HomeMy WebLinkAboutAtt Kendrick summary9/9/2026
I am writing to address the timeliness of the appellant’s appeal, filed pursuant to G.L. c. 40A,
§§ 8 and 15. For the reasons that follow, in my opinion, the appeal is untimely.
The appellant is direct abutter to 210 North Street. On March 12, 2025, the Building
Commissioner issued a building permit to the owner of 210 North Street for the removal of
the roof from an existing one-story building, and the construction of additional stories in the
existing footprint. More than one year later, on April 2, 2026, the appellant emailed the
Building Commissioner a purported request for zoning enforcement under G.L. c. 40A, §
7. The Building Commissioner denied the enforcement request via correspondence dated
April 29, 2026 on grounds that the so-called enforcement demand did not identify any zoning
violations. Rather, the alleged violations derived from the Massachusetts Building Code. The
Building Commissioner also noted that the enforcement request was untimely because it had
been more than thirty days since the building permit had been issued.
Pursuant to G.L. c. 40A, §§ 8, an aggrieved party may appeal an “order or decision” of the
building commissioner to the zoning board of appeals. Under Chapter 40A, Section 15, any
appeal under Section 8 must be taken within thirty days from the “order or decision” being
appealed. For purposes of Sections 8 and 15, a building permit is an “order or decision” of
the building commissioner. For a building permit, the date of the “order or decision” is the
date the building permit was issued—here March 12, 2025.
Massachusetts courts have consistently held that where an aggrieved party has adequate
notice of a building permit’s issuance, they are required to appeal to the zoning board of
appeals within thirty days of the date the permit was issued. An appellant who had adequate
notice of the issuance of a building permit cannot use the enforcement mechanism available
under Section 7 to circumvent the thirty-day appeal period for appealing the issuance of a
building permit. In such circumstances, a later appeal to the zoning board of appeals from a
denial of a request for enforcement made pursuant to G.L. c. 40A, § 7, is not an available
alternative remedy. Here, the appellant is a direct abutter to the development at
issue. Further, by the time the appellant submitted their appeal to the Building
Commissioner, construction at 210 North Street was nearly complete. Accordingly, the
appellant was aware of the issuance of the building permit for well more than thirty days
before they submitted their enforcement demand to the Building Commissioner. As such,
their appeal should be dismissed.