HomeMy WebLinkAbout4-21-2023 - Decommissing Estimate_WAKEBY REV 1Total System Module Count 8860
Racking Orientation 2 Up Vertical
Linear Feet of Racking 33648
Estimated Business Days to Demolish
(8 Man Crew - Rate of 300 modules & Associated Inverters or 500 Linear Feet of Racking/Day)49
Estimated Total Number of 40 Yard Dumpsters
(400 Modules/Miscellaneous Debris Per Container)23
Dumpster Disposal Cost
($600 per Container)13,800.00$
Cost for Journeymen Electrican (1 Worker/8-Hr Day)
(Prevailing Wage - $74/Hr)29,008.00$
Cost for Apprentice Laborers (8 Workers/8-Hr Day)
(Prevailing Wage - $62/Hr)194,432.00$
Heavy Equipment (Excavator & Rear Dumptruck for Removal/Transport)
($750/Day)36,750.00$
Estimated Mobilization & Site Repair
(2.5% of Costs)6,849.75$
Total Current Day Decommissioning Estimate 280,839.75$
810 WAKEBY ROAD SOLAR PROJECT
BARNSTABLE, MA
ADE Project 3064.04
February 1, 2023
Revised April 21, 2023
System Information Summary
Decommissioning Summary