HomeMy WebLinkAboutBeacon Wind CP Invitation & Notification Signature
December 9, 2022
RE: Invitation to Consult on the Beacon Wind Project and Notification of Using the National
Environmental Policy Act (NEPA) Process to Fulfill Section 106 Obligations; Response
Requested by No Later Than 30 Days of Receipt of This Letter
Dear Potential Consulting Party,
The Bureau of Ocean Energy Management (BOEM), serving as lead Federal agency under the
National Historic Preservation Act (NHPA) and the National Environmental Policy Act (NEPA),
is reviewing the Construction and Operation Plan (COP) submitted by Beacon Wind, LLC
(Beacon Wind) proposing the Beacon Wind Project (the Project). BOEM has determined that
the construction, operation, and maintenance, and eventual decommissioning of the Project
constitutes an undertaking subject to Section 106 of the NHPA (Section 106).
If approved, the Project will consist of up to 155 wind turbine generators in the designated
Renewable Energy Lease Area OCS-A 0520 (Lease Area), up to two offshore substations, inter-
array cables linking the individual turbines to the offshore substations, substation interconnector
cables linking the substations to each other, offshore export cables, an onshore export cable
system, two onshore points of interconnection. The Lease Area covers approximately 128,811
acres and is located approximately 20 miles south of Nantucket, Massachusetts and 60 miles east
of Montauk, New York. Beacon Wind proposes to develop the entire Lease Area in two wind
farms, known as Beacon Wind 1 and Beacon Wind 2. Each wind farm would gather the
associated turbines to a central offshore substation and deliver the generated power via a
submarine export cable to an onshore substation for final delivery into the local utility
distribution system at the selected point of interconnection. The offshore export cables would be
buried below the seabed surface within Federal and state waters. The Project location is depicted
on Enclosure 1.
BOEM has assigned ICF as the third-party contractor to facilitate the Section 106 consultation
process. All Federal oversight and decisions will remain with BOEM. ICF’s role in this Section
106 review is administrative; ICF will coordinate communication with the consulting parties;
facilitate distribution of BOEM-approved documents; provide technical assistance; and arrange
and lead meetings, webinars, or calls with consulting parties.
With this letter, BOEM invites you to be a consulting party to the Project and its potential to
affect historic properties. Consulting parties have certain rights and obligations under the NHPA
2
and its implementing regulations at 36 Code of Federal Regulations (CFR) Part 800 and NEPA
and its implementing regulations at 40 CFR Parts 1500–1508. These regulations provide for a
review process, known under the NHPA as Section 106 review. The regulations at 36 CFR
800.8(c) provide for the use of the NEPA process to fulfill a Federal agency’s NHPA Section
106 review obligations in lieu of the procedures set forth in 26 CFR 800.3 through 800.6.
BOEM intends to use the NEPA process for NHPA Section 106 purposes in lieu of the
procedures set forth in 36 CFR 800.3 through 800.6 for the Project. The Section 106 process and
NEPA substitution are described at: https://www.achp.gov/digital-library-section-106-
landing/citizens-guide-section-106-review and https://www.achp.gov/integrating_nepa_106,
respectively. As part of this process, consultation with appropriate federally-recognized tribes
will occur during the preparation of the Project Environmental Impact Statement (EIS) in
accordance with NEPA regulations at 36 CFR 800.8(c)(1), during NEPA scoping, environmental
analysis, and preparation of NEPA documents. To aid those consulting parties who may not be
familiar with the NEPA substitution process, BOEM has developed a National Environmental
Policy Act Substitution for Section 106 Consulting Party Guide, which is enclose for your
reference (Enclosure 2).
By becoming a consulting party, you will be actively informed of steps in the review process,
including public meetings, and your views will be actively sought. If you would like to be a
consulting party to this project, please respond to Alice Muntz at BeaconWind106@icf.com or
804-614-3426.
Please submit your request to become a consulting party no later than 30 days of receipt of this
letter. While you may also request to be a consulting party at a later date, the Project may
advance without your input and your opportunity to fully comment on each step of the process
may be affected. If you are requesting consulting party status, designate one primary
representative and one alternate from your organization to receive correspondence and attend
meetings; please provide contact information for any such designees. We also request that you
indicate your preferred correspondence method: hard copy correspondence by mail, electronic
correspondence by email, or both.
Please contact me, the BOEM Section 106 Project Lead, at Marissa.Moshier@boem.gov or 571-
373-0759 if you require additional information. We look forward to working with you.
Sincerely,
Marissa Moshier
BOEM Section 106 Lead
Environment Branch for Renewable Energy
Office of Renewable Energy Programs
Enclosure 1
National Environmental Policy Act (NEPA) Substitution for Section 106 Consulting Party Guide
Updated August 4, 2021
Page 1 of 4
I. Introduction
The regulations at 36 Code of Federal Regulations (CFR) § 800.8 provide for use of the National
Environmental Policy Act (NEPA) process to fulfill a Federal agency’s National Historic Preservation Act
(NHPA) Section 106 review obligations in lieu of the procedures set forth in 36 CFR § 800.3 through
800.6. This process is commonly known as “NEPA substitution for Section 106” and the Bureau of Ocean
Energy Management (BOEM) plans to use the process and documentation required for the preparation
of an Environmental Impact Statements (EIS) and Record of Decision (ROD) to comply with Section 106
on all future offshore wind project Construction and Operations Plans (COPs) for which you may be
invited to participate as a Consulting Party.
This document is intended to act as a guide for Consulting Parties on the “NEPA substitution for Section
106” process to aid understanding of how this process works, how it compares to BOEM’s traditional
Section 106 process approach, and where in BOEM’s NEPA substitution process you will be involved.
More information regarding integration of NEPA and Section 106 reviews can be found at:
https://www.achp.gov/integrating_nepa_106.
II. Why is BOEM implementing a NEPA substitution process?
BOEM is using the NEPA substitution process under 36 CFR § 800.8(c) as part of a multi-faceted
approach to meet the Office of Renewable Energy Program’s needs. With a large number of COPs
submitted for BOEM’s review, there is an increased need for streamlining and efficiency in the NEPA
process. In addition to efficiency, BOEM anticipates several other benefits from implementing the NEPA
substitution process for its Section 106 review of COPs, including the following:
• Earlier and more direct input from Consulting Parties into the development and selection of
alternatives and avoidance, minimization, or mitigation measures.
• Better integration of comments and responses, especially concerning natural and cultural
resources, historic properties, visual effects, environmental justice issues, and traditional
cultural practices.
• Providing a more holistic and meaningful approach to government-to-government consultation
with Indian Tribes, as defined at 36 CFR § 800.16(m).
III. What are the major differences between the standard Section 106 and the “NEPA substitution
for Section 106” approaches?
The key differences between the standard approach for Section 106 as set out in 36 CFR § 800.3 through
800.6 and how BOEM will comply with the 36 CFR § 800.8(c) approach for Section 106 review of COPs
include the following:
• BOEM will seek formal consultation earlier, during significant NEPA milestones (at scoping and
after publication of the Draft EIS); parties may comment throughout the development of the EIS.
• The identification of historic properties, finding of effects, and resolution of adverse effects will
be documented in the Draft and Final EIS rather than in a separate Section 106 Finding
National Environmental Policy Act (NEPA) Substitution for Section 106 Consulting Party Guide
Updated August 4, 2021
Page 2 of 4
document. BOEM will provide the reports documenting the identification of historic properties
along with the Draft EIS. These include:
o the Marine Archaeological Resources Assessment,
o the Terrestrial Archaeological Resources Assessment, and
o the Report of Visual Effects on Historic Properties, along with viewshed analyses and
visual simulations.
• Resolution of adverse effects may be documented in a binding ROD and as conditions of COP
approval. This differs from the standard Section 106 process in which a Memorandum of
Agreement (MOA) is developed to resolve adverse effects. The combination of BOEM’s binding
ROD and application of conditions of COP approval provide effective and equivalent legal
requirements on itself and on the lessee.
• BOEM’s government-to-government consultation responsibilities to Federally recognized tribes
remain unchanged and efforts to consult with tribes are likely to expand under NEPA
substitution.
Below, the graphic on the left illustrates the standard approach to NEPA and NHPA Section 106 review,
showing the major milestones in each process when executed in parallel. The graphic on the right shows
the “NEPA substitution for Section 106” approach, and how these milestones will be combined.
Standard Section 106 Process
“NEPA Substitution for Section 106” Process
1. Initiate the
Process
2. Identify
Historic
3. Assess
Adverse Effects
4. Resolve
Adverse Effects
Significant Environmental
Effects May or Will Occur
Notice of Intent
Public Scoping and Public
Involvement
DEIS
Public Review and Comment
and Public Involvement
FEIS
Public Availability
ROD
Agreement
(MoA/PA) or
Council
Comment
NHPA
NEPA EIS NEPA Substitution
1. Initiate the Process
Significant Environmental Effects May or Will Occur
Notice of Intent
Public Scoping and Public
2. Identify Historic Properties
3. Assess Adverse Effects DEIS
4. Resolve Adverse Effects
Public Review and Comment and Public Involvement
FEIS
Public Availability
ROD and Conditions of COP Approval
National Environmental Policy Act (NEPA) Substitution for Section 106 Consulting Party Guide
Updated August 4, 2021
Page 3 of 4
IV. How will BOEM meet the requirements of 36 CFR § 800.8(c) under the “NEPA substitution for
Section 106” process?
As provided in 36 CFR § 800.8(c), four standards must be met:
1. The first standard is to identify Consulting Parties and invite them to participate in the process.
Under the “NEPA substitution for Section 106” process, BOEM will identify Consulting Parties
for each project pursuant to 36 CFR § 800.3(f) prior to or with issuance of its Notice of Intent
(NOI) to prepare an EIS. During the NEPA scoping period BOEM will send a formal letter to these
parties inviting them to participate in the process. These letters will also state that BOEM
intends to use the NEPA process for Section 106 purposes as laid out in 36 C.F.R. § 800.8(c) to
comply with Section 106 in lieu of 36 CFR § 800.3 through § 800.8.
2. The second standard is to identify historic properties and assess the effects of the undertaking
in a manner consistent with 36 CFR § 800.4 through § 800.5. Under NEPA substitution, the Draft
EIS will identify historic properties and assess the effects of the undertaking using the lessee’s
cultural resources reports from the COP as well as Consulting Party and public input provided
during the scoping period. BOEM’s regulations require that lessees include in their COPs
information about historic properties, any adverse effects from their project on these historic
properties, and how they propose to resolve those adverse effects (through avoidance,
minimization, and mitigation measures). This information will be sent to Consulting Parties with
the Draft EIS for their review, so that final measures may be developed in consultation. The
Final EIS will reflect continued consultations, as well as Consulting Party comments received on
the Draft EIS.
3. The third standard is to consult with Consulting Parties during NEPA scoping, environmental
analysis, and preparation of the EIS regarding the effects of the undertaking on historic
properties. Under the “NEPA substitution for Section 106” process as laid out in 36 CFR §
800.8(c), formal consultation will occur during the scoping period as well as during the public
comment period after publication of the Draft EIS. However, Consulting Party comments will be
accepted at any point during the preparation of the EIS. Additionally, if necessary, Section 106-
specific consultation meetings with Consulting Parties can be arranged. Comments submitted
by Consulting Parties during NEPA comment periods will help inform the effects analysis for
historic properties in the Draft and Final EIS.
4. The fourth standard is to involve the public in accordance with BOEM’s NEPA procedures and
develop alternatives and proposed avoidance, mitigation, and minimization measures in
consultation with Consulting Parties. Proposed measures to avoid, minimize, or mitigate any
adverse effects on historic properties will be first presented in the lessee’s COP, which
Consulting Parties will be able to review, as well as through consultation with Consulting Parties
during scoping and the Draft EIS comment period. These measures will be further developed
and refined in consultation, and those changes will be reflected in the Draft and Final EIS. Public
involvement will take place during the NEPA comment periods and through standard public
participation practices for the NEPA process, including posting of relevant information on
BOEM’s website and through Federal Register notices.
National Environmental Policy Act (NEPA) Substitution for Section 106 Consulting Party Guide
Updated August 4, 2021
Page 4 of 4
V. When and How do I provide input?
Opportunities for formal and informal consultation will occur throughout the development of the EIS.
Consulting Parties will be formally invited to submit comments twice during this process: first, during
the NEPA Scoping Period (so that comments can be incorporated into the Draft EIS) and second, during
the Draft EIS public comment period (so that comments can be incorporated into the Final EIS). While
comments can be submitted by Consulting Parties at any time, we encourage you to submit these during
the scoping comment period, thus allowing BOEM to consider these comments in the development of
the Draft and Final EIS.
Furthermore, BOEM is encouraging lessees to coordinate with Consulting Parties prior to their COP
submission to request input as they develop their proposed avoidance, minimization, and mitigation
measures.
VI. Will sensitive information regarding historic properties or traditional practices or places
remain confidential under NEPA Substitution?
All sensitive information provided during the “NEPA substitution for Section 106” process will be treated
the same way it would have been under the standard Section 106 review process as set out in 36 CFR §
800.3 through 800.6. Please note that all comments submitted through the NEPA process are submitted
through regulations.gov and are available for viewing by the public. However, BOEM will provide a
different means for Consulting Parties to provide comments that contain sensitive information, if
requested. For Indian Tribes, as defined at 36 CFR § 800.16(m), BOEM’s Tribal Liaison Officers can
provide additional guidance on sharing sensitive information for Section 106 review purposes.
VII. What is the role of third-party contractors in the “NEPA substitution for Section 106” process?
A third-party contractor has been contracted to aid with the preparation of each EIS assessing the
environmental effects of a renewable energy COP. The lessee pays for the third-party contractor’s
services, but BOEM is responsible for providing all work direction as well as reviewing all work
performed by the third-party contractor. Third-party contractor support is essential so BOEM can meet
deadlines for multiple projects occurring simultaneously. Throughout the “NEPA substitution for Section
106” process you can expect to be contacted by the third-party contractor. The third-party contractor
will support BOEM by performing various administrative and logistical tasks, including but not limited to
coordinating communication with the consulting parties; distributing BOEM-approved documents;
providing technical assistance; and hosting and facilitating NEPA and/or NHPA meetings, webinars, and
calls with consulting parties. It is important to note that it is BOEM’s responsibility to comply with
Section 106 and all decisions and content of the Draft EIS, Final EIS, and ROD as well as other documents
are determined by BOEM.
Additionally, BOEM fully recognizes that the responsibility to consult with the appropriate federally
recognized tribes (as defined at 36 CFR 800.16(m)) is its own and cannot be delegated, per 36 CFR
Section 800.2(c)(4). Due to the special legal relationship between BOEM and federally recognized
Tribes, third party contractors will not participate in government-to-government consultations between
BOEM and federally recognized Tribes.