HomeMy WebLinkAboutBCC_08.08.23_Hearing_Final (Reduced)08/08/2023
Barnstable Conservation CommissionNew England Wind 1 Connector
Avangrid Offshore Wind August 2023
2
Content
Holly Carlson Johnston, Associate, Epsilon Associates, Inc.
Jack Vaccaro, Senior Consultant, Epsilon Associates, Inc.
02 Project Description
03 Discussion and Q&A
Pat Johnson, Manager of External Affairs, Avangrid
0 1 Welcome & Project Overview
Hans van Lingen, Permitting Manager, Avangrid
Ken Fitzgerald, Senior Principal, Stantec
3
Project Overview
Key Project Facts
800+ MW
OCS-A 0534
Anticipated federal approval Q1 2024
Anticipated 2027
100% Avangrid
40+ miles from Barnstable
West Barnstable
Capacity
Federal lease area
Permitting status
Commercial operation
Ownership
Distance to shore
Interconnection point
Park City
Wind
4
Project Benefits
800 + Megawatts (MW) of clean, renewable energy delivered to the New England grid,
powering approximately 400,000 homes and businesses
Reduces greenhouse gas emissions by 1.5 9 million US tons per year, the equivalent of
taking over 310,000 cars off the road
Creation of 4,700 direct, full -time equivalent (FTE) job -years across MA and CT
Improving grid reliability and delivering clean power locally to Cape Cod
5
Project Benefits in Barnstable
Host Community Agreements and Tax Revenue
–Signed Host Community Agreement (HCA) with the Town of
Barnstable in 2022
–Includes host community fees of $16 million
–Avangrid will be one of the largest taxpayers to the Town of
Barnstable, West Barnstable Fire District, and COMM Water
District, with little demand for town services
Coordination on Sewer Work
–Coordination with Barnstable DPW to install duct bank with
t he Town of Barnstable’s sewer lines to advance the Town’s
sewer project and defray associated costs and disruption
Minimizing Disruption
–Parking lot and in-road work limited to non-summer months
6
Project Overview & Offshore Export Cable Corridor
–800+ MW offshore wind energy
g eneration facility (federal
waters, 41 miles from Cape Cod
–Offshore export cable corridor
–6.6 miles in Barnstable waters
–Largely the same as for Vineyard
W ind Connector
–2 offshore export cables
–Target burial depth of 5-8 feet
–4-mile onshore export cable
route to proposed substation
–Interconnection at the West
Barnstable Substation
7
Landfall Site & Offshore-to-Onshore Transition
–Landfall site is the paved parking lot at Craigville Public Beach
–Horizontal directional drilling will avoid nearshore and beach
impacts
–Burial depth of ~40 feet at the High Tide Line
–Piping Plover Protection Plan, approved by NHESP, will avoid impacts
8
Onshore Transmission Route
–Route extends about 4 miles from the landfall site to proposed substation
–Follows existing roadway layouts (Craigville Beach Road, Main Street, Old
Stage Road, Shootflying Hill Road).
–4-mile-long buried concrete duct bank with splice vaults installed at every
15 0 0 -2500 feet.
–Trenchless crossing of Centerville River by microtunnel
–No permanent impacts to wetlands or rare species habitat
–Extensive coordination with the Town of Barnstable
–Variant 2 is no longer considered a viable alternative.
9
Buried Duct Bank
•Duct bank will have eight conduits for the six
o nshore conductors (two spares), with smaller
conduits for fiber optic communications
cables.
•Conduits typically arranged in a four wide by
two deep configuration and encased in
concrete.
•Trench will measure 9-11 f e e t wide at the road
surface (typically occupies one travel lane).
•Target burial depth is 3.5 feet but depth could
be reduced if needed to provide required
separation from other buried utilities.
10
Splice Vaults
-Cable splicing will be required at various
p oints along the onshore transmission route.
-Splice vault pairs will be installed at
intervals of every 1,500 to 2,500 feet along
the onshore route.
-At each splice vault location, the excavated
area will be expanded to approximately 20
feet wide by 50 feet long .
-Due to their size, the positions of the two
splice vaults will be staggered one in front
of the other in order to reduce the required
area of disturbance.
11
Onshore Transmission Route-Wetland Areas
Buffer zones of wetland resource areas in the vicinity of Wequaquet Lake.
Inland Bank/Beach
Freshwater Wetlands
Previously disturbed coastal resource areas between the cable landfall and
the Centerville River crossing
Barrier Beach System
Coastal Dune
LSCSF
Riverfront Area
Buffer zones of other coastal resource areas at the Centerville River crossing
Land Under the Ocean
Land Containing Shellfish
Salt Marsh
Coastal Bank
12
Onshore Duct Bank Route & Wetland Resource Areas
-Duct bank will be installed beneath
p avement of Shootflying Hill Road.
-Trench area to be restored at the end
o f each work day.
-Utility work in a buffer zone meets the
c riteria of "Minor Project"and is
exempt from regulations established
under Wetlands Protection Act (310
CMR 10.02).
-Barnstable Conservation Commission
retains jurisdiction over work in this
area under the town's Wetlands
Protection Bylaw (Ch. 237).
13
Onshore Duct Bank Route & Wetland Resource Areas
–Duct bank to be installed
b eneath the pavement
of Craigville Beach Road
–Southern portion of Craigville
Beach Road is within Barrier
Beach system and LSCSF .
–Small area of Coastal Dune
will be temporarily disturbed
by construction and will be
restored and replanted
following duct bank
installation.
14
Coastal Dune Restoration Plan
Coastal Dune between TJB vaults and
Craigville Beach Road.
–Narrow, isolated strip (approx. 420 square
f eet of impact)
–Dune restoration plan
15
Centerville River Crossing
–Reinforced concrete pipe installed
at least 10’ below river bottom by
micro -tunneling.
–Avoids impacts to the river and its
associated resource areas.
–Jacking shaft and staging area at 2
Short Beach Road (south side of
crossing) within the 200 -
foot Riverfront Area (RFA)
–Receiving shaft and transition
v aults will be installed within the
road layout north of the river and
beyond the 200 -foot RFA.
16
Centerville River Crossing (Microtunnel )
-Microtunneling is a remotely controlled pipe
jacking operation that utilizes a microtunnel
boring machine (MTBM).
-The MBTM is pushed into the earth by
hy draulic jacks mounted in the jacking shaft.
-Concrete casing pipe is lowered into the
shaft and inserted between the jacking
frame and the MTBM or previously jacked
pipe.
-Upon completion of the tunnel, equipment is
removed, the carrier pipeline is pulled
through the concrete casing pipe utilizing
rollers, and the annular space is grouted.
CUTAWAY VIEW OF A MICROTUNNEL SETUP
17
Centerville River Crossing (Slurry Recycling)
-Microtunneling requires the use of a
bentonite slurry to cool the drill bit, lubricate
the bore hole, and provide a medium to carry
drill cuttings back to the point of entry.
-The slurry/ cutting mix is then processed
using a separator plant to remove cuttings
from the slurry for transfer to large metal
bins for transport offsite
-The processed slurry is then recycled for
reuse in the microtunneling operation.
-Bins containing t he processed cuttings will
be staged at the Craigville Beach parking lot
prior to transport offsite.
CUTAWAY VIEW OF A MICROTUNNEL SETUP
18
Centerville River Crossing (Dewatering)
-Jacking shaft will be constructed to
be "water-tight" but some amount of
seepage of groundwater into the shaft is
anticipated
-Dewatering, or the removal of groundwater
f rom the shaft, will be required during the
tunneling operation.
-Water gathered from the shaft by the
d ewatering system will be discharged at an
upland location using on-site storage (frac
tanks) and appropriate filtering apparatus.
-Dewatering system will be monitored daily
f or turbidity as required under the EPA
Construction General Permit.
-Any use of catch basins for the discharge of
w ater will require town approval.CUTAWAY VIEW OF A MICROTUNNEL SETUP
19
Site Restoration Plan for 2 Short Beach Road
20
Visual Simulations for Site Restoration at 2 Short Beach Road
21
Visual Simulations for Site Restoration at 2 Short Beach Road
22
Visual Simulations for Site Restoration at 2 Short Beach Road
23
Visual Simulations for Site Restoration at 2 Short Beach Road
08/08/2023
New England Wind 1 Connector Thank You
Avangrid Offshore Wind August 2023