HomeMy WebLinkAboutBarrett_Complete NOI Application_2026-08-25_SUB(1)Invasive Management
Plan and Narrative
88 Route 6A, Suite 2B
Sandwich MA
508.477.1346
info@crawfordlm.com
WWW.CRAWFORDLM.COM
PREPARED FOR
Barrett Residence
52 Caillouet Lane
Osterville, MA 02655
DATE
August 24, 2026
Salt Marsh Restoration Protocol
2
PROJECT AREA DESCRIPTION
The proposed project is located at 52 Caillouet Lane in Osterville, MA, adjacent to East Bay. Resource areas
include a salt marsh with associated buffers, as well as flood zones: X (Min. Flood Hazard) FEMA Zone VE
Elevation 16, and FEMA Zone AE Elevation 12. There is also a small (fragment) state bank within the outer
Buffer zone to the marsh. This Invasive Management Plan and accompanying Restoration Plan was created to
restore of wetland resource areas including flood zone and salt marsh.
The proposed limited ecological restoration strategy by Crawford Land Management addresses invasive
species within the salt marsh, parts of which are heavily invaded mostly with Phragmites australis (Common
Reed). The general locations of these proposed restoration areas are outlined on the aerial photograph below
and also on the Salt Marsh Restoration Plan dated 7/28/2026 by Crawford Land Management.
PROPOSED RESTORATION / PHRAGMITES TREATMENT AREA
The existing salt marsh is currently inundated with invasive Phragmites australis (Common Reed). The areas
with the most dense populations are diagrammed on the Restoration Plan. There are several large areas
of healthy salt marsh grasses and colonies of Marsh Elder (Iva frutescens) and High Tide Bush (Baccharis
halimifolia) which may eventually be overtaken by the Phragmites if it is left untreated.
Image:
Aerial photograph of 52 Caillouet
Lane from Google Earth Imagery
2026 Airbus, Maxar Technologies,
Map Data 2026 Google
HEAVILY INVADED AREAS OF SALT MARSH(MOSTLY PHRAGMITES)
SPORADIC PRESENCE OF INVASIVE SPECIES
3
This project proposes the removal and treatment of Phragmites to elimate the existing colonies and manage
incursions over the next several growing seasons. Treatment protocol as well as applicator and oversight
notes are outlined on the Phragmites Eradication Plan, attached.
Dense populations of Phragmites australis and other state listed invasive species are invading the salt marsh
and encroaching on adjacent meadow and woodland areas. Photos: Crawford Land Management (6-11-2026)
4
PHRAGMITES (COMMON REED) ERADICATION PLAN AND PROTOCOL
The eradication of the common reed (Phragmites australis) is proposed to prevent it from spreading within
the wetland area and adjacent plant communities. To remove and manage incursions of Phragmites on the
property, the use of herbicide treatments will be coupled with mowing/or cutting.
APPLICATOR AND OVERSIGHT NOTES
• All herbicide treatments will be completed by Massachusetts state-licensed and insured
pesticide applicators.
• Any machine work will be completed by a state licensed and insured machine operator.
MANAGEMENT ACTIVITY TIME LINE
Initial Treatment (Late Summer/Early Fall 2026)
For the initial treatment, Phragmites will be allowed to grow to its full growth potential, undisturbed. Phrag-
mites will be treated in the latter half of summer depending on environmental conditions.
Using 100% bio-degradable jute/twine, groupings of Phragmites will be bundled and tied off, leaving bun-
dles in the treatment area. The tops of the bundles will be cut off and an EPA aquatic approved herbicide
with the active ingredient Glyphosate will immediately be applied to all cut stems. Stalks too small to bundle
will either be treated with a low-volume foliar method, or wiped with tongs/sponges. Phragmites will then be
allowed to take up and translocate the herbicide through the root system into the winter. No Mowing is pro-
posed for the initial treatment phase.
Ongoing Maintenance and Monitoring (2026-2029)
Follow up treatments will need to be done throughout the summer months using the low-volume foliar
method or cut and wipe method, as treated Phragmites often grows back after the first treatment in a witch-
broom form.
The restoration area should also be monitored for both cool season and warm season invasive, non-
native and aggressive species that have germinated from the existing seed bank, or re-sprouted from roots
remaining in the soil. These species will be removed through low volume foliar or cut and wipe treatments or
by hand weeding.
In the winter to early spring the Phragmites will be cut down and treatments will be repeated until Phragmites
has been eradicated from the treatment area. Phragmites will be cut to a height of 4” which will minimize
impacts on native vegetation and small animals. This height also eliminates soil disturbance, which can
spread rhizomes, thus creating new plants. The purpose of the cutting is to remove dead stalks and thatch
from the area as to allow sunlight to reach the native seed bank and allow for germination. The cutting
also increases the effectiveness of additional herbicide treatments as only new live growth is present to be
treated, although care can be taken not to include the dead stalks within the bundles. Any mowing or cutting
should be ideally carried out before or after bird nesting seasons. Bird nesting season can vary depending on
locale.
ENFORCEMENT ORDER AND MEADOW AREA RESTORATION PROTOCOL AND TIMELINE (FOR
SPECIES OTHER THAN PHRAGMITES AUSTRALIS):
INITIAL INVASIVE MANAGEMENT (LATE SUMMER / FALL 2026)
• Treat and remove all approved vegetation using an appropriate herbicide (Glyphosate-based or Triclopyr-
based) using a cut and wipe method.
• Vegetation to be flush cut and treated leaving the roots in place to maintain soil stability.
• Seed any exposed soils within the mitigation / restoration area with the specified seed mixes to establish a
native vegetative groundcover.
• Rejuvenate any native shrub or tree species uncovered in the restoration area with regenerative pruning
techniques to encourage new, dense growth. If the structure of the specimen is compromised due to
repetitive improper cutting techniques, the specimens will be flush cut and managed as a stump sprout.
PLANT INSTALLATION: (BETWEEN SEPTEMBER 1, 2026 AND OCTOBER 31, 2026)
• Per Enforcement order of Conditions, the property owner shall place strawbales, backed by trenched in
siltation fencing, along the edge of the disturbance prior to planting.
• Plantings to be installed after invasive vegetation has achieved a minimum of approx. 80% eradication.
• Plantings to be installed in spring or fall unless irrigation is installed immediately after planting.
• Existing and proposed plant locations shown on the plan are approximate. New plant locations may be
slightly adjusted in the field to accommodate existing, healthy native vegetation.
• Per Enforcement Order, locations of trees to be planted shall be identified in the field by stakes.
• Trees shall be transported on dollies to avoid heavy equipment in the 50' buffer.
• Mulch will not be used in the restoration / mitigation areas except immediately under and within the drip
line of an individual plant and only for initial establishment of plantings.
SUPPLEMENTAL IRRIGATION:
• Install a temporary, above-ground irrigation system to provide supplemental water to woody plantings for
2-3 growing seasons or until plants are fully established.
MAINTENANCE (3 SEASONS MIN.): (FALL 2026 TO FALL 2029)
• Monitor restoration area and perform maintenance cut and wipe treatments, selective foliar applications, or
hand weed invasive, non-native, and aggressive species that have germinated from existing seed bank, or re-
sprouted from roots after removal.
• Mow/cut seeded areas in early spring and/or in June to help establish warm season grasses, if necessary.
• Site will be monitored and maintained throughout the year for both cool season and warm season invasive,
non-native, and aggressive species.
• Per Enforcement Order Conditions List, annual reports with photos shall be submitted by a wetland
specialist or certified arborist or horticulturalist or Certified Ecological Restoration Practitioner (CERP
landscape contractor for 3 years, starting once the plantings have been in for one growing season. Report
due dates: Oct 31, 2026, 2027, 2028.
• Per Enforcement Order Conditions List, any trees or shrubs that have died or are listed in poor health in
each of the annual reports filed during the 3 year period shall be replaced in kind.
• Additional clearing or pruning of vegetation within the restoration planting area is prohibited except for the
removal of storm damaged limbs and branches which may impact the newly planted specimens.
APPLICATOR & OVERSIGHT REQUIREMENTS:
• All machine work will be completed by an insured operator with appropriate hoisting and hydraulics
licenses.
• Herbicide application will only be completed by Massachusetts state-licensed and -insured pesticide
applicators knowledgeable with invasive, non-native, and native plant identification, both in-leaf and bare-
twig.
• Any tree work will be completed and/or overseen by an ISA or MA Certified Arborist.
• All restoration work will be overseen by a Certified Ecological Restoration Practitioner (CERP).
• Contractor must be able to provide a proven track record of successful stabilization and restoration projects
1
Performance Standards
Narrative
PREPARED FOR
BARRETT RESIDENCE
52 CAILLOUET LANE
OSTERVILLE, MA 02655
DATE
AUGUST 24, 2026
88 Route 6A, Suite 2B
Sandwich MA
508.477.1346
info@crawfordlm.com
WWW.CRAWFORDLM.COM
2
310 CMR 10.00: The Wetlands Protection Act
Coastal Wetlands
10.32: Salt Marshes
(3) A proposed project in a salt marsh, on lands within 100 feet of a salt marsh, or in a body of water
adjacent to a salt marsh shall not destroy any portion of the salt marsh and shall not have an adverse effect
on the productivity of the salt marsh. Alterations in growth, distribution and composition of salt marsh
vegetation shall be considered in evaluating adverse effects on productivity. 310 CMR 10.32(3) shall not be
construed to prohibit the harvesting of salt hay.
The proposed activity will not destroy any portion of the salt marsh and will not have an adverse
effect on the productivity of the salt marsh. The removal of invasive species will enhance the salt marsh and
increase the productivity of the salt marsh.
(4) Notwithstanding the provisions of 310 CMR 10.32(3), a small project within a salt marsh, such as an
elevated walkway or other structure which has no adverse effects other than blocking sunlight from the
underlying vegetation for a portion of each day, may be permitted if such a project complies with all other
applicable requirements of 310 CMR 10.21 through 10.37.
No structures are proposed within the salt marsh.
(5) Notwithstanding the provisions of 310 CMR 10.32(3), a project which will restore or rehabilitate a salt
marsh, or create a salt marsh, may be permitted in accordance with 310 CMR 10.11 through 10.14, 10.24(8),
and/or 10.53(4).
The purpose of the proposed activity is to restore and rehabilitate the salt marsh.
(6) Notwithstanding the provisions of 310 CMR 10.32(3) through (5), no project may be permitted which will
have any adverse effect on specified habitat sites of Rare Species, as identified by procedures established
under 310 CMR 10.37.
The project area is not located within Estimated/Priority Habitat for Rare Species according to the
Massachusetts Natural Heritage & Endangered Species Program (MANHESP). The proposed
restoration will enhance habitat for wildlife.
3
Town of Barnstable: Chapter 704
Regulation Governing Activity in the 100 ft. Buffer Zone Under Notice of Intent Applications
704-6 Applicability
A. This regulation shall not be construed to preclude the following activities, any of which may be permitted
at the Commission's discretion, and without accompanying requirement for mitigation planting:
(1) Access paths;
N/A Does not apply
(2) The following maintenance activities: vista pruning; invasive species control; repair/replacement
of subsurface septic disposal systems; or removal/replacement of underground fuel tanks or 21e
cleanup.
Invasive species control is proposed
(3) Projects undertaken by a government agency that can be demonstrated to provide an overriding
public benefit, such as the area-wide improvement of water quality or the reduction of ground or
surface water pollution.
N/A Does not apply
(4) The construction or reconstruction, without expansion or intensification of use, of all or a portion
of a previously existing structure which utilizes a preexisting foundation or footprint without need of
additional excavation or filling, and either: is approved, or was constructed prior to 1973.
N/A Does not apply
(5) The construction of water-dependent facilities as defined in § 704-2 herein.
N/A Does not apply
Caillouet Lane
PHRAGMITES TO BE TREATED AND
REMOVED THROUGHOUT ENTIRE
SALT MARSH. AREAS IN ORANGE
INDICATE LOCATIONS OF DENSE
POPULATIONS
X (MIN. FLOOD HAZARD) FEMA ZONE VE ELEV 16
MARSH AREA
RESTORATION
PROPERTY LINE PROPERTY LINE
PROPERTY LINE
PROPERTY
LI
N
E
POOL
#52 2 STY
W/F DWELLING
EXISTING LAWN
TO REMAIN
ESTIMATED AREA OF
DENSE PHRAGMITES
TO BE REMOVED
ESTIMATED AREA OF
DENSE PHRAGMITES
TO BE REMOVED
ESTIMATED AREA OF
DENSE PHRAGMITES
TO BE REMOVED
100' BUFFER50' BUFFEREXTENT OF CONSERVATION JURISDICTIONSTATE BANKPATIO
PATIO
MARSH AREA
RESTORATION
WETLAND DELINEATION BY ECR (2026)
SCALE:
DATE:
All rights reserved. The drawings, designs, and
ideas embodied therein are property of
CLM/JS and shall not be copied, reproduced,
or disclosed in connection with any work other
than the project for which they have been
prepared, in whole or part, without prior
written authorization of CLM/JS.NO:DATE:REVISION:BY:88 Route 6A, Suite 2B | Sandwich, MA 02563
www.crawfordlm.com | 508.477.1346
www.jenickstudio.com | 508.477.1346
52 CAILLOUET LANEBARRETT RESIDENCE8/24/2026
1" = 20'-0"
1 OF 1 SALT MARSH RESTORATION PLANOSTERVILLE, MA (BARNSTABLE)ENGINEER/SURVEYOR
NOT FOR CONSTRUCTION
(ISSUED FOR CONSERVATION
PERMITTING)
Sullivan Engineering
& Consulting, Inc.
711 Main St
Osterville, MA 02655
508.428.3344
sullivanengin.com
CLM WILL NOT PROVIDE
OVERSIGHT OR CERTIFICATION
FOR ANY WORK COMPLETED
BY OTHERS, NOR DOES CLM
TAKE ANY RESPONSIBILITY FOR
WORK COMPLETED BY OTHERS.
APPROX. LOCATION OF
EXISTING TREE (NOT SURVEYED)
ESTIMATED AREAS OF DENSE
PHRAGMITES AUSTRALIS (COMMON
REED) TO BE TREATED AND
REMOVED (
WETLAND / MARSH RESTORATION:
REMOVE SPORADIC OCCURENCES
OF INVASIVE SPECIES. ALL EXISTING
NATIVE PLANTINGS TO REMAIN.
LANDSCAPE LEGENDGENERAL MARSH RESTORATION NOTES:
(NOT INCLUDING PHRAGMITES)
INITIAL INVASIVE MANAGEMENT :
Treat and remove all approved vegetation using an appropriate herbicide
(Glyphosate-based or Triclopyr-based) using a cut and wipe method.
Vegetation to be flush cut and treated leaving the roots in place to maintain soil stability.
Seed any exposed soils within the mitigation / restoration area with the specified seed
mixes to establish a native vegetative groundcover.
Rejuvenate any native shrub species uncovered in the restoration area with regenerative
pruning techniques to encourage new, dense growth. If the structure of the specimen is
compromised due to repetitive improper cutting techniques, the specimens will be flush
cut and managed as a stump sprout.
MAINTENANCE (3 SEASONS MIN.):
Monitor restoration area and perform maintenance cut and wipe treatments, selective
foliar applications, or hand weed invasive, non-native, and aggressive species that have
germinated from existing seed bank, or re-sprouted from roots after removal.
Mow/cut seeded areas in early spring and/or in June to help establish warm season
grasses, if necessary.
Site will be monitored and maintained throughout the year for both cool season and
warm season invasive, non-native, and aggressive species.
Plan prepared under direct
supervision of:
NICK CRAWFORD (CRAWFORD
LAND MANAGEMENT)
(CERP #0385, EXP. 6/1/2030).
TOTAL ESTIMATED SQUARE FOOTAGE OF PHRAGMITES TREATMENT:
21,150 SF. SEE INVASIVE MANAGEMENT PLAN AND NARRATIVE BY
CRAWFORD LAND MANAGEMENT FOR PHRAGMITES TREATMENT
PROTOCOL.
SEE INVASIVE MANAGEMENT PLAN AND NARRATIVE BY CRAWFORD LAND MANAGEMENT
FOR ADDITIONAL PROTOCOL
20 10 0 20 60
PHRAGMITES (COMMON REED)
ERADICATION NOTES
The eradication of the common reed (Phragmites australis)
is proposed to prevent it from spreading within the wetland
area and adjacent plant communities. To remove and
manage incursions of Phragmites on the property, the use
of herbicide treatments will be coupled with mowing/or
cutting.
MANAGEMENT ACTIVITY TIME LINE
Initial Treatment (Late Summer / Early Fall
2026):
For the initial treatment, Phragmites will be allowed to grow
to its full growth potential, undisturbed. Phragmites will be
treated in the latter half of summer depending on
environmental conditions.
Using 100% bio-degradable jute/twine, groupings of
Phragmites will be bundled and tied off, leaving bun}dles in
the treatment area. The tops of the bundles will be cut off
and an EPA aquatic approved herbicide with the active
ingredient Glyphosate will immediately be applied to all
cut stems. Stalks too small to bundle will either be treated
with a low-volume foliar method, or wiped with
tongs/sponges. Phragmites will then be allowed to take up
and translocate the herbicide through the root system into
the winter. No Mowing is pro}posed for the initial treatment
phase.
Ongoing Maintenance and Monitoring
(2026-2029):
Follow up treatments will need to be done throughout the
summer months using the low-volume foliar method or cut
and wipe method, as treated Phragmites often grows back
after the first treatment in a witch-broom form.
The restoration area should also be monitored for both cool
season and warm season invasive, non-native and
aggressive species that have germinated from the existing
seed bank, or re-sprouted from roots remaining in the soil.
These species will be removed through low volume foliar or
cut and wipe treatments or by hand weeding.
In the winter to early spring the Phragmites will be cut down
and treatments will be repeated until Phragmites has been
eradicated from the treatment area. Phragmites will be cut
to a height of 4" which will minimize impacts on native
vegetation and small animals. This height also eliminates soil
disturbance, which can spread rhizomes, thus creating new
plants. The purpose of the cutting is to remove dead stalks
and thatch from the area as to allow sunlight to reach the
native seed bank and allow for germination. The cutting
also increases the effectiveness of additional herbicide
treatments as only new live growth is present to be treated,
although care can be taken not to include the dead stalks
within the bundles. Any mowing or cutting should be ideally
carried out before or after bird nesting seasons. Bird nesting
season can vary depending on locale.
APPLICATOR & OVERSIGHT REQUIREMENTS:
·All machine work will be completed by an insured operator
with the appropriate hoisting and hydraulics licenses.
·Herbicide application will only be completed by
Massachusetts state-licensed and -insured pesticide
applicators knowledgable with invasive, non-native, and
native plant identification, both in-leaf and bare-twig.
·Any tree work will be completed and/or overseen by an ISA
or MA Certified Arborist.
·All restoration work will be overseen by a Certified Ecological
Restoration Practitioner (CERP).
·Contractor should be able to provide a proven track record
of successful stabilization and restoration projects in New
England.