Total Fee less $12.50 City/Town share of filling Fee: c. 1/2 Total Fee plus $12.50 C. Submittal Requirements a.) Complete pages 1 and 2 and send with a check or money order for the state share of the fee, payable to the Commonwealth of Massachusetts. Department of Environmental Protection Box 4062 Boston, MA 02211 b.) To the Conservation Commission: Send the Notice of Intent or Abbreviated Notice of Intent; a copy of this form; and the city/town fee payment. To MassDEP Regional Office (see Instructions): Send a copy of the Notice of Intent or Abbreviated Notice of Intent; a copy of this form; and a copy of the state fee payment. (E-filers of Notices of Intent may submit these electronically.) Town of Barnstable NOI Submission Checklist Chap 707/rev. February 2025 Page 1 CHAPTER 707 Regulation Governing Minimum Submission Requirements for a Notice of Intent Application The Barnstable Conservation Commission has adopted the following requirements in order to obtain more consistently complete submission documents necessary for a thorough and efficient review of all Notice of Intent (NOI) applications. Failure to complete any of the items in this checklist may result in your application being denied. Applicant or applicant’s agent should check each box denoting that the task has been completed or in certain instances, like field staking, denoting that the task will be completed. The following submission checklist covers the requirements of Chapter 237, Wetlands Protection, of the Part I General Ordinances of the Code of the Town of Barnstable. This checklist shall be submitted to the Barnstable Conservation Division with the NOI application. 1. Requirements a. The applicant understands, unless they’ve instructed otherwise, they are applying both under the Massachusetts Wetlands Protection Act M.G.L. c.131,§40 and Chapter 237 of the Town of Barnstable General Ordinances. b. Attach a written narrative to the NOI application (WPA Form 3), available at: www.mass.gov/eea/agencies/massdep/service/approvals/wpa-form-3.html describing any project impacts and proposed mitigation as they relate to the following: 1) Any of the interests of Chapter 237 of the General Ordinances and the MassDEP Wetlands Protection Act M.G.L. 131, §40. 2) The performance standards contained in the MassDEP Wetlands Protection Regulations (310 CMR 10.00) 3) Chapter 704: Regulation Governing Activity in the 100-ft. Buffer Zone. 4) Chapter 703: Private Docks and Piers. 5) Any other applicable regulations (310 CMR 10.00 or as promulgated under Chapter 237 of the General Ordinances). c. Enclose proper payment to cover the fee for Chapter 237 filings. Consult current Fee Schedule at www.townofbarnstable.us/Conservation d. Please indicate who is to record the Order of Conditions (check one): Applicant Agent 2. Abutter Notification (See Abutter Notification Regulation, Chapter 706) Town of Barnstable Conservation Commission 230 South Street Hyannis Massachusetts 02601 Office: 508-862-4093 E-mail: conservation@town.barnstable.ma.us Chap 707/rev. February 2025 Page 2 a. Contact the Conservation Division office at (508) 862-4093 regarding the docketing process, or see current schedule of Conservation Hearings and submission deadlines at: www.townofbarnstable.us/Conservation/ b. Provide a copy of the list of abutters within a 100 ft radius of the project parcel. c. Provide a copy of the Assessor’s Map indicating the parcel of the project site and showing the 100 ft radius of the project parcel. d. Provide a copy of the abutter notification letter. Use the form letter provided in our Abutter Notification Regulation (Chapter 706), available on the Conservation Division website. e. Email copies of the green return receipts, from the certified mailings to the abutters, as proof of notification . If any mailings are returned, email a copy of the entire envelope, indicating by postal service stamp the reason for return. You will retain the receipts afterwards, not the Conservation Division. f. I further certify under the penalties of perjury that all abutters were notified of the Notice of Intent Application, pursuant to the requirements of Chapter 237 of the General Ordinances of the Code of the Town of Barnstable. Notice must be made in writing by certified mail to all abutters within 100 ft of the property line of the project location. _______________________________________ Signature of Applicant or Representative Date 3. Field Staking: a. On or before Tuesday, @ 8:30 a.m., one week prior to the scheduled public hearing, have your project staked by a professional engineer or registered land surveyor showing all outside corners of all proposed structures and the continuous proposed “limit of work” line. b. Have a wetland scientist or other qualified professional flag all wetland resource areas on or within 100 ft of the work area. Make sure that the flags are sequentially numbered. c. Provide a project identification stake with bright painted top and applicant name and address, easily visible from the street approaching the site. 4. Legal Advertisement Fees: a. Conservation will submit the legal ad for publication in a local newspaper. The applicant or his/her agent is responsible for payment, by check (payable to the Town of Barnstable), at the hearing or by mail. The cost of the legal ad will be pre-calculated and posted on the hearing agenda prior to the hearing. 5. Minimum Documentation for a Complete Application: a. Provide a completely filled-out (in all parts) NOI application as locally adopted for the Town of Barnstable, including MassDEP Vegetated Wetland Field Data Form. Indicate Assessor’s map and parcel of the project, as well as the street or road address, and pertinent village (i.e., Hyannis, Centerville, Barnstable, etc). b. Provide two (2) original project plans, stamped in blue or red ink (wet stamp). Plans must be signed and dated by a Massachusetts licensed, professional engineer, land surveyor, architect or landscape architect (as applicable), and shall be drawn at a readable scale (1" = 20' preferred). For multi-acre sites, a second site plan, drawn at larger scale showing the entire site, should also be provided. Chap 707/rev. February 2025 Page 3 c. Provide a signed Permission to Access Property, Form PA. The form must be signed by the property Owner, or legal representative and submitted with the NOI. . Form PA is available at www.townofbarnstable.us/Conservation/. d. For projects requiring mitigation plantings under Chapter 704 -3, 704-4, and 704-5, mitigation planting location(s) shall clearly be shown on landscaping planting plan. The planting plan shall include: 1. species (chosen from the Town of Barnstable Conservation Commission approved planting lists), sizes, densities and/or quantities. 2. area calculations in 0’ - 50’ and 50’ – 100’ separately for the amount of mitigation planting required. 3. the amount of mitigation planting proposed. 4. a note or indication stating the area between the proposed plants will either be planted with an appropriate native seed mix or left to naturalize. 5. a note stating mulch may only be used under the dripline of proposed plants. 6. demarcation markers along the landward side of the mitigation planting area. The type of demarcation marker shall be selected from the list approved by the Conservation Commission. e. Provide detailed, written street directions to the locus (site). f. Provide a copy of a U.S.G.S. locus map indicating the general area of the project site. g. Provide a check for the Town of Barnstable portion of the required filing fee. (The portion payable to the Commonwealth, see 7. e. below) h. Provide any other documentation, photographs, architectural renderings or other supporting data prepared by professionals competent in the field which may be relevant to the application. 6. The site plan shall also show: a. All existing and proposed contours at 2-ft. minimum intervals (1-ft. preferred). b. Clear delineation of all existing and proposed structures and features. Building structures must be accurately dimensioned (fixed location) from property lines and wetland resource areas. Plans shall provide sufficient detail to show all potential wetland impacts, mitigation, compensatory areas, engineered structures, utilities, landscaping, etc. within the area of jurisdiction. On complicated sites, existing and proposed conditions must be shown on separate sheets. c. Locus inset map of the site clearly showing its location relative to surrounding public streets. d. All wetland resource area flags by individual flag number (matched to the field) to clearly identify all resource areas on or within 100 feet of the work area. The individual who performed the flagging and date of flagging shall be identified on the plan next to the resource line. e. Section views showing changes in grade, cuts and fills. 7. SUBMISSION OF THE COMPLETED APPLICATION WITH PLANS: a. Email NOI application and all associated materials in PDF format to Kimberly.Cavanaugh@town.barnstable.ma.us AND Edwin.Hoopes@town.barnstable.ma.us Do not include copies of checks. All attachments must be named with the hearing date (year first), type, name, address. Examples 20220301 NOI Smith 21 Main Street or 2022031 NOI Plan Smith 21 Main Street. c. Provide two (2) full NOI applications with folded plans (colored ink stamp) with signature/date to the Town of Barnstable Conservation Division Office for administrative use; Chap 707/rev. February 2025 Page 4 d. Provide seven (7) additional collated copies of the NOI (with folded plans and all pertinent data attached) to the Barnstable Conservation Division Office for distribution to, and review by, Conservation Commission members. Any supplementary documentation for administrative and commission review should be submitted as soon as possible prior to the scheduled public hearing.* e. Mail one (1) copy of the complete NOI with plan(s) to the Massachusetts Department of Environmental Protection (MassDEP) Southeast Regional Office, 20 Riverside Dr., Lakeville, MA 02347. Send MassDEP portion of filing fee to: MA Department of Environmental Protection, Box 4062, Boston, MA 02211. MassDEP also recommends applicants send their Notices of Intent by email to SERO_NOI@mass.gov. f. For roadway construction or repair projects, provid e one electronic copy of the NOI and plans to the Senior Project Manager Special Projects, c/o the Town of Barnstable Department of Public Works, 382 Falmouth Road, Hyannis, MA 02601. g. For coastal piers, dredging, coastal engineering structures or other coastal erosion control projects, provide two hard copies of the NOI and plans to the Shellfish Biologist, c/o Town of Barnstable Natural Resources, 1189 Phinney’s Ln., Centerville, MA 02632. In addition, email a (PDF) version to: 1) shellfishNOI@town.barnstable.ma.us. (Email must be sent the same day as submission to the Conservation Division); and 2) conservationprojects@town.barnstable.ma.us h. Also, for coastal piers, dredging, coastal engineering structures, provide two hard copies of the NOI and plans to the Harbormaster, c/o Town of Barnstable Marine and Environmental Affairs (MEA), 1189 Phinney’s Ln., Centerville, MA 02632. In addition, email a (PDF) version to: 1) harbormaster@town.barnstable.ma.us. (Email must be sent the same day as submission to the Conservation Division); and 2) conservationprojects@town.barnstable.ma.us Note: Please title the file for your NOI project as follows: a. Submission date, b. Last name of applicant, c. Map/parcel of property, e.g., 082316-Smith-076024. *Note: If a revised plan needs to be submitted prior to a hearing, please follow same instructions as 7. b. above (and submit to other entities as may be applicable). Plan revisions must be clearly noted and dated in the revision block. (The same individual who stamped the original plan must also stamp and sign the revised plan). Submitted this day of in the year in accordance with the Town of Barnstable “Regulation Governing Minimum Submission Requirements for a Notice of Intent Application” by: (Print Name) Owner / Applicant Signature Telephone Number Owner’s Authorized Agent Signature Telephone Number Approved: May 28, l997 Revised March 15, 2022 Revised: May 12, 2015 Revised February 5, 2025 Revised: August 23, with minor rev. Sept. 6, 2016 Adopted Mar Property o Applicant’ Project st Barnstabl Applicant’ ACCESS As the Ow the Mas General designate purpose o (Notice o possible, either wee understan to inspect I/we conf Commiss regarding 1. F ap 2. F of pr I have rea ________ Signature ________ Represen rch 15, 2022, effec owner’s name ’s (Represent reet address_ e Assessor’s ’s Contact Ph TO PROPER wner(s) of the sachusetts W Ordinances ed staff are a of reviewing t f Intent or R notice will be ekdays or we nd that if attem t the outside a firm my/our ioners, its ag this applicati rom the subm pproval of the rom the issua f the project a roject. ad the above ___________ e of property ___________ ntative’s sign ctive April 18, 202 P e(s): _______ tative’s) Name ___________ Map & Parce hone Number: RTY PERMIS e above refer Wetlands Prot (Chapter 23 authorized, a the existing c Request for D e provided to t eekends as ne mpts to conta areas of said understandin gent, and its on for the pe mission of the e Notice of Int ance of the O and the final e and I under ____________ y owner ____________ nature C Office: 508- 22. Permission ___________ e(s)________ ____________ el: Map___ : SION renced prope tection Act (M 37), the Bar as a matter o conditions an Determination the applicant ecessary for t act me are un property unde ng the purpo s designated riod as descr e Application tent Request Order(s) of Co inspection by rstand and a __ __ Tow Conserv Hyann -862-4093 to Access P ____________ ___________ ____________ _______ erty, I/we have MGL Ch 131 rnstable Con of law, to ente d the propos ) to the Ba prior to the v the Commiss nsuccessful, t er this applica ose of this d staff, to en ibed below: (Notice of In or Request fo onditions (app y the Conser gree to allow ____ Date ____ Date wn of Ba vation C 230 South nis Massach E-mail: con Property ___________ ___________ ___________ Parcel___ e been advis 1, Section 40 nservation C er the outsid sed work as d arnstable Con visit. Visits wil sion and its ag the Commiss ation. permission a nter the outs ntent or Requ or Determinat proval for No rvation staff to w inspection ___________ e signed ___________ e signed arnstab Commi Street husetts 0260 nservation@to ___________ ____________ ___________ _________ sed that unde 0) and the To ommission, e areas of th described in nservation Co l occur during gent to exam sioner or its a and I/we gra side areas o uest for Deter tion; and tice of Intent) o confirm the s as describ ________ ________ ble ission 01 own.barnstab ___________ ___________ ____________ er the provisio own of Barns its Agents o he property fo my/our applic ommission. W g daylight hou ine said prop agent may pro ant permissi of my/our pro rmination) un ) to the comp e completion bed. ble.ma.us Form _____ ____ _____ ons of stable or its or the cation Where urs on perty. I oceed on to operty ntil the pletion of the m PA P r oject Narrative Notice of Intent | 1-1 SECTION 1 | Project Background This section provides an overview of the proposed Craigville Beach Road Bridge Repair Project relative to the Barnstable Conservation Commission’s jurisdiction, and a summary of other required and/or anticipated permits. 1.1 Project Location The project area consists of the Craigville Beach Road Bridge its associated embankments, and adjacent jurisdictional resource areas and is located in the Village of Centerville, in the Town of Barnstable, Massachusetts. The bridge conveys Craigville Beach Road, a two -lane urban minor arterial roadway, over the Centerville River. This roadway provides access to Craigville Beach, Covell’s Beach, residential neighborhoods, and businesses. While a bridge has existed in this area since the late 1800’s, MassDOT records indicate that the existing bridge was most recently reconstructed in 2002 and has not undergone rehabilitation since that date. Bridge deflciencies have accumulated since the 2002 reconstruction, as noted in the most recent MassDOT inspection report and as observed during Tighe & Bond’s comprehensive visual inspection. Land use within the general vicinity of the project site consists of the Centerville River to the east and west of the bridge. Res idential properties and salt marsh associated with the Centerville River are present to the north. Residential properties are also present to the south of the bridge, as well as Craigville Beach, a public beach with frontage along Centerville Harbor. GIS flgures showing the project location are provided in Appendix A and representative site photographs are provided in Appendix B. 1.2 Project Need Tighe & Bond conducted a comprehensive on-site visual inspection of the Craigville Beach Road Bridge in November 2022 to review existing conditions and to identify speciflc deflciencies that warrant repair. This inspection, in conjunction with the most recent Massachusetts Department of Transportation (MassDOT) inspection report (dated July 2024), indicated the need for repairs due to the presence of several deflciencies with varying severity levels. These inspections identifled multiple issues in need of repair, including structural deflciencies (e.g. cracks, spalling), scour, vegetation overgrowth, failed bank channel protection, guard rail damage, and sidewalk deflciencies. The proposed bridge repairs are intended to address the reported deflciencies to the bridge itself, its embankment, and the associated Craigville Beach Road roadway. 1.3 MAWPA and Barnstable Conservation Commission Jurisdiction The proposed project will involve dredging and the placement of permanent flll in areas subject to jurisdiction under the Massachusetts Wetlands Protection Act (MAWPA; M.G.L. c. 131 § 40), the Town of Barnstable Wetlands Protection Bylaw (Chapter 237), and their implementing regulations to reestablish the 2002 bridge footprint. These areas include Salt Marsh, Coastal Bank, Barrier Beach, Land under the Ocean, Fish Run, Land Subject to Coastal Storm Flowage, the 200-foot Riverfront Area, and the 100-foot Buffer Zone. Section 1 | Project Background Notice of Intent | 1-2 1.4 Summary of Anticipated Permits Table 1-1 contains a list of federal, state, and municipal agencies from which permits or other actions are or may be required. TABLE 1-1 Summary of permits, reviews, and approvals required by Municipal, State, and Federal Agencies Federal U.S. Coast Guard Bridge Permit Advance Approval received April 10, 2026 Offlce of Coastal Zone Management Federal Consistency Review Coordination Pending U.S. Army Corps of Engineers Pre-Construction Notiflcation Submission Pending State MA Executive Offlce of Energy and Environmental Affairs MA Environmental Policy Act Certiflcate Environmental Notiflcation Form submitted April 29, 2026 MA Department of Environmental Protection Chapter 91 Minor Project Notiflcation Notiflcation submitted April 9, 2026 MA Department of Environmental Protection Section 401 Water Quality Certiflcation Application submitted June 26, 2026 Municipal Barnstable Conservation Commission Order of Conditions NOI Submitted July 21, 2026 Agency Permit, Review, or Approval Status Section 2 | Existing Environment Notice of Intent | 2-3 SECTION 2 | Existing Environment This section provides a site description and resource area characterization within the vicinity of the proposed project. Wetland resource areas and land use in the general vicinity were determined based on direct observations made during site visits and a review of information available through the Massachusetts Geographic Information System (MassGIS) MassMapper. Results from a desktop review of the project’s potential to affect Rare, Threatened, and Endangered (RTE) Species and Historic Properties is also included below. 2.1 Wetland and Watercourse Delineation 2.1.1 Methodology of Resource Area Investigations On June 2, 2025, a Tighe & Bond wetland scientist conducted wetland resource area fleld investigations in general accordance with the Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Northcentral and Northeast Region (Version 2.0, U.S. Army Corps of Engineers, January 2012), Delineating Bordering Vegetated Wetlands Under the Massachusetts Wetlands Protection Act (MassDEP, 2022), 310 CMR 10.55(2)(c)(1), and the Town of Barnstable Wetlands Protection Bylaw (Chapter 237). Boundaries of jurisdictional resource areas within the project area were delineated using sequentially numbered day-glow pink fiagging tape. Each fiag was located by a surveyor at a later date and incorporated into the existing conditions base map. Wetland resource areas were named based on the wetland system n umber and alphabetical letter in the order in which they were observed, i.e., “1A -1” refers to the flrst resource area delineated within wetland system 1. Resource area boundaries are shown on the Project Drawings in Appendix C. 2.1.2 Jurisdictional Wetland Resource Areas SALT MARSH Per 310 CMR 10.32(2), Salt Marsh is deflned as: “… a coastal wetland that extends landward up to the highest high tide line, that is, the highest spring tide of the year, and is characterized by plants that are well adapted to or prefer living in, saline soils...” Four areas of salt marsh were identifled within the project site on both the north and south sides of the bridge. These were demarcated in the fleld with fiag series 1A (northwest corner), 2A (southwest corner), 3A (southeast corner), and 4A (northeast corner). Vegetation observed in these areas included smooth cord grass (Spartina alternifiora; OBL), maritime marsh-elder, seaside goldenrod (Solidago sempervirens; FACW), and triangle orache (Atriplex prostrata; FAC). A summary of delineated salt marsh by fiag series is presented in Table 2-1. TABLE 2-1 Summary of Wetland Resource Areas by Flag Series Wetland System ID Flag Numbers Resource Area Type 1A 1A-1 to 1A-10 Salt Marsh 2A 2A-1 to 2A-7 Salt Marsh 3A 3A-1 to 3A-6 Salt Marsh 4A 4A-1 to 4A-8 Salt Marsh Section 2 | Existing Environment Notice of Intent | 2-4 COASTAL BANK In accordance with 310 CMR 10.30(2), Coastal Bank is deflned as: “… the seaward face or side of any elevated landform, other than a coastal dune, which lies at the landward edge of a coastal beach, land subject to tidal action, or other wetland .” Chapter 237, the Barnstable Wetlands Protection By-Law, deflnes Coastal Bank as: “…the flrst signiflcant break in slope beyond the one-hundred-year storm elevation on a seaward face or elevated landform, other than a coastal dune, which lies at the landward edge of a coastal beach, land subject to tidal action, or other coastal wetland. The slope of the bank must be greater than 18% and serve to contain storm fiowage, rather than being inundated by it, or function as a sediment source.” Coastal Bank in this area consists of an armored, structural bank and is comprised of the rip rap embankments on the north and south sides of the bridge and generally follows the edge of the roadway. Delineated coastal banks serve as a manmade vertical buffer to storm waters, as placed rip rap defiects and absorbs wave energy that could otherwise erode the bridge embankments. Common vegetation observed along the Coastal Banks included Norway maple (Acer platanoides; UPL), pitch pine (Pinus rigida; FACU), black locust (Robinia pseudoacacia; FACU), white oak (Quercus alba; FACU), black cherry (Prunus serotina; FACU), scarlet oak (Quercus coccinea), sassafras (Sassafras albidum; FACU), poison ivy (Toxicodendron radicans; FAC), honeysuckle (Lonicera sp.), orchard grass (Dactylis glomerata; FACU), scotch broom (Cytisus scoparius), eastern gamagrass (Tripsacum dactyloides; FAC), Virginia rose (Rosa virginiana; FAC), switch panicgrass (Panicum virgatum; FAC), Oriental bittersweet (Celastrus orbiculatus; UPL), sweet-fern (Comptonia peregrina), Virigina creeper (Parthenocissus quinquefolia; FACU), bayberry (Morella caroliniensis; FAC), cypress surge (Euphorbia cyparissias), winterberry (Ilex verticillata; FACW), greenbriar (Smilax glauca; FACU), mugwort (Artemisia vulgaris; UPL), and maritime marsh-elder (Iva frutescens, FACW). LAND UNDER THE OCEAN In accordance with 310 CMR 10.25(2), LUO is deflned as: “…land extending for the mean low water line seaward to the boundary of the municipality’s jurisdiction and includes land under estuaries.” Within the Project Site, Land Under the Ocean (LUO) is associated with the Centerville River. LUO extends seaward from the Mean Low Water (MLW) line. At the Project Site, MLW is at elevation -1.91 feet NAVD83, as determined by survey data collected in May 2025. LUO located south of the bridge (downstream) is mapped as a shellflsh suitability area for soft-shell clam (Mya arenaria) and quahog clam (Mercenaria mercenaria). COASTAL DUNE In accordance with 310 CMR 10.28(2), Coastal Dune is deflned as: “…any natural hill, mound o ridge of sediment landward of a coastal beach deposited by wind action or storm overwash. Coastal dune also means sediment deposited by artiflcial means and serving the purpose of storm damage prevention or fiood control.” The area to the south of the Craigville Beach Road Bridge has been heavily modifled and primarily consists of maintained lawn and residential properties. However, these are underlain by windborne sediment characteristic of Coastal Dunes. The Natural Resource Conservation Service (NRCS) Web Soil Survey (WSS) also maps this area as “Dune Land”. As such, this area is classifled as Coastal Dune. Section 2 | Existing Environment Notice of Intent | 2-5 BARRIER BEACH In accordance with 310 CMR 10.29(2), Barrier Beach is deflned as: “…a narrow low-lying strip of land generally consisting of coastal beaches and coastal dunes extending roughly parallel to the trend of the coast. It is separated from the mainland by a narrow body of fresh, brackish or saline water or a marsh system. A barrier beach may be joined to the mainland at one or both ends.” Land to the south of the Craigville Beach Road Bridge is classifled as Barrier Beach as it consists of Coastal Dune, is separated from the mainland by the Centerville River and is bound by the Atlantic Ocean to the south. Barrier Beach present within the vicinity of the project site was observed to be heavily modifled and consists primarily of maintained lawn and single-family housing. FISH RUN In accordance with 310 CMR 10.35(2), Fish Run is deflned as: “…that area within estuaries, ponds, streams, creeks, rivers, lakes or coastal waters, which is a spawning or feeding ground or passageway for anadromous or catadromous flsh and which is identifled by the Division of Marine Fisheries or has been mapped on the Coastal Atlas of the Coastal Zone Management Program…” According to the Diadromous Fish Migratory Habitat Layer in MassMapper, the site is classifled as Migratory Habitat for alewife (Alosa pseuodharengus), blueback herring (Alosa aestivalis), and American eel (Anguilla rostrata). As such, the Centerville River is classifled as Fish Run. LAND CONTAINING SHELLFISH In accordance with 310 CMR 10.34(2), Land Containing Shellflsh is deflned as: “…land under the ocean, tidal fiats, rocky intertidal shores, salt marshes and land under salt ponds when any such land contains shellflsh.” According to the Shellflsh Suitability Layer in MassMapper, the western embankment to the Craigville Beach Road Bridge, and land beneath the bridge are classifled as suitable habitat for quahog (Mercenaria mercenaria) and soft-shell calm (Mya arenaria). LAND SUBJECT TO COASTAL STORM FLOWAGE In accordance with 310 CMR 10.04, LSCSF is deflned as: “…land subject to any inundation caused by coastal storms up to and including that caused by the 100 - year storm, surge of record or storm of record, whichever is greater.” According to the FEMA Flood Insurance Rate Map (FIRM; Panel No. 25001C0563J, effective July 16, 2014), the Project is located within the limits of the 100-year fioodzone (Special Flood Hazard Area, Zone AE). According to FEMA, the base fiood elevation (BFE) at the site is 13 feet (NAVD88). The entirety of the Project falls within LSCSF. A FEMA FIRMette of the project area is provided in Attachment A. Section 2 | Existing Environment Notice of Intent | 2-6 RIVERFRONT AREA In accordance with 310 CMR 10.58(2)(a), RFA is deflned as: “…the area of land between a river’s mean annual high water line and a parallel line measured horizontally… (2)(a)2.c in tidal rivers, the mean annual high-water line is coincident with the mean high water line determined under 310 CMR 10.23.” 310 CMR 10.23: “Mean High Water Line means the line where the arithmetic mean of the high water heights observed over a speciflc 19-year metonic cycle (the National Tidal Datum Epoch) meets the shore and shall be determined using hydrographic survey data of the National Ocean Survey of the U.S. department of Commerce.” Per these deflnitions, RFA present on site extends 200 -feet horizontally from the Mean High Water line, which is located at elevation +1.18 feet NAVD83. RFA present within the project area includes the Craigville Beach Road Bridge, and the associated embankments and roadway. 100-FOOT BUFFER ZONE In accordance with 310 CMR 10.02(2)(b), Salt Marsh and Coastal Bank are afforded a 100 -Foot Buffer Zone. The Buffer Zone present within the project area consists of Craigville Beach Road Bridge, and the associated embankments and roadway. 2.2 Rare Species 2.2.1 State-Listed Species The Massachusetts Natural Heritage and Endangered Species Program (NHESP) Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. 2.3 Historic and Archaeological Resources In accordance with Section 106 of the National Historic Preservation Act (NHPA), a Project Notiflcation Form (PNF) was submitted to the Massachusetts Historical Commission (MHC), Massachusetts Bureau of Underwater Archaeological Resources (MABUAR), and relevant Tribal Historic Preservation Offlcers (THPOs) on March 14, 2025. In their response dated April 27, 2025, MHC determined that the project was unlikely to affect signiflcant historic or archaeological resources. No response from the MABUAR or the THPOs has been received to date. A copy of the PNF and related correspondence is provided in Appendix F. Section 3 | Project Description Notice of Intent | 3-7 SECTION 3 | Project Description 3.1 Bridge Repair Activities The proposed project will involve repairs to the existing Craigville Beach Road Bridge to address various deflciencies and extend the useful life of the structure. The limit of work (LOW) will be an approximately 25,605 sf area consisting of the roadway, roadway shoulders, salt marsh, LUO/Fish Run, Land Containing Shellflsh, and Coastal Bank (rip rap slopes). The proposed activities include repairs to the bridge, embankment restoration, roadway improvements, and vegetation management. These activities are described in greater detail in the following sections. 3.1.1 Bridge Work Structural deflciencies of the bridge will be addressed including cracks and spalling in the retaining walls, east and west abutments, and wingwalls. Cracks will be improved via patching with cementitious mortar. These repairs will require water control measures to create a dry work area to allow for crack sealant to cure. Additionally, bridge joints will be sealed with elastomeric sealant, and abutments and wingwalls will be power washed and painted. Repairs to the existing bridge railing include replacement of deteriorated components and cleaning and painting of all railing elements. 3.1.2 Embankment Work Bridge embankments will be stabilized, and areas of scour will be repaired via regrading and the placement of rip rap underlain by new geotextile fabric for permanent erosion control. Water control measures will be necessary to allow for new geotextile fabric to be placed, subgrades to be compacted, dredging and new flll material to be placed, and channel protection measures to be installed. Embankment work will require permanent impacts, including dredging and placement of flll (e.g., rip rap), to salt marsh and LUO. It should be noted that the proposed dredging and placement of rip rap in resource areas is being proposed to reestablish the historic footprint of the bridge, which has become displaced over time since 2002. The loss of rip rap in these areas due to scour has led to the encroachment of regulated resource areas into the historic bridge footprint. According to MassDOT design speciflcations, the minimum preferred slope for rip rap embankments is 2:1. Given site constraints, impacts to salt marsh are unavoidable to meet this standard. Steeper slopes are generally less stable and would not meet the project goals of repairing existing structural deflciencies. As such, rip rap impacts to salt marsh have been avoided and minimized to the greatest extent feasible, given site and design constraints. 3.1.3 Roadway Work As part of the proposed activities, roadway improvements will be completed, including guardrail and transition rail repairs and replacements. Sidewalk settlement will be repaired with asphalt patches . 3.1.4 Vegetation Work Minor tree clearing is proposed; a total of flve (5) small eastern red cedar (Juniperus virginiana, FACU) trees will be removed from the existing rip rap slopes on the north and south sides of the bridge. Stump cores will also be removed, and voids will be fllled with rip rap. Additionally, vegetation growth will be removed from along the sidewalk and curbs. Section 3 | Project Description Notice of Intent | 3-8 3.2 Anticipated Construction Sequence Proposed activities are shown in detail on the Project Drawings provided in Appendix C and are summarized in sequence below. While the exact means and methods of construction are left to the discretion of the contractor, it can generally be assumed, based on Tighe & Bond’s experience with projects of a similar scope, that the proposed activities will occur in the following sequence. • Notify pertinent regulatory agencies of the construction schedule. • Mobilize to the site and install temporary sediment and erosion control measures around the perimeter of work. • Schedule and conduct site walks with pertinent regulatory agencies to inspect construction -phase BMPs. • Install temporary cofferdams on the up- and downstream sides of the bridge to isolate the work area. • Repair cracks and spalling in retaining walls, east and west abutments, and wingwalls • Install elastomeric sealing in bridge joints • Construct embankment stabilization and scour protection for permanent erosion control through placement of geotextile fabric and rip rap. • Remove trees on existing rip rap slopes and complete general cleaning and repainting of bridge components. • Remove cofferdams and restore the area to pre-existing conditions. • Complete roadway work, including guardrail and transition rail repairs/replacement, asphalt sidewalk patches, sidewalk and curb vegetation management, and bridge railing repairs. • Restore and stabilize all disturbed areas. • Remove erosion control barriers once site has stabilized and regulatory agencies have authorized the actions. 3.3 Construction Period Protective Measures Erosion control barriers, temporary cofferdams, and other construction -phase Best Management Practices (BMPs) will be installed for construction. Descriptions of these measures are provided in the following sections. 3.3.1 Erosion Control Barriers Proposed erosion, sedimentation, and pollution controls are shown on the Project Drawings in Appendix C. The erosion control barriers will be placed to restrict the contractor(s) to the areas necessary to conduct the work and will deflne the limits of work. Erosion control barriers will consist of compost fllter tubes (or equivalent) and silt fence staked in place between the proposed areas of disturbanc e and jurisdictional wetland resource areas to minimize the potential for migration of disturbed soil. The contractor(s) will be required to maintain the barriers in good working order and to repair and replace sections, as necessary. These barriers will b e inspected daily during construction and until disturbed soils have become stabilized. The contractor will be required to maintain a reserve supply of erosion control barriers on site to make repairs, as necessary. Protective measures will be inspected after signiflcant precipitation events. Erosion and sedimentation controls will be installed prior to construction and will remain in place until permanent restoration features are implemented and the site is stabilized. Section 3 | Project Description Notice of Intent | 3-9 3.3.2 Water Control Measures In order to complete the proposed bridge repairs (e.g., sealing of cracks) and embankment improvements/scour protection, water control measures will be necessary to allow for repairs to be conducted in-the-dry. Cofferdams will be installed upstream and downstream at the corners of the bridge to create an isolated (i.e., dry) work area. The cofferdams may be constructed of sandbags, jersey barriers, water-fllled barriers, or equivalent. Turbidity curtains will also be installed along the upstream and downstream limits of work to minimize migration of sediment outside of the work area. The selected cofferdam materials are subject to the discretion and design of the contractor; however, the use of unconsolidated flll material will be strictly prohibited, and cofferdams will be located within the limits shown on the Project Drawings. The cofferdams will separate the work area from water fiow which will protect the tidal stream from construction debris and sedimentation and reduce the pumping and discharge treatment required for construction. All work will be performed in-the-dry to protect wetland resource areas. The location of cofferdams is shown on the Project Drawings. 3.3.3 Dewatering If necessary, sediment-laden water that collects in work areas will be pumped using a discharge hose into a fllter bag underlain by a fllter fabric mat and surrounded with straw bales in a stabilized area. All dewatering structures will be placed as far away from wetland resources as possible. Filter bags used during construction will be bundled and removed for proper disposal. Dewatering of excavated material will be conducted in a manner that does not introduce potential contaminants (e.g., flnes) of excavated material into new areas (where excavated material was not generated). 3.3.4 Soil and Stockpile Management Material stockpiles will be placed as far away from wetland resource areas as possible and will be protected with a perimeter barrier of straw bales and silt fence. Stockpiles will be stabilized or covered if inactive for 30 days or more. 3.3.5 Sediment Management Sediment to be dredged for embankment/scour improvements will be hauled away from the site and disposed of at a permitted facility. 3.3.6 Construction Period Access and Staging Access for construction will be from the Craigville Beach Roadway Right-of-Way (ROW) and adjacent areas. If necessary to complete construction, the selected contractor may access portions of the bridge via boat/barge in the river. A staging area for construction materials will be located along the ROW, or at the Craigville Beach Parking Lot, located approximately 1,000 feet south of the site. All materials will be staged as far from jurisdictional resource areas to the extent practicable and will be surroun ded by erosion control barriers. The exact location of the staging area(s) will be left to the discretion of the contractor. Section 3 | Project Description Notice of Intent | 3-10 3.3.7 Other Protective Measures The following general measures will be employed to minimize impacts to jurisdictional wetland resources: • Protective measures will be inspected weekly during construction and after signiflcant precipitation events and repaired, as necessary. • Water control systems will be designed to handle typical fiows and fiows from small precipitation events. The Contractor will be required to prepare a fiood contingency plan with procedures for monitoring weather forecasts and preparing the site for fioodi ng. • The use of products containing hay and plastic or nylon netting is strictly prohibited. • Use of air quality and dust control measures will be implemented, as necessary. This include wetting agents, truck bed covers, use of ultra-low sulfur diesel fuel, limitation on idling, vehicle anti-tracking pads, and street cleaning. Construction equipment will be refueled as far away from jurisdictional resource areas as practicable. 3.4 Post-Construction Site Restoration Following the completion of construction, all disturbed upland areas along the side of the roadway will be restored in-kind with loam and seed. Resource areas temporarily impacted by the bridge repair activities will be restored to pre-existing conditions to the greatest extent practicable. 3.5 Mitigation Measures The project will incorporate measures to avoid and/or minimize adverse environmental impacts to the greatest extent practicable. These measures are commensurate with the size and scope of the proposed work. General construction-phase measures will be implemented to the extent practicable to mitigate construction -related, temporary impacts. Project impacts have been minimized through construction -period BMPs and the limiting of proposed disturbance only to areas necessary for project completion. Mitigation measures for other, unavoidable impacts will be determined based on consultations with regulatory agencies as the project advances through the permitting process. The project is not anticipated to have long-term adverse impacts to the environment. Ongoing inspections and maintenance of the bridge will continue for the duration of the structure’s useful life. Section 4 | Alternatives Analysis Notice of Intent | 4-11 SECTION 4 | Alternatives Analysis 4.1 Alternatives Considered The project is proposed to repair and improve the existing Craigville Beach Road Bridge over Centerville River. As such, there is no alternative location for proposed work. The following sections discuss alternatives considered for the proposed project and an o verview of the impacts and beneflts of each. 4.1.1 Alternative 1 – No Action The “No Action” alternative would consist of making no improvements to the existing bridge on Craigville Beach Road over the Centerville River. This option would not allow the Town to improve the existing structural deflciencies or address scour. This risks further degradation and potential bridge failure, which has signiflcant public safety and environmental impact concerns. As such, the alternative of “No Action” is not feasible. 4.1.2 Alternative 2 – Bridge Repairs (Preferred Alternative) The preferred alternative as proposed involves repairs to the structural deflciencies by a comprehensive bridge assessment. The repairs will address localized issues and extend the useful life of the bridge to protect public safety and the environment. This alternative would result in the least amount of impact to the environment, the least cost, and would achieve desired project goals to maintain critical transportation infrastructure. 4.1.3 Alternative 3 – Bridge Rehabilitation (Major Reconstruction) This alternative consists of major bridge reconstruction to address the existing deflciencies observed in the bridge assessment report. This would generally include replacement of speciflc bridge features rather than localized repairs or full bridge replac ement. This alternative would result in greater unnecessary impacts to the environment and would be more costly to achieve the project goal of maintaining the bridge infrastructure in good working order. For these reasons, Alternative 3 is not preferred. 4.1.4 Alternative 4 – Bridge Replacement Alternative 4 consists of a full bridge replacement, which could include upgrades to the bridge span size and allow for improved tidal fiow/reduction of tidal restrictions. This alternative would result in the greatest environmental impacts to the surrounding area and would be the costliest option. Additionally, the bridge is not in need of repairs signiflcant enough to warrant a full bridge replacement. Ultimately, this alternative is not feasible due to resource area impacts, design needs, and available budget for infrastructure improvements. Section 4 | Alternatives Analysis Notice of Intent | 4-12 4.2 Alternatives Impacts and Benefits Comparison. A summary of each alternative’s impacts and beneflts is provided in Table 4-1, below. TABLE 4-1 Alternatives Analysis Summary Table Factor Evaluated Alternative 1 – No Action Alternative 2 – Bridge Repairs (Preferred Alternative) Alternative 3 – Bridge Rehabilitation (Major Reconstruction) Alternative 4 – Bridge Replacement Resource Area Impacts No construction period impacts. The preferred alternative would result in the least impact to resource areas (aside from “No Action”) . Greater construction- period impacts than the preferred alternative, but less than Alternative 4. This would have the greatest impact to resource areas among the considered alternatives. Design Life of the Project N/A – however, the existing structure would continue to deteriorate. Design life improved from existing conditions but less than other alternatives. Design life is greater compared to localized repairs as specific bridge components would be replaced. Longest design life of the considered alternatives as the bridge would be fully replaced with a new structure. Project Cost N/A – however, costs incurred would be signiflcant in the event of a bridge failure. $ $$ $$$ Project Resiliency N/A – however, no action would fail to address resiliency of the structure to coastal storm damage. Improves bridge resiliency against coastal storms. Improves bridge resiliency against coastal storms. Improves bridge resiliency against coastal storms Construction Considerations N/A Least complex construction than other alternatives and less temporary disturbance to transportation. Greater construction complexity than the preferred alternative and greater temporary impact to transportation. Greatest construction complexity and temporary impacts to transportation. Construction Duration N/A Shortest duration Medium length duration Longest duration Section 4 | Alternatives Analysis Notice of Intent | 4-13 Factor Evaluated Alternative 1 – No Action Alternative 2 – Bridge Repairs (Preferred Alternative) Alternative 3 – Bridge Rehabilitation (Major Reconstruction) Alternative 4 – Bridge Replacement Impacts to Abutters and Neighborhood N/A – however, no action would fail to address existing public safety issues and fail to provide protection from future safety issues in the event of a bridge failure. Least impact to abutters and surrounding areas due to shorter construction time period and less complex work. Similar impact to abutters and surrounding area as preferred alternative, but potentially greater temporary impact to transportation. Greatest impact to abutters and surrounding areas due to longest construction time, work complexity, temporary transportation impacts, and potential downstream and/or upstream effects. Operations and Maintenance Ongoing inventory and maintenance of Town infrastructure Bridge would be maintained via the existing operations and maintenance plan by the Town. Bridge would be maintained via the existing operations and maintenance plan by the Town. Bridge would be maintained via a new/updated operations and maintenance plan by the Town. Permitting Complexity N/A Least complex permitting pathway as the work is limited to in-kind repairs. Medium permitting complexity as work is generally in-kind replacements/rehabili tation but greater impacts to resource areas than repairs. Greatest permitting complexity due to greater impacts, design complexity, and additional stakeholders. Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-14 SECTION 5 | MAWPA and Barnstable Wetlands By-Law Regulatory Compliance The proposed activities will occur within areas subject to protection and jurisdiction under the MAWPA and the Barnstable Wetlands Protection By-Law. These areas include Salt Marsh, Coastal Bank, LUO, Fish Run, Land Containing Shellflsh, LSCSF, Riverfront Area, as well as the 100-foot Buffer Zone. This section summarizes the project’s relationship to these jurisdictional areas as well as compliance with the MAWPA -established performance standards. 5.1 Limited Project The proposed work qualifles for limited project status as per 310 CMR 10.24(7)c.2: “The maintenance, repair and improvement (but) not substantial enlargement except when necessary to reduce or eliminate a tidal restriction) of structures, including buildings, piers, towers, headwalls, bridges and culverts which existed on November 1, 1987.” As the proposed work consists of the repair of existing bridge infrastructure, and as a bridge has existed at the current location and conflguration prior to November 1, 1987, it qualifles for consideration as a Limited Project. Therefore, the Conservation Commission has the authority to discretionarily waive or otherwise relax adherence to certain performance standards for this work. As the proposed project has overriding public safety beneflts, we request to invoke Limited Project Status relative to the performance standards for Salt Marsh and LUO. 5.2 Environmental Impacts The proposed activities will result in temporary and permanent impacts to jurisdictional wetland resource areas. These impacts are summarized in Table 5-1, below. TABLE 5-1 Summary of Anticipated Wetland Impacts Resource Area Proposed Activities Temporary Impact* Permanent Impact * Salt Marsh Rip rap slope repairs/embankment stabilization (including dredge), site access 1,410 square feet 350 square feet† Coastal Bank Rip rap slope repairs/embankment stabilization 475 linear feet 0 linear feet Barrier Beach Rip rap slope repairs/embankment stabilization, site access and staging, roadway and bridge repair work 7,200 square feet 0 square feet Land Under Ocean / Fish Run Rip rap slope repairs/embankment stabilization/scour protection (including dredge), cofferdams, site access 2,480 square feet 2,080 square feet Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-15 *Several jurisdictional resource areas overlap, resulting in fewer total impacts than depicted here. †Permanent salt marsh impacts are limited to the former embankment footprint that has become displaced since 2002. 5.3 MAWPA Performance Standards The following section describes the project ’s relation to pertinent performance standards. The performance standards are provided below in italics, while the project’s relation to the performance standards follow in normal font. 5.3.1 Salt Marsh WHEN A SALT MARSH IS DETERMINED TO BE SIGNIFICANT TO THE PROTECTION OF MARINE FISHERIES, THE PREVENTION OF POLLUTION, STORM DAMAGE PREVENTION OR GROUND WATER SUPPLY, 310 CMR 10.32(3) THROUGH (6) SHALL APPLY: (3) A proposed project in a salt marsh, on lands within 100 feet of a salt marsh, or in a body of water adjacent to a salt marsh shall not destroy any portion of the salt marsh and shall not have an adverse effect on the productivity of the salt marsh. Alterations in growth, distribution and composition of salt marsh vegetation shall be considered in evaluating adverse effects on productivity. 310 CMR 10.32(3) shall not be construed to prohibit the harvesting of salt hay. The proposed project will result in approximately 350 sf of permanent impacts to salt marsh. These impacts are limited to the previously authorized (2002) bridge footprint and are conflned to areas where salt marsh has encroached upon the former footprint of the bridge embankment. As such, these impacts are intended to be corrective in nature and do not constitute an expansion of flll beyond the previously authorized bridge footprint. In addition, the proposed project qualifles for consideration as a Limited Project pursuant to 310 CMR 10.24(7)(c) for repairs to an existing bridge that existed before November 1, 1987. Therefore, the Conservation Commission has the authority to discretionarily waive or otherwise relax adherence to certain performance standards for this work. (4) Notwithstanding the provisions of 310 CMR 10.32(3), a small project within a salt marsh, such as an elevated walkway or other structure which has no adverse effects other than blocking sunlight from the underlying vegetation for a portion of each day, may be permitted if such a project complies with all other applicable requirements of 310 CMR 10.21 through 10.37. Not applicable. Resource Area Proposed Activities Temporary Impact* Permanent Impact * Land Containing Shellfish Rip rap slope repairs/embankment stabilization 2,900 square feet 2,350 square feet Land Subject to Coastal Storm Flowage Rip rap slope repairs/embankment stabilization, site access, roadway, and bridge repair work 20,350 square feet 0 square feet Riverfront Area Rip rap slope repairs/embankment stabilization, site access and staging, roadway and bridge repair work 20,350 linear feet 0 square feet 100-Foot Buffer Zone Site access and staging, roadway and bridge repair work 20,350 linear feet 0 square feet Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-16 (5) Notwithstanding the provisions of 310 CMR 10.32(3), a project which will restore or rehabilitate a salt marsh, or create a salt marsh, may be permitted in accordance with 310 CMR 10.11 through 10.14, 10.24(8), and/or 10.53(4). Not applicable. (6) Notwithstanding the provisions of 310 CMR 10.32(3) through (5), no project may be permitted which will have any adverse effect on specifled habitat sites of Rare Species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. 5.3.2 Coastal Bank WHEN A COASTAL BANK IS DETERMINED TO BE SIGNIFICANT TO STORM DAMAGE PREVENTION OR FLOOD CONTROL BECAUSE IT IS A VERTICAL BUFFER TO STORM WATERS, 310 CMR 10.30(6) THROUGH (8) SHALL APPLY: (6) Any project on such a coastal bank or within 100 feet landward of the top of such coastal bank shall have no adverse effects on the stability of the coastal bank. This proposed project is intended to repair/rehabilitate the existing bridge embankments that have been subject to environmental degradation over time. As such, the project is anticipated to improve bank stability. (7) Bulkheads, revetments, seawalls, groins, or other coastal engineering structures may be permitted on such a coastal bank except when such bank is signiflcant to storm damage prevention or fiood control because it supplies sediment to coastal beaches, coastal dunes, and barrier beaches. Not applicable. The existing coastal banks consist of rip rap slopes and are not a signiflcant sediment source. (8) Notwithstanding the provisions of 310 CMR 10.30(3) through (7), no project may be permitted which will have any adverse effect on specifled habitat sites of rare vertebrate or invertebrate species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. 5.3.3 Barrier Beach When a Barrier Beach Is Determined to Be Signiflcant to Storm Damage Prevention, Flood Control, Marine Fisheries or Protection of Wildlife Habitat. 310 CMR 10.27(3) through (6)(coastal beaches) and 10.28(3) through (5) (coastal dunes) shall apply to the coastal beaches and to all coastal dunes which make up a barrier beach. Proposed work is conflned to the existing Craigville Beach Road Bridge Roadw ay and associated rip rap embankments, and Barrier Beach/Coastal Dune is only present to the south of the proposed work area. The project’s relation to the performance standards for Coastal Dune are described in §5.3.4, below. (4) Notwithstanding the provisions of 310 CMR 10.29(3), no project may be permitted which will have any adverse effect on specifled habitat sites of rare vertebrate or invertebrate species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-17 5.3.4 Coastal Dune WHEN A COASTAL DUNE IS DETERMINED TO BE SIGNIFICANT TO STORM DAMAGE PREVENTION, FLOOD CONTROL OR THE PROTECTION OF WILDLIFE HABITAT, 310 10.28(3) THROUGH (6) SHALL APPLY: (3) Any alteration of, or structure on, a coastal dune or within 100 feet of a coastal dune shall not have an adverse effect on the coastal dune by: (a) affecting the ability of waves to remove sand from the dune; (b) disturbing the vegetative cover so as to destabilize the dune; (c) causing any modiflcation of the dune form that would increase the potential for storm or fiood damage; (d) interfering with the landward or lateral movement of the dune; (e) causing removal of sand from the dune artiflcially; or (f) interfering with mapped or otherwise identifled bird nesting habitat. No work is proposed within the Coastal Dune itself, and the proposed work is not anticipated to interfere with the dune’s natural sand transport dynamics. No modiflcations to vegetative cover on the Coastal Dunes is proposed as part of the project and no bird nesting habitat was identifled within the limits of work. (4) Notwithstanding the provisions of 310 CMR 10.28(3), when a building already exists upon a coastal dune, a project accessory to the existing building may be permitted, provided that such work, using the best commercially available measures, minimizes the adverse effect on the coastal dune caused by the impacts listed in 310 CMR 10.28(3)(b) through (e). Such an accessory project may include, but is not limited to, a small shed or a small parking area for residences. It shall not include coastal engineering s tructures. Not applicable. The proposed work consists of repairs to existing transportation infrastructure. No new buildings are proposed as part of this project. (5): The following projects may be permitted, provided that they adhere to the provisions of 310 CMR 10.28(3): (a) pedestrian walkways, designed to minimize the disturbance to the vegetative cover and traditional bird nesting habitat; (b) fencing and other devices designed to increase dune development; and (c) plantings compatible with the natural vegetative cover. Not applicable. The proposed work consists of repairs to existing transportation infrastructure. (6) Notwithstanding the provisions of 310 CMR 10.28(3) through (5), no project may be permitted which will have any adverse effect on specifled habitat sites of Rare Species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. 5.3.5 Land Under the Ocean WHEN LAND UNDER THE OCEAN OR NEARSHORE AREAS OF LAND UNDER THE OCEAN ARE FOUND TO BE SIGNIFICANT TO THE PROTECTION OF MARINE FISHERIES, PROTECTION OF WILDLIFE HABITAT, STORM DAMAGE PREVENTION, OR FLOOD CONTROL, 310 CMR 10.25(3) THROUGH (7) SHALL APPLY: (3) Improvement dredging for navigational purposes affecting land under the ocean shall be designed and carried out using the best available measures so as to minimize adverse effects on such interests caused by changes in: Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-18 (a) bottom topography which will result in increased fiooding or erosion caused by an increase in the height or velocity of waves impacting the shore; (b) sediment transport processes which will increase fiood or erosion hazards by affecting the natural replenishment of beaches; (c) water circulation which will result in an adverse change in fiushing rate, temperature, or turbidity levels; or (d) marine productivity which will result from the suspension or transport of pollutants, the smothering of bottom organisms, the accumulation of pollutants by organisms, or the destruction of marine flsheries habitat or wildlife habitat. Not applicable. Proposed dredging is not intended for navigational purposes. (4) Maintenance dredging for navigational purposes affecting land under the ocean shall be designed and carried out using the best available measures so as to minimize adverse effects on such interests caused by changes in marine productivity which will result from the suspension or transport of pollutants, increases in turbidity, the smothering of bottom organisms, the accumulation of pollutants by organisms, or the destruction of marine flsheries habitat or wildlife habitat. Not applicable. Proposed dredging is not intended for navigational purposes. (5) Projects not included in 310 CMR 10.25(3) or (4) which affect nearshore areas of land under the ocean shall not cause adverse effects by altering the bottom topography so as to increase storm damage or erosion of coastal beaches, coastal banks, coastal dunes, or salt marshes. The project is intended to improve bank stability be re-establishing previously authorized rip rap along the base of the bridge embankments and abutments. As such, the project is not expected to increase the infrastructure’s susceptibility to storm damage or contribute to the erosion of jurisdictional resource areas. (6) Projects not included in 310 CMR 10.25(3) which affect land under the ocean shall if water-dependent be designed and constructed, using best available measures, so as to minimize adverse effects, and if non -water- dependent, have no adverse effects, on marine flsheries habitat or wildlife habitat caused by: (a) alterations in water circulation; (b) destruction of eelgrass (Zostera marina) or widgeon grass (Rupia maritina) beds; (c) alterations in the distribution of sediment grain size; (d) changes in water quality, including, but not limited to, other than natural fiuctuations in the level of dissolved oxygen, temperature or turbidity, or the addition of pollutants; or (e) alterations of shallow submerged lands with high densities of polychaetes, mollusks or macrophytic algae. The proposed work consists of the repair/rehabilitation of a water-dependent structure (bridge) and has been designed to minimize adverse effects to the greatest extent practicable. (7) Notwithstanding the provisions of 310 CMR 10.25(3) through (6), no project may be permitted which will have any adverse effect on specifled habitat sites of rare vertebrate or invertebrate species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-19 5.3.6 Land Containing Shellfish WHEN A RESOURCE AREA, INCLUDING LAND UNDER THE OCEAN, TIDAL FLATS, ROCKY INTERTIDAL SHORES, SALT MARSHES, OR LAND UNDER SALT PONDS IS DETERMINED TO BE SIGNIFICANT TO THE PROTECTION OF LAND CONTAINING SHELLFISH AND THEREFORE TO THE PROTECTION OF MARINE FISH ERIES, 310 CMR 10.34(4) THROUGH (8) SHALL APPLY: (4) Except as provided in 310 CMR 10.34(5), any project on land containing shellflsh shall not adversely affect such land or marine flsheries by a change in the productivity of such land caused by: (a) alterations of water circulation; (b) alterations in relief elevation; (c) the compacting of sediment by vehicular trafflc; (d) alterations in the distribution of sediment grain size; (e) alterations in natural drainage from adjacent land; or (f) changes in water quality, including, but not limited to, other than natural fiuctuations in the levels of salinity, dissolved oxygen, nutrients, temperature or turbidity, or the addition of pollutants. The proposed work is conflned to the previously established bridge footprint and is not anticipated to result in changes to the land’s productivity. The Town will provide a copy of this NOI to the Barnstable Shellflsh Biologist and the Massachusetts Division of Marine Fisheries (MassDMF) and will adhere to any recommended conservation measures to limit shellflsh impacts. (5) Notwithstanding the provisions of 310 CMR 10.34(4), projects which temporarily have an adverse effect on shellflsh productivity but which do not permanently destroy the habitat may be permitted if the land containing shellflsh can and will be returned substantially to its former productivity in less than one year from the commencement of work, unless an extension of the Order of Conditions is granted, in which case such restoration shall be completed within one year of such extension. Temporary erosion controls, to include cofferdams and turbidity curtains, will be removed upon completion of work. Proposed permanent impacts will be conflned to the historic (2002) bridge footprint and are not anticipated to result in an expansion of impacts beyond the previously authorized bridge footprint. (6) In the case of land containing shellflsh deflned as signiflcant in 310 CMR 10.34(3)(b) (i.e., those areas identifled on the basis of maps and designations of the Shellflsh Constable), except in Areas of Critical Environmental Concern, the issuing authority may, after consultation with the Shellflsh Constable, permit the shellflsh to be moved from such area under the guidelines of, and to a suitable location approved by, the Division of Marine Fisheries, in order to permit a proposed project on such land. An y such project shall not be commenced until after the moving and replanting of the shellflsh have been commenced. Coordination with the Barnstable Shellflsh Biologist and MassDMF will be undertaken to determine appropriate measures to conserve potential shellflsh present within the vicinity of the project site. (7) Notwithstanding 310 CMR 10.34(4) through (6), projects approved by the Division of Marine Fisheries that are speciflcally intended to increase the productivity of land containing shellflsh may be permitted . Aquaculture projects approved by the appropriate local and state authority may also be permitted. Not applicable. (8) Notwithstanding the provisions of 310 CMR 10.34(4) through (7), no project may be permitted which will have any adverse effect on specifled habitat of rare vertebrate or invertebrate species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-20 5.3.7 Fish Run WHEN SUCH LAND OR BANK IS DETERMINED TO BE SIGNIFICANT TO THE PROTECTION OF MARINE FISHERIES, 310 CMR 10.35(3) THROUGH (5) SHALL APPLY: (3) Any project on such land or bank shall not have an adverse effect on the anadromous or catadromous flsh run by: (a) impeding or obstructing the migration of the flsh, unless DMF has determined that such impeding or obstructing is acceptable, pursuant to its authority under M.G.L. c. 130, § 19; (b) changing the volume or rate of fiow of water within the flsh run; or (c) impairing the capacity of spawning or nursery habitats necessary to sustain the various life stages of the flsh. As part of the proposed work, the project includes the placement of temporary cofferdams in the Centerville River to allow the work to be conducted “in the dry.” These will be installed in accordance with all applicable Time of Year (TOY) restrictions and other provisions recommended by DMF. (4) Unless otherwise allowed by DMF pursuant to M.G.L. c. 130, § 19, dredging, disposal of Dredged Material or fllling in a flsh run shall be prohibited between March 15th and June 15th in any year. The proposed work will be conducted in accordance with all applicable TOY restrictions. (5) Notwithstanding the provisions of 310 CMR 10.35(3), no project may be permitted which will have any adverse effect on specifled habitat sites of rare vertebrate or invertebrate species, as identifled by procedures established under 310 CMR 10.37. The NHESP Atlas (15th edition, effective August 1, 2021), and MassGIS online mapping data (August 1, 2021) have been reviewed relative to the proposed work. According to these sources, the project site is not located within the limits of mapped Priority Habitats of Rare Species or Estimated Habitats of Rare Wildlife. (6) Any person proposing a new stream crossing of a Fish Run shall demonstrate to the issuing authority that there are no practicable alternatives to the crossing, that the impacts of the crossing have been minimized and that mitigation measures have been provided to contribute to the protection of the interests identifled in M.G.L. c. 131, § 40. An applicant will be presumed to have made this showing if the project is designed as follows: (a) If the project includes the construction of a new non-tidal crossing, the applicant demonstrates to the satisfaction of the issuing authority that the crossing complies with the Massachusetts Stream Crossing Standards by consisting of a span or embedded culvert in which, at a minimum, the top of the structure is above the elevation of the top of the bank and the structure spans the channel width by a minimum of 1.2 times the bankfull width. (b) If the project includes the construction of a new tidal crossing, the applicant demonstrates to the satisfaction of the issuing authority that the project is designed in a manner that does not restrict tidal fiow over the full natural tidal range by consisting of a span or embedded culvert in which, at a minimum, the top of the structure is above the elevation of the top of the bank and the structure spans the channel width by a minimum of 1.2 times the bankfull width. Not applicable. No new crossings are proposed as part of the project, rather the project consists of the repair and rehabilitation of an existing crossing. 5.3.8 Riverfront Area This section describes how the proposed project satisfles the provisions for developed Riverfront Area as stipulated at 310 CMR 10.58 (5). The performance standards are provided below in italics, while the details of project design follow. Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-21 Notwithstanding the provisions of 310 CMR 10.58(4)(c) and (d), the issuing authority may allow work to redevelop a previously developed riverfront area, provided the proposed work improves existing conditions. Redevelopment means replacement, rehabilitation or expansion of existing structures, improvement of existing roads, or reuse of degraded or previously developed areas. A previously developed riverfront area contains areas degraded prior to August 7, 1996 by impervious surfaces from existing structues or pavement, absence of topsoil, junkyards, or abandoned dumping grounds. Work to redevelop previously developed riverfront areas shall conform to the following criteria: (a) At a minimum, proposed work shall result in an improvement over existing conditions of the capacity of the riverfront area to protect the interests identifled in M.G.L. c. 131 §40. When a lot is previously developed but no portion of the riverfront area is degraded, the requirements of 310 CMR 10.58(4) shall be met. Proposed work within RFA will be conflned to previously developed/disturbed areas, to include the existing Craigville Beach Road Bridge, and the associated roadway and embankments. Minor vegetation clearing within the embankments is proposed, however this work is relatively minor in nature and consists of the removal of flve (5) eastern red cedar trees that have colonized the rip rap embankments. (b) Stormwater management is provided according to standards established by the Department. The proposed project is not anticipated to create additional stormwater discharges, nor will it result in changes to existing stormwater infrastructure. (c) Within 200 foot riverfront areas, proposed work shall not be located closer to the river than existing conditions or 100 feet, whichever is less… The proposed work within RFA is conflned to the pre-existing footprint of the paved roadway and associated rip- rap embankments. (d) Proposed work, including expansion of existing structures, shall be located outside the riverfront area or toward the riverfront area boundary and away from the river, except in accordance with 310 CMR 10.58(f) or (g). The proposed embankment repair work is intended to restore the historic footprint of the embankments. No expansion of existing structures within RFA is proposed as part of this project. (e) The area of proposed work shall not exceed the amount of degraded area, provided that the proposed work may alter up to 10% if the degraded area is less than 10% of the riverfront area, except in accordance with 310 CMR 10.58(f) or (g). Proposed work in RFA is conflned to previously degraded areas, and no alteration of undisturbed areas is proposed as part of this project. (f) When an applicant proposes restoration on-site of degraded riverfront area, alteration may be allowed notwithstanding the criteria of 310 CMR 10.58(c), (d), and (e) at a ratio in square feet of at least 1:1 of restored area to area of alteration not conforming to the criteria. Areas immediately along the river shall be selected for restoration. Alteration not conforming to the criteria shall begin at the riverfront area boundary… Not applicable. Proposed work in RFA is conflned to previously disturbed areas and no restoration is proposed as part of this project. (g) When an applicant proposes mitigation either on-site or in the riverfront area… Not applicable. Proposed work in RFA is conflned to previously disturbed areas and no mitigation is proposed as part of this project. Section 5 | MAWPA and Barnstable Wetlands By -Law Regulatory Compliance Notice of Intent | 5-22 (h) The issuing authority shall include a continuing condition in the Certiflcate of Complian ce for projects under 310 CMR 10.58(f) or (g) prohibiting further alteration within the restoration or mitigation area, except as may be required to maintain the area in its restored or mitigated condition… Not applicable, no restoration or mitigation is proposed as part of the project. 5.4 Abutter Notifications Abutters within 100-feet of the proposed repair work have been notifled in accordance with the procedures outline in the Town of Barnstable’s Abutter Notiflcation Regulation (Chapter 706). A copy of the Abutters List and the Abutter Notice is provided in Appendix E. Section 6 | Other Regulatory Compliance Notice of Intent | 6-23 SECTION 6 | Other Regulatory Compliance 6.1 State Permits 6.1.1 Massachusetts Historical Commission (MHC) / Section 106 Compliance New construction projects that require funding, licenses, or permits from any state or federal governmental agencies must be reviewed by the Massachusetts Historical Commission (MHC) for impacts to historic and archaeological properties. On March 24, 2025, a PNF was submitted to the MHC, as well as the Massachusetts Board of Underwater Archaeological Resources (MA BUAR) and geographically pertinent Tribal Historic Preservation Offlcers (THPOs) to determine potential impacts on historical, cultural, and/or archaeological resources. In their response dated April 27, 2025, MHC indicated that the proposed project is unlikely to affect signiflcant historic or archaeological resources. As of the date of this PCN submittal, no response has been received from MA BUAR or the THPOs. Should artifacts or human remains be encountered during construction, work will be halted, and appropriate agencies will be notifled. Information regarding historical resources is included in Appendix F. 6.1.2 MassDEP Individual 401 Water Quality Certification The proposed work will require an Individual 401 Water Quality Certification (WQC) because the project requires a federal permit and will result in a discharge of dredged or fill material to WOTUS (e.g., Salt Marsh, Land Under the Ocean) within the Commonwealth of Massachusetts. An application for a 401 WQC was submitted to MassDEP on June 26, 2026. 6.1.3 Massachusetts Environmental Policy Act (MEPA) As the proposed project requires a State Agency Action in the form of an Individual 401 WQC, the project is subject to environmental review pursuant to §11.01(2)(a) of the Massachusetts Environmental Policy Act (MEPA) regulations). As the project exceeds one or more Environmental Notiflcation Form (ENF) review thresholds as per the MEPA regulations (301 CMR 11.00), an ENF (EEA#17063) was prepared and submitted to the MEPA offlce on April 29, 2026. The ENF was published in the Environmental Monitor on May 8, 2026. 6.1.4 MassDEP Chapter 91 Minor Project Modification The Craigville Beach Road Bridge is located within areas subject to jurisdiction under Chapter 91: Waterways. As the proposed work involves maintenance/repairs to an existing structure, a request for a minor project modiflcation was submitted to MassDEP on April 9, 2026. No response has been received from MassDEP as of the date of this NOI submittal. 6.2 Federal Permits 6.2.1 Coastal Zone Management Act As the proposed work will fall within the Coastal Zone, it is thus subject to Coastal Zone Management (CZM) Federal Consistency Review. This review will be undertaken by the Massachusetts Offlce of CZM concurrently with the Corps review of the PCN application. Section 6 | Other Regulatory Compliance Notice of Intent | 6-24 6.2.2 U.S. Coast Guard Bridge Permit As the proposed work involves the work on a bridge spanning a navigable waterway, the proposed work falls within United State Coast Guard (USCG) jurisdiction, the project may require a USCG Bridge Permit. However, as the bridge is located over waters that are not used nor susceptible to use in their natural condition or by reasonable improvement as a means to transport interstate or foreign commerce, Tighe & Bond contacted the USCG Bridge Program Manager for the USCG Northeast District to conflrm whether the project would be exempt under 23 U.S.C. §144(c)(2) on April 9, 2026. On April 10, 2026, the USCG Northeast District Bridge Program Manager issued advance approval for the proposed work under 33 CFR 115.70. 6.2.3 U.S. Army Corps of Engineers Section 404 Clean Water Act The proposed work will result in impacts to Waters of the United States and thus requires review by the Army Corps of Engineers (the Corps) under Section 404 of the Federal Clean Water Act and Section 10 of the Rivers and Harbors Act. A Pre-Construction Notiflcation (PCN) application for coverage under the 2026 Nationwide Permits (effective March 2026) will be submitted to the Corps via the Regulatory Request System following submittal of this NOI submittal. Appendix A: Site Figures A G:\GIS\MA\SiteLocus\Barnstable\B0633_CraigvilleBeachRdBridge\B0633_CraigvilleBeachRdBridge.aprx\Figure1_CraigvilleBridge_Topo [Exported By: LFrassinelli, 1/26/2026, 11:17 AM] Based on USGS The National Map Topo Basemap. Contour Interval Equals 10 Feet. Circles indicate 500-foot and half-mile radii. B-0633 January 2026 0 1,000 2,000 FeetNÞ1:24,000 SITE LOCATION FIGURE 1 ,SITE LOCATIONSITE LOCATION Craigville Beach Road Bridge Repair Craigville Beach Road Barnstable, Massachusetts Repairs G:\GIS\MA\SiteLocus\Barnstable\B0633_CraigvilleBeachRdBridge\B0633_CraigvilleBeachRdBridge.aprx\Figure2_CraigvilleBridge_Resource [Exported By: LFrassinelli, 1/26/2026, 11:17 AM] !Þ !Þ !Þ !Þ!Þ X X X X X X XX X CENTERVILLE CRAIGVILLE CRAIGVILLE BEACH WEST HYANNISPORT L O N G B E A C H HYANNIS POINT C R A I G V I L L E B E A C H SPINDLE ROCK D O W S E E B E A C H LONG P O N D SCUDDER BAY C e nterville River NORTH POND COLEMAN POND CENTERVILLE RIVERCENTERVILLE HARBOR EAST BAY PHINNEYS BAY CRYSTAL LAKE CentervilleRiverCe n t e r villeRiverLAKE ELIZABETH 4020002-05G 4020002-03G 4020002-08G 4020002-07G Elliott Road Linda Lane O ld P o s t R o a d R iverviewLaneHi-On-A-Hill Roa d Seaboard LaneW atersideDrive P o n d S t r e e t L i n denAvenueF ernbroo k L anePena Way AdrenaAvenue BeldanL a n e O l d MillRoadWhidahWayPutterLan e Spice LaneLi amLaneCr os byRoadGinaCourt KalmiaWayCa n t e r b u r y C i r c l e Swift Av e n u eB utlerAvenueAlb e rt i Way La r c h L aneBumps R i v e r R o a dFiveCornersRoad EvelynCircleBeach St r e et L o n g B e a c h R o a d Pine StreetGlenwoodAvenue Sa ndpi pe r La n eOldStageRoadOverlookDrive SeventhAvenueLa u r e l A v e n u e GreenDunesDriveSpringMeadows Birch DriveHarbo r H i l ls Road Scottsdale Road Linco ln StreetCraigwood RoadMarrick Court Sac hemDri veThird AvenueGreat MarshRoad M ainStree t So u t h C e d a r R o a d KearsargeAvenueJib WayWianno Avenue Ellas LaneC r a i g vi l l e B e a c h R o ad Oak Drive Falmouth Road Carla Road P i n e W a y Hayward Roa d Earles CourtRudderRoadFullerRoadP hinneysLaneO ldCraigvilleRoadBl ackber r yLaneMapleRoadBlantyre Avenue Mallard LaneSwainLan eLumber t Mi l l Roa dSunset AvenueCirc uitAvenueHo r n b e a mLaneS o u th M a in S tr e etChadwick AvenueHoratioLaneLincoln L a n e TrinityPlaceQuiet WayLongacre Lane Argyle A v e n u e We s t M a i n S t r e e t Dar b y W a y Daniel WayWest View LaneCottageLaneBirchillR o a d Pond Vie wDriveOld Salem WayKirk Lane West WayWinns WayH i l l Creek Road Gosling Path Pheasant WayS h o rtBea c h R o a d Central Avenue Waterm a nFarmRoad Joan RoadFortes Way Thyme Lane Shorey Roa d Tanager Roa dBee LaneTawny Avenu e Kay AvenuePearl RoadKatherine RoadElliott StreetCan n o n D r i v e SixthAvenueCrawf o rdEmersonWayCrosby CirclePineTree D r i v e Strawber r yHillRoadLeonard Road Sylvia Lane OldTown R oad CoveRo a dOrchard Road MothersParkRoadWe a v e r R o a d KeelWayGinger Lane Soundview Road B riarcliff Lan e MalonyRoadJuniper RoadBayberryLanePleasantParkAvenueFarm Hill RoadCrocker S t r e e t Thornberry LaneNatkaDriveB ay LaneEvsunDrive Holly Hill R o a d ChappaquiddickRoad LimerickCourtCranberryLaneWest TerraceLawrenceLaneP o w e r s D r i v e MagnoliaAvenueDonegalCircleBeth-Ann LaneParkAvenueL illian D r i v e Cross Way PlaceMaureen RoadPeacock DriveBretw o o d L a n e Ch ur ch H i llR o a d RaymondStreet W e s t m in s t e r R o a d FoxHillRoad P arsley L a n e DeerfieldRoadHol l yLaneDolphin LaneKennesawAvenueMaple WayTobey WayBe a c h P l u m L a n e Baco n L a n eShootflyingHillRoadSeansCircle C lif t onLaneAut u m n D riv e First AvenueSecond AvenueChilds StreetC ampOpecheeRoadBridget s P a t h St anl eyWayPo w d e r h o r n W a y Sea gateLaneLongfellowDriveL i e t rimCircleStoneyCliffRoadDunns Pond RoadTaramac R o a d E astBayRoad AmesWay Fifth AvenueSkunknetRoadStarboard La n e UV28 Data source: Bureau of Geographic Information (MassGIS), Commonwealth of Massachusetts, Executive Office of Technology. Circles indicate 500-foot and half-mile radii. Data valid as of January 2026. B-0633 X NHESP Certified Vernal PoolXNHESP Potential Vernal Pool#Non-Landfill Solid Waste Site !Þ Proposed Well !Þ Emergency Surface Water !Þ Community Public Water Supply - Surface Water !Þ Community Public Water Supply - Groundwater "Non-Community Non-Transient Public Water Supply "T Non-Community Transient Public Water Supply Limited Access Highway Multi-Lane Highway, NOT Limited Access Other Numbered Route Major Road - Arterials and Collectors Minor Street or Road Aqueduct Hydrologic Connection Stream/Intermittent Stream !!Powerline Pipeline Track or Trail Railroad Public Surface Water Supply Protection Area (Zone A) DEP Approved Wellhead Protection Area (Zone I) DEP Approved Wellhead Protection Area (Zone II) DEP Interim Wellhead Protection Area (IWPA) Protected and Recreational Open Space Solid Waste Landfill Area of Critical Environmental Concern (ACEC) NHESP Priority Habitat for Rare Species NHESP Estimated Habitat for Rare Wildlife EPA Designated Sole Source Aquifer Major Drainage Basin Sub Drainage Basin MassDEP Inland Wetland MassDEP Coastal Wetland MassDEP Not Interpreted Wetland Public Surface Water Supply (PSWS) Water Body Non-Potential Drinking Water Source Area - High Yield Non-Potential Drinking Water Source Area - Medium Yield Potentially Productive Medium Yield Aquifer Potentially Productive High Yield Aquifer County Boundary Municipal Boundary USGS Quadrangle Sheet Boundary 0 1,000 2,000 FeetNÞ1:24,000 January 2026 PRIORITY RESOURCES FIGURE 2 ,SITE LOCATIONSITE LOCATION Craigville Beach Road Bridge Repair Craigville Beach Road Barnstable, Massachusetts Repairs G:\GIS\MA\SiteLocus\Barnstable\B0633_CraigvilleBeachRdBridge\B0633_CraigvilleBeachRdBridge.aprx\Figure3_CraigvilleBridge_Aerial [Exported By: LFrassinelli, 1/26/2026, 11:17 AM] C r a i g v i l l e B e a c h R o a d Short B e a c h R o a d Centerville River Based on latest Nearmap Imagery. 0 25 50 FeetNÞ1:600 B-0633 Mean High Water Line Approximate Salt Marsh Area Proposed Dredge Area Limit of Work Boundary January 2026 AERIAL FIGURE 3Craigville Beach Road Bridge Repair Craigville Beach Road Barnstable, Massachusetts Repairs AERIAL WITH PROJECT LIMITS National Flood Hazard Layer FIRMette 0 500 1,000 1,500 2,000250 Feet Ü SEE FIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT SPECIAL FLOOD HAZARD AREAS Without Base Flood Elevation (BFE) Zone A, V, A99 With BFE or Depth Zone AE, AO, AH, VE, AR Regulatory Floodway 0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mile Zone X Future Conditions 1% Annual Chance Flood Hazard Zone X Area with Reduced Flood Risk due to Levee. See Notes.Zone X Area with Flood Risk due to Levee Zone D NO SCREEN Area of Minimal Flood Hazard Zone X Area of Undetermined Flood Hazard Zone D Channel, Culvert, or Storm Sewer Levee, Dike, or Floodwall Cross Sections with 1% Annual Chance 17.5 Water Surface Elevation Coastal Transect Coastal Transect Baseline Profile Baseline Hydrographic Feature Base Flood Elevation Line (BFE) Effective LOMRs Limit of Study Jurisdiction Boundary Digital Data Available No Digital Data Available Unmapped This map complies with FEMA's standards for the use of digital flood maps if it is not void as described below. The basemap shown complies with FEMA's basemap accuracy standards The flood hazard information is derived directly from the authoritative NFHL web services provided by FEMA. This map was exported on 4/24/2026 at 4:53 PM and does not reflect changes or amendments subsequent to this date and time. The NFHL and effective information may change or become superseded by new data over time. This map image is void if the one or more of the following map elements do not appear: basemap imagery, flood zone labels, legend, scale bar, map creation date, community identifiers, FIRM panel number, and FIRM effective date. Map images for unmapped and unmodernized areas cannot be used for regulatory purposes. Legend OTHER AREAS OF FLOOD HAZARD OTHER AREAS GENERAL STRUCTURES OTHER FEATURES MAP PANELS 8 B 20.2 The pin displayed on the map is an approximate point selected by the user and does not represent an authoritative property location. 1:6,000 70°20'59"W 41°38'35"N 70°20'22"W 41°38'8"N Basemap Imagery Source: USGS National Map 2023 Figure 4: National Flood Hazard Layer FIRMette Appendix B: Photo Log Phot o graphic Log Client: Town of Barnstable Job Number 11-0633-0020 Site: Craigville Beach Road Bridge Repair Project (Barnstable, Massachusetts) Photograph No.: 1 Date: June 2, 2025 Direction Taken: Northwest Description: View from Craigville Beach Road Bridge of the Centerville River, facing downstream. Photograph No.: 2 Date: June 2, 2025 Direction Taken: Northeast Description: Representative view of Salt Marsh adjacent to the Craigville Beach Road Bridge, facing upstream. Phot o graphic Log Client: Town of Barnstable Job Number 11-0633-0020 Site: Craigville Beach Road Bridge Repair Project (Barnstable, Massachusetts) Photograph No.: 3 Date: June 2, 2025 Direction Taken: North Description: View of Craigville Beach Road at the bridge, facing north. Photograph No.: 4 Date: June 2, 2025 Direction Taken: Southeast Description: View of the Centerville River and existing riprap from the bridge, facing upstream. Phot o graphic Log Client: Town of Barnstable Job Number 11-0633-0020 Site: Craigville Beach Road Bridge Repair Project (Barnstable, Massachusetts) Photograph No.: 5 Date: June 2, 2025 Direction Taken: Southeast Description: View of the Centerville River and riprap embankments beneath the bridge (upstream). Photograph No.: 6 Date: June 2, 2025 Direction Taken: North Description: View of Land Under the Ocean associated with the river beneath the bridge (downstream). Phot o graphic Log Client: Town of Barnstable Job Number 11-0633-0020 Site: Craigville Beach Road Bridge Repair Project (Barnstable, Massachusetts) Photograph No.: 7 Date: June 2, 2025 Direction Taken: South Description: View of the approximate salt marsh area (circled in red) to be permanently impacted within the historic bridge footprint (downstream). Photograph No.: 8 Date: June 2, 2025 Direction Taken: Northwest Description: View of the approximate salt marsh area (circled in red) to be permanently impacted within the historic bridge footprint (downstream). Phot o graphic Log Client: Town of Barnstable Job Number 11-0633-0020 Site: Craigville Beach Road Bridge Repair Project (Barnstable, Massachusetts) Photograph No.: 9 Date: June 2, 2025 Direction Taken: North Description: View of the approximate salt marsh area (circled in red) to be permanently impacted within the historic bridge footprint (upstream). Photograph No.: 10 Date: June 2, 2025 Direction Taken: East Description: View of the approximate salt marsh area (circled in red) to be permanently impacted within the historic bridge footprint (upstream). Appendix C: Project Drawings Plotted On:Jul 17, 2026-3:31pm By: JManLast Saved: 7/10/2026Tighe & Bond: J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Cover.dwgPREPARED BY: TOWN OF BARNSTABLE, MASSACHUSETTS COMPLETE SET 17 SHEETS THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. PREPARED FOR: TOWN OF BARNSTABLE DEPARTMENT OF PUBLIC WORKS PAUL GRAVES, PE, SENIOR PROJECT MANAGER GRIFFIN BEAUDOIN, PE, TOWN ENGINEER ERIC OHANIAN, PE BRIAN GARGAN, PE JULY 2026 PROPOSED BRIDGE REPAIR CRAIGVILLE BEACH ROAD OVER CENTERVILLE RIVER 90% DESIGN MASSDOT BRIDGE NO. B-01-002, BIN NO. AED N NAD 83PROJECT END STA. 20+00.00 N 2695620.0746 E 972118.3740 BR# B-01-002 PROJECT BEGIN STA. 16+80.00 N 2695843.9363 E 971889.7198 PROJECT LOCATION THESE PLANS ARE SUPPLEMENTED BY THE LATEST EDITIONS OF THE FOLLOWING PUBLICATIONS, AS IDENTIFIED IN THE CONTRACT SPECIAL PROVISIONS: THE MASSDOT CONSTRUCTION STANDARD DETAILS, THE MASSDOT STANDARD DRAWINGS FOR SIGNS AND SUPPORTS, THE MASSDOT STANDARD DRAWINGS FOR TRAFFIC SIGNALS AND HIGHWAY LIGHTING, THE MASSDOT OVERHEAD SIGNAL STRUCTURE AND FOUNDATION STANDARD DRAWINGS, THE MASSDOT TRAFFIC MANAGEMENT PLANS AND DETAIL DRAWINGS, AND THE ANSI AMERICAN STANDARD FOR NURSERY STOCK. INDEX SHEET NO.DESCRIPTION 1 TITLE SHEET AND INDEX 2 GENERAL NOTES, LEGEND & ABBREVIATIONS 3 EXISTING CONDITIONS & DEMOLITION PLAN 4 SITE PLAN 5 TEMPORARY TRAFFIC CONTROL PLAN (1 OF 2) 6 TEMPORARY TRAFFIC CONTROL PLAN (2 OF 2) 7 WATER CONTROL DETAILS 8 EROSION CONTROL DETAILS 9 - 17 BRIDGE PLANS LENGTH OF PROJECT = 325 FEET = 0.062 MILES 200 SCALE: 1" = 200' 0 500 1000 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION NO SCALE GENERAL NOTES, LEGEND & ABBREVIATIONS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_General.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:32pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_General.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man SHEET 2 OF 17VVVVVVHHWHHWHHW · · · STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION 07/29/2026 VVVVVVVVVVVVVVVVVVVVVVVV VVVVVV VVVVVVVVVVVVVVV VVVVVVVVVVVVVVVVV VVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV VV V V VVVV V VVVVVVV VV V V VVVVVVVVVVVV V V V VVVVVVVVVVVVVVVVV VV V VV VVV V VVV V V VVVVV V V VVVVVVVVV VVVVVVVV V VV VVV VVV VVVVVVVVVVVVVVVVVS 45° 36' 24" E 495.00'34567 BY OPENING THIS FILE(S) YOU AGREE TO THE FOLLOWING CONDITIONS OF TRANSFER:1.TOWN OF BARNSTABLE'S POLICY IS TO PROVIDE SEALED AND CERTIFIED DRAWINGS THAT REPRESENTOUR FINAL DESIGN PRODUCT. DIGITAL OR ELECTRONIC FILES DO NOT REPRESENT SEALED AND CERTIFIED DESIGNPRODUCTS.2.ELECTRONIC OR DIGITAL FILES CAN BE MODIFIED WITHOUT OUR KNOWLEDGE OR APPROVAL;THEREFORE, TOWN OF BARNSTABLE DOES NOT CERTIFY ELECTRONIC FILES.3.THE DIGITAL OR ELECTRONIC FILES ARE BEING PROVIDED AS REQUESTED BY RECIPIENT. THETRANSFER OF THE DIGITAL OR ELECTRONIC FILES DOES NOT REPRESENT A SALE OF DATA NOR DOES IT CREATE ALICENSE FOR RECIPIENT TO COPY OR MODIFY THE DIGITAL OR ELECTRONIC FILES. TOWN OF BARNSTABLE RETAINSFULL OWNERSHIP AND COPYRIGHTS OF THE FILES AND DATA WITHIN THE FILES, INCLUDING SUBSEQUENT COPIES.4.IT IS UP TO THE USERS OF THIS DATA TO DETERMINE IF THE INTEGRITY AND INTENDED PURPOSE OFTHE FILES ARE ADEQUATE FOR THEIR PURPOSES. TOWN OF BARNSTABLE DOES NOT ASSUME ANY RESPONSIBILITYOR LIABILITY FOR THEIR USE OR RE-USE. THE RECIPIENT AND USERS ARE SOLELY RESPONSIBLE FOR THEIR USE ANDSUBSEQUENT COSTS OR DAMAGES ARISING FROM THE USE.5.THE ELECTRONIC OR DIGITAL FILES ARE NOT CONTRACT DOCUMENTS AND DO NOT REPRESENTCONSTRUCTION DOCUMENTS.6.ANY SURFACES OR LAYERS IN THE DIGITAL OR ELECTRONIC FILES MAY NOT BE CONSTRUCTION LEVEL,MAY NOT BE CURRENT WITH THE LATEST DESIGN, OR MAY NOT REPRESENT THE CURRENT CONDITIONS OF THESITE, AND THE DATA MAY NEED ADDITIONAL ENGINEERING WORK BEFORE BEING USED FOR FURTHER DESIGN ORCONSTRUCTION PURPOSES.7.TO THE FULLEST EXTENT ALLOWED BY LAW, THE USE OR RE-USE OF THE FILES REPRESENTS THERECIPIENT'S AGREEMENT TO INDEMNIFY, DEFEND AND HOLD HARMLESS TOWN OF BARNSTABLE FROM ANYLIABILITY, CLAIMS, COSTS, OR DAMAGE WHICH RESULTS DUE TO THE USE OR RE-USE OF THE FILES, INCLUDINGBUT NOT LIMITED TO, ATTORNEY'S FEES, COSTS OF DEFENSE, SUITS, DAMAGES OR CLAIMS.8.IN NO EVENT WILL TOWN OF BARNSTABLE BE LIABLE FOR ANY DIRECT OR INDIRECT DAMAGES ORCOSTS DUE TO THE FILES, THEIR USE, THEIR RE-USE OR THEIR CONTENTS.9.THE FILES AND THEIR CONTENTS ARE COPYRIGHTED AND TRANSFERENCE OR SHARING FILES OR FILEDATA WITH OTHERS IS NOT AUTHORIZED.10.THE REFERENCE TO TOWN OF BARNSTABLE REFERS TO THE CORPORATION, ITS OFFICERS, ITSEMPLOYEES AND IT'S AGENTS.BY OPENING THIS FILE(S) YOU AGREE TO THE FOLLOWING CONDITIONS OF TRANSFER:1.TOWN OF BARNSTABLE'S POLICY IS TO PROVIDE SEALED AND CERTIFIED DRAWINGS THAT REPRESENTOUR FINAL DESIGN PRODUCT. DIGITAL OR ELECTRONIC FILES DO NOT REPRESENT SEALED AND CERTIFIED DESIGNPRODUCTS.2.ELECTRONIC OR DIGITAL FILES CAN BE MODIFIED WITHOUT OUR KNOWLEDGE OR APPROVAL;THEREFORE, TOWN OF BARNSTABLE DOES NOT CERTIFY ELECTRONIC FILES.3.THE DIGITAL OR ELECTRONIC FILES ARE BEING PROVIDED AS REQUESTED BY RECIPIENT. THETRANSFER OF THE DIGITAL OR ELECTRONIC FILES DOES NOT REPRESENT A SALE OF DATA NOR DOES IT CREATE ALICENSE FOR RECIPIENT TO COPY OR MODIFY THE DIGITAL OR ELECTRONIC FILES. TOWN OF BARNSTABLE RETAINSFULL OWNERSHIP AND COPYRIGHTS OF THE FILES AND DATA WITHIN THE FILES, INCLUDING SUBSEQUENT COPIES.4.IT IS UP TO THE USERS OF THIS DATA TO DETERMINE IF THE INTEGRITY AND INTENDED PURPOSE OFTHE FILES ARE ADEQUATE FOR THEIR PURPOSES. TOWN OF BARNSTABLE DOES NOT ASSUME ANY RESPONSIBILITYOR LIABILITY FOR THEIR USE OR RE-USE. THE RECIPIENT AND USERS ARE SOLELY RESPONSIBLE FOR THEIR USE ANDSUBSEQUENT COSTS OR DAMAGES ARISING FROM THE USE.5.THE ELECTRONIC OR DIGITAL FILES ARE NOT CONTRACT DOCUMENTS AND DO NOT REPRESENTCONSTRUCTION DOCUMENTS.6.ANY SURFACES OR LAYERS IN THE DIGITAL OR ELECTRONIC FILES MAY NOT BE CONSTRUCTION LEVEL,MAY NOT BE CURRENT WITH THE LATEST DESIGN, OR MAY NOT REPRESENT THE CURRENT CONDITIONS OF THESITE, AND THE DATA MAY NEED ADDITIONAL ENGINEERING WORK BEFORE BEING USED FOR FURTHER DESIGN ORCONSTRUCTION PURPOSES.7.TO THE FULLEST EXTENT ALLOWED BY LAW, THE USE OR RE-USE OF THE FILES REPRESENTS THERECIPIENT'S AGREEMENT TO INDEMNIFY, DEFEND AND HOLD HARMLESS TOWN OF BARNSTABLE FROM ANYLIABILITY, CLAIMS, COSTS, OR DAMAGE WHICH RESULTS DUE TO THE USE OR RE-USE OF THE FILES, INCLUDINGBUT NOT LIMITED TO, ATTORNEY'S FEES, COSTS OF DEFENSE, SUITS, DAMAGES OR CLAIMS.8.IN NO EVENT WILL TOWN OF BARNSTABLE BE LIABLE FOR ANY DIRECT OR INDIRECT DAMAGES ORCOSTS DUE TO THE FILES, THEIR USE, THEIR RE-USE OR THEIR CONTENTS.9.THE FILES AND THEIR CONTENTS ARE COPYRIGHTED AND TRANSFERENCE OR SHARING FILES OR FILEDATA WITH OTHERS IS NOT AUTHORIZED.10.THE REFERENCE TO TOWN OF BARNSTABLE REFERS TO THE CORPORATION, ITS OFFICERS, ITSEMPLOYEES AND IT'S AGENTS. CRAIGVILLE BEACH RD CONSTRUCTION BASELINE DATA NUMBER L1 STARTING STATION 15+55.00 NORTHING 2695931.384 EASTING 971800.400 CURVE DATA LINE DATA S45°36'24"E 495.00' ENDING STATION 20+50.00 NORTHING 2695585.092 EASTING 972154.106 200014.2969TREE-200024.8956TREE-1200034.7409TREE-1200045.5546TREE-5200054.3024TREE-4200065.9152TREE-3200075.4166TREE-3RTCM-Ref 005588.403 AS SHOWN EXISTING CONDITIONS & DEMOLITION PLAN 00 20'40' SCALE: 1" = 20' CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Civil.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:33pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Civil.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man N A D 8 3 N SHEET 3 OF 17 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION VVVVVVVVVVVVVVVVVVVVVVVV VVVVVV VVVVVVVVVVVVVVV VVVVVVVVVVVVVVVVV VVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV VV V V VVVV V V VVVVVV VV V V VVVVVVVVVVVV V V V VVVVVVVVVVVVVVVVV VV V VV VVV V VVV V V VVVVV V V VVVVVVVVV VVVVVVVV V VV VVV VVV VVVVVVVVVVVVVVVVVS 45° 36' 24" E 495.00'34567 AS SHOWN SITE PLAN 00 20'40' SCALE: 1" = 20' CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Civil.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:33pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Civil.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man N A D 8 3 N SHEET 4 OF 17 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_TTCP.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:33pm By: JManLast Saved: 7/7/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_TTCP.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man SPEED LIMIT (S)TAPER LENGTH (L) FEET POLICE OFFICER AHEAD ONE LANE ROAD AHEAD ONE LANE ROAD AHEAD POLICE OFFICER AHEAD RIGHT SHOULDER CLOSED ROAD NARROWS ROAD AHEAD WORK NAD 83N panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18 panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18 EXISTING SIDEWALK WORK ZONE TO BE ENCLOSED BY FENCING TYPE III BARRICADE TEMPORARY CROSSWALK EXISTING SIDEWALK TEMPORARY CROSSWALK PEDESTRIAN PATH AS SHOWN SHEET 5 OF 17 TEMPORARY TRAFFIC CONTROL PLAN (1 OF 2) S P E E D I N G F I N E SDOUBL E D W O R K Z O N E E N D R O A D W O R K D O U B L E F I N E S E N D 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION 45AS SHOWN SHEET 6 OF 17 TEMPORARY TRAFFIC CONTROL PLAN (2 OF 2) CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_TTCP.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:33pm By: JManLast Saved: 7/7/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_TTCP.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man N AD 8 3 N TEMPORARY CONSTRUCTION SIGN SUMMARY ROAD WORK AHEAD SIDEWALK CLOSED CROSS HERE SIDEWALK CLOSED CROSS HERE W5-1 W21-5a W20-4 MA-W20-7b 36 36 3636 3636 3636 BLACK BLACKORANAGE BLACK BLACKORANAGE BLACK BLACKORANAGE BLACK BLACKORANAGE1 1 2 2 ROAD NARROWS POLICE OFFICER AHEAD RIGHT SHOULDER CLOSED ONE LANE ROAD AHEAD 2 2 2 1 1 1 S P E E D I N G F I N E S D O U B L E D W O R K Z O N E E N D R O A D W O R K D O U B L E F I N E S E N D MA-R2-10a 1836 2 2 BLACK BLACKORANAGE /WHITE BLACK BLACKORANAGE /WHITEMA-R2-10e 1836 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN SHEET 7 OF 17 WATER CONTROL DETAILS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Const.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:33pm By: JManLast Saved: 7/7/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Const.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN SHEET 8 OF 17 EROSION CONTROL DETAILS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Const.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:33pm By: JManLast Saved: 7/7/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Const.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION VVVVVVVVVVVVVVVVVVVV VVVVVVVVVVVVVVVVV VVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVS 45° 36' 24" E 495.00'45NAVD 88 BASE ELEV -15.00 -10 0 10 20 -15 -10 0 10 20 17+50 18+00 19+00 19+507.2417+507.248.4718+008.489.038.6519+008.657.7419+50 NAVD 88 BASE ELEV -15.00 -10 0 10 20 -15 -10 0 10 20 3+75 4+00 4+50 5+00 5+25-9.743+75 -10.274+00-10.27-8.67-10.545+00-10.55-12.555+25-10.55AS SHOWN BRIDGE KEY PLAN, PROFILES & LOCUS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Civil.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:34pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Civil.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man SHEET 9 OF 17NAD 83N COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division N A D 8 3 N 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION NO SCALE BRIDGE NOTES CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_General.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:35pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_General.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man SHEET 10 OF 17 · · · 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN GENERAL PLAN AND ELEVATION CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Bridge.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:35pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Bridge.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man SHEET 11 OF 17 N AD 8 3 N 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN RIPRAP REPAIRS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Civil.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:36pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Civil.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) J. Man S. Sak B. Gargan J. Man SHEET 12 OF 17 COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN SHEET 13 OF 17 EAST ABUTMENT PLAN AND ELEVATION CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Bridge.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:36pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Bridge.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man NAD 83N07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN WEST ABUTMENT PLAN AND ELEVATION CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Bridge.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:36pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Bridge.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man SHEET 14 OF 17 N NAD 8307/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN CONCRETE REPAIR DETAILS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Repair Detail.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:37pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Repair Detail.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man SHEET 15 OF 17 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN SHEET 16 OF 17 MISCELLANEOUS REPAIR DETAILS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Repair Detail.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:37pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Repair Detail.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION AS SHOWN SHEET 17 OF 17 BRIDGE RAIL REPAIRS CHECKED BY: DRAWN BY: FILE: APPROVED BY: DATE: PROJECT NO: MARK DATE DESCRIPTION B0633-020_Rail.dwg JULY 2026 B0633-020 SCALE:Plotted On:Jul 17, 2026-3:38pm By: JManLast Saved: 7/17/2026Tighe & Bond:J:\B\B0633 Barnstable\020 - Craigville Beach Road Bridge\Drawings\AutoCAD\Sheet\B0633-020_Rail.dwgDESIGNED BY: THIS DOCUMENT IS RELEASED TEMPORARILY FOR PROGRESS REVIEW ONLY. IT IS NOT INTENDED FOR BIDDING OR CONSTRUCTION PURPOSES. 90% DESIGN Proposed Bridge Repair Town of Barnstable Craigville Beach Road over Centerville River B-01-002 (AED) COMMONWEALTH OF MASSACHUSETTS MassDOT, Highway Division J. Man S. Sak B. Gargan J. Man N A D 8 3 N 07/29/2026 STAMPED FOR PERMITTING PURPOSES ONLY NOT FOR CONSTRUCTION Appendix D: 1998 Project Drawings for 2002 Bridge Reconstruction Appendix E: Abutter Noti fication Information 206050 206136 206087 206085001206053 206085003 206047 206085002 206048 206044 206089 206045 206090 206097 206088 206042206043 206046 206049 100' NOI Buffer Subject Area Abutters Conservation NOI Abutter List For Centerville Bridge ProjectThis list by itself does NOT constitute a certified list of abutters and is provided only as an aid to the determination of abutters. The requestor of this list is responsible for ensuring the correct notification of abutters. Owner and address data taken from the Town of Barnstable Assessor's database on 5/11/2026Property owners within 100 ft. of the perimeter of work area. Mappar Owner1 Owner2 Address 1 City State Zip CountryAddress 2206042FRANKS, THOMAS M & BELL, BETH A39 HORSECHESTNUT ROADBRIARCLIFF MANORNY10510206043DAVID JAMES DEVELOPMENT LLCPO BOX 200NORTHBOROMA01532206044PARK CITY WIND LLCAVANGRID, ATTN PROPERTY TAX DEPT.2701 NW VAUGHN STREET, SUITE 300PORTLANDOR97210206045GUILLET, EDWARD E TREDWARD E GUILLET REV TRUST650 CHARLES VAN DAMME WAYSONOMACA95476206046SCHNEIDER, JACK & BETTY ANNE131 TRANQUILLA DRIVEPALM BEACH GARDENSFL33418206047HIGGINS, JAMES R & ELAINE M42 GRAYSTONE CIRCLEWINCHESTERMA01890206048BLACKWELL, RICHARD M & DIANE5 FREDERICK CIRCLEWOBURNMA01801206049KENNEDY, DOUGLAS & NICOLE96 MILLBROOK AVEWALPOLEMA02081206050NEWBERG, JENNIFER L TR1187 CBR REALTY TRUST35 BERWICK ROADNEWTON CENTREMA02459206053LEBOW, BERNARD & GUILFOILE, BARBARA J40 ALGONQUIN ROADCHESTNUT HILLMA02467206085001CBA SUMMER HILL LLCPO BOX 1678NAPLESFL34106206085002BALSAMO, MARY E TRC/O MURPHY & MURPHYPO BOX 922CENTERVILLEMA02632206085003CBA SUMMER COTTAGE LLCPO BOX 1678NAPLESFL34106206087CBA SUMMER HILL LLCPO BOX 1678NAPLESFL34106Tuesday, May 12, 2026Page 1 of 2 Mappar Owner1 Owner2 Address 1 City State Zip CountryAddress 2206088132 BAY SHORE ROAD LLC5521 GOODWIN AVEDALLASTX75206206089BARNSTABLE LAND TRUST INC1540 MAIN STREETWEST BARNSTABLEMA02668206090PAPA, MARIA M50 WASHINGTON AVENUESCHENECTADYNY12305206097LASHGARI, VIDA11 SHORT BEACH ROADCENTERVILLEMA02632206136PEPE, ROBERT F & MICHELLE F56 EISENHOWER DRIVESHARONMA02067Tuesday, May 12, 2026Page 2 of 2 NOTICE OF INTENT ABUTTER NOTIFICATION LETTER DATE: RE: Upcoming Barnstable Conservation Commission Public Hearing To Whom It May Concern, As an abutter within 100 feet of a proposed project, please be advised that a NOTICE OF INTENT application has been filed with the Barnstable Conservation Commission. APPLICANT: PROJECT ADDRESS OR LOCATION: ASSESSOR’S MAP & PARCEL: MAP PARCEL PROJECT DESCRIPTION: ________________________________________________________ APPLICANT’S AGENT: PUBLIC HEARING: WILL BE HELD REMOTELY VIA ZOOM See agenda posting on Town Clerks website available at least 48 hours in advance of the meeting for details. DATE: / / TIME: P.M. NOTE: Plans and applications describing the proposed activity are on file with the Conservation Commission at https://itlaserfiche.town.barnstable.ma.us/WebLink/Browse.aspx?id=825530&dbid=0&repo=TownOfBarns table, by email to Kimberly.Cavanaugh@town.barnstable.ma.us or by calling (508-862-4093) Appendix F: Historical and Archeological Resources Information 1 Julia Novotny From:Julia Novotny Sent:Thursday, February 19, 2026 2:31 PM To:David.S.Robinson@mass.gov; thpo@wampanoagtribe-nsn.gov; 106review@mwtribe-nsn.gov; david.weeden@mwtribe-nsn.gov; narrawamp@gmail.com Cc:Amanda J. Houle; Eric Ohanian; Sebastian Sak Subject:Project Notification Form - Craigville Beach Road Bridge (Barnstable, MA) Attachments:Craigville Beach Road Bridge PNF.pdf; Figure1_CraigvilleBridge_Topo.pdf; B0633-020_02042026.pdf Good afternoon, Attached, please find the Project Notification Form (PNF), a USGS Topographic Map, and a set of Project Drawings for the Craigville Beach Road Bridge Repair Project located in Barnstable, Massachusetts, for your review relative to historic and archaeological resources. This PNF has also been submitted to the Massachusetts Historical Commission, the State Historic Preservation O Ưicer. Please send responses to this notification directly to the USACE via email: cenae-r-ma@usace.army.mil or address regular mail responses to: Regulatory Division U.S. Army Corps of Engineers New England District 696 Virginia Road Concord, Massachusetts 01742-2751. Should you have any questions or require additional information, please do not hesitate to contact me. Thank you, Julia A. Novotny Project Environmental Scientist O 781.614.9989 C 203.841.8960 300 TradeCenter Suite 5580 Woburn, MA 01801-7433 TIGHEBOND.COM 1 Julia Novotny From:Microsoft Outlook To:David.S.Robinson@mass.gov; thpo@wampanoagtribe-nsn.gov; 106review@mwtribe-nsn.gov; david.weeden@mwtribe-nsn.gov; narrawamp@gmail.com Sent:Thursday, February 19, 2026 2:31 PM Subject:Relayed: Project Notification Form - Craigville Beach Road Bridge (Barnstable, MA) Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: David.S.Robinson@mass.gov (david.s.robinson@mass.gov) thpo@wampanoagtribe-nsn.gov (thpo@wampanoagtribe-nsn.gov) 106review@mwtribe-nsn.gov (106review@mwtribe-nsn.gov) david.weeden@mwtribe-nsn.gov (david.weeden@mwtribe-nsn.gov) narrawamp@gmail.com (narrawamp@gmail.com) Subject: Project Notification Form - Craigville Beach Road Bridge (Barnstable, MA) 1 Julia Novotny From:Bettina Washington <thpo@wampanoagtribe-nsn.gov> To:Julia Novotny Sent:Friday, February 20, 2026 11:43 AM Subject:Read: Project Notification Form - Craigville Beach Road Bridge (Barnstable, MA) Your message To: Bettina Washington Subject: Project Notification Form - Craigville Beach Road Bridge (Barnstable, MA) Sent: Thursday, February 19, 2026 2:30:45 PM (UTC-05:00) Eastern Time (US & Canada) was read on Friday, February 20, 2026 11:42:03 AM (UTC-05:00) Eastern Time (US & Canada).