Loading...
HomeMy WebLinkAbout20220429_NOI_NE Wind Barnstable Part 1New England Wind 1 Connector Notice of Intent Massachusetts Wetland Protection Act (M.G.L. c. 131 §40) Chapter 237 of the Barnstable General Ordinance April 29, 2022 Prepared by Epsilon Associates, Inc. Submitted to Barnstable Conservation Commission 200 Main Street Hyannis, MA 02601 Submitted by Park City Wind LLC New England Wind 1 Connector Notice of Intent Massachusetts Wetlands Protection Act (M.G.L. c. 131 §40) Chapter 237 of the Barnstable General Ordinance Submitted to: BARNSTABLE CONSERVATION COMMISSION 200 MAIN STREET HYANNIS, MA 02601 Submitted by: PARK CITY WIND LLC 125 High Street, 6th Floor Boston, MA 02110 Prepared by: EPSILON ASSOCIATES, INC. 3 Mill & Main Place, Suite 250 Maynard, MA 01754 In association with: FOLEY HOAG LLP STANTEC, INC. GEO SUBSEA LLC April 29, 2022 Table of Contents 5526.10/New England Wind 1 Connector i Table of Contents Notice of Intent – Barnstable, MA Epsilon Associates, Inc. TABLE OF CONTENTS Notice of Intent - New England Wind 1 Connector, Barnstable, MA MASSACHUSETTS DEP, WPA FORM 3 TOWN OF BARNSTABLE NOI SUBMISSION CHECKLIST – Chapter 707 ATTACHMENT A PROJECT NARRATIVE 1 1.0 Introduction and Project Overview 1 1.1 Current Permitting Status 1 2.0 Project Purpose and Public Benefits 5 3.0 Existing Conditions within the Town of Barnstable 7 3.1 Offshore Export Cable Corridor (OECC) 7 3.1.1 Special, Sensitive, and Unique (SSU) Habitats 10 3.1.1.1 Hard/Complex Seafloor 10 3.1.1.2 Hard Bottom Habitat 11 3.1.1.3 Complex Bottom 11 3.1.1.4 Eelgrass 12 3.1.2 Shellfish Habitat 13 3.1.3 Rare Species Habitat 13 3.2 Craigville Public Beach Landfall Site 14 3.3 Onshore Transmission Route 15 3.3.1 Wetlands along the Duct Bank Route 15 3.3.2 Centerville River Crossing 16 4.0 Proposed Construction Activities and Impacts 17 4.1 Offshore Cable Installation 17 4.1.1 General Offshore Installation Methods 18 4.1.2 Anticipated Offshore Project Impacts 22 4.1.2.1 Cable Installation Tool 24 4.1.2.2 Anchoring 25 4.1.2.3 Cable Protection 27 4.1.2.4 Sand Wave Dredging 28 4.1.3 Sediment Dispersion and Turbidity 30 4.2 Onshore Construction 32 4.2.1 HDD Construction Methodology 32 4.2.1.1 HDD Construction Sequence and Schedule 33 4.2.1.2 Management of Drilling Fluids and HDD Contingency Plan for Seepage 36 4.2.2 Duct Bank Construction and Centerville River Crossing 38 4.2.2.1 Duct Bank Construction and Cable Installation 38 4.2.2.2 Centerville River Crossing 41 4.2.3 Anticipated Impacts to Coastal Resource Areas from Onshore Construction 44 5526.10/New England Wind 1 Connector ii Table of Contents Notice of Intent – Barnstable, MA Epsilon Associates, Inc. TABLE OF CONTENTS (Continued) 5.0 Regulatory Compliance 45 5.1 Water-Dependent Projects 46 5.2 Limited Project Status 46 5.3 Wetland Resource Areas and Performance Standards 47 5.3.1 Riverfront Area 48 5.3.2 Land Under the Ocean 48 5.3.2 Coastal Dune/Barrier Beach 51 5.3.3 Land Containing Shellfish 52 5.3.4 Salt Marsh 55 5.4 Interests Protected under Barnstable Wetlands Protection Bylaw 56 6.0 Mitigation Measures 58 ATTACHMENT B FIGURES Figure 1 Project Overview, USGS Locus Figure 2 Offshore Export Cable Corridor (Barnstable waters), NOAA Chart Figure 3 OECC and SSU Areas in Barnstable waters Figure 4 Shellfish Suitability Areas and the OECC in Barnstable waters Figure 5 Rare Species Habitats within Installation Corridor in Barnstable Waters Figure 6 NHESP-Mapped Habitat near Craigville Public Beach Landfall Site Figure 7 Wetland Resource Areas at Landfall Site and Centerville River Crossing Figure 8 Wetland Resources Areas – Onshore Transmission Route Figure 9 Centerville River Crossing – Microtunnel – Aerial View Figure 10 HDD Staging and Transition Vault/Joint Bay Locations, Craigville Public Beach Landfall Site Figure 11 Typical Duct Bank Cross-Sections ATTACHMENT C MARINE SURVEY CHART (BARNSTABLE WATERS) ATTACHMENT D PHOTOGRAPHS OF CRAIGVILLE PUBLIC BEACH LANDFALL SITE ATTACHMENT E DUCT BANK ENGINEERING PLANS ATTACHMENT F HDD ENGINEERING PLANS ATTACHMENT G PIPING PLOVER PROTECTION PLAN ATTACHMENT H MICROTUNNEL ENGINEERING PLANS ATTACHMENT I DUNE RESTORATION PLAN 5526.10/New England Wind 1 Connector iii Table of Contents Notice of Intent – Barnstable, MA Epsilon Associates, Inc. TABLE OF CONTENTS (Continued) ATTACHMENT J ABUTTER INFORMATION i List of Abutters i Affidavit of Service (to be finalized once hearing date is set) ATTACHMENT K WETLAND FEE TRANSMITTAL FORM ATTACHMENT L NHESP MESA DETERMINATION LIST OF TABLES Table 1-1 Environmental Permits, Reviews, and Approvals for the New England Wind 1 Connector and Park City Wind 1-3 Table 3-1 Temporary Wetland Resource Area Impacts for Centerville River Crossing Microtunnel (square feet) 3-17 Table 4-1 Impacts to Land Under the Ocean from Installation of Two Offshore Export Cables within Barnstable Waters 4-23 Table 4-2 Estimated Anchoring Impacts from Installation of 2 Offshore Export Cables in Barnstable Waters. 4-26 Table 4-3 Landfall Site HDD Installation Schedule 4-36 Table 4-4 Summary of Duct Bank and Trench Dimensions (feet) 4-39 WPA Form 3 Massachusetts DEP ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ Important: :KHQILOOLQJRXW IRUPVRQWKH FRPSXWHUXVH RQO\WKHWDENH\ WRPRYH\RXU FXUVRUGRQRW XVHWKHUHWXUQ NH\ 1RWH %HIRUH FRPSOHWLQJWKLV IRUPFRQVXOW \RXUORFDO &RQVHUYDWLRQ &RPPLVVLRQ UHJDUGLQJDQ\ PXQLFLSDOE\ODZ RURUGLQDQFH A. General Information 3URMHFW/RFDWLRQ Note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‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ A. General Information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uffer Zone & Resource Area Impacts (temporary & permanent) %XIIHU=RQH2QO\±&KHFNLIWKHSURMHFWLVORFDWHGRQO\LQWKH%XIIHU=RQHRID%RUGHULQJ 9HJHWDWHG:HWODQG,QODQG%DQNRU&RDVWDO5HVRXUFH$UHD ,QODQG5HVRXUFH$UHDV VHH&05LIQRWDSSOLFDEOHJRWR6HFWLRQ% &RDVWDO5HVRXUFH$UHDV  &KHFNDOOWKDWDSSO\EHORZ$WWDFKQDUUDWLYHDQGDQ\VXSSRUWLQJGRFXPHQWDWLRQGHVFULELQJKRZWKH SURMHFWZLOOPHHWDOOSHUIRUPDQFHVWDQGDUGVIRUHDFKRIWKHUHVRXUFHDUHDVDOWHUHGLQFOXGLQJ VWDQGDUGVUHTXLULQJFRQVLGHUDWLRQRIDOWHUQDWLYHSURMHFWGHVLJQRUORFDWLRQ ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ B. Buffer Zone & Resource Area Impacts (temporary & permanent) (cont’d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specify coastal or inland :LGWKRI5LYHUIURQW$UHD FKHFNRQH  IW'HVLJQDWHG'HQVHO\'HYHORSHG$UHDVRQO\ IW1HZDJULFXOWXUDOSURMHFWVRQO\ IW$OORWKHUSURMHFWV 7RWDODUHDRI5LYHUIURQW$UHDRQWKHVLWHRIWKHSURSRVHGSURMHFWVTXDUHIHHW 3URSRVHGDOWHUDWLRQRIWKH5LYHUIURQW$UHD D WRWDOVTXDUHIHHW E VTXDUHIHHWZLWKLQIWFVTXDUHIHHWEHWZHHQIWDQGIW +DVDQDOWHUQDWLYHVDQDO\VLVEHHQGRQHDQGLVLWDWWDFKHGWRWKLV12,"<HV1R :DVWKHORWZKHUHWKHDFWLYLW\LVSURSRVHGFUHDWHGSULRUWR$XJXVW"<HV1R &RDVWDO5HVRXUFH$UHDV 6HH&05  Note:IRUFRDVWDOULYHUIURQWDUHDVSOHDVHFRPSOHWHSection B.2.fDERYH ;&HQWHUYLOOH5LYHU ; VI ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ B. Buffer Zone & Resource Area Impacts (temporary & permanent) FRQW¶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aDFUHV WUHQFKVNLGVGUHGJLQJSURWHFWLRQDQFKRULQJQHDUVKRUHJURXQGLQJ  VTXDUHIHHW  FXELF\DUGVGUHGJHG F%DUULHU%HDFK ,QGLFDWHVL]HXQGHU&RDVWDO%HDFKHVDQGRU&RDVWDO'XQHVEHORZ G&RDVWDO%HDFKHV VTXDUHIHHW  FXELF\DUGVEHDFKQRXULVKPHQW H&RDVWDO'XQHV VTXDUHIHHW  FXELF\DUGVGXQHQRXULVKPHQW 6L]HRI3URSRVHG$OWHUDWLRQ 3URSRVHG5HSODFHPHQW LIDQ\  I&RDVWDO%DQNV OLQHDUIHHW J5RFN\,QWHUWLGDO 6KRUHV VTXDUHIHHW K6DOW0DUVKHV VTXDUHIHHW  VTIWUHVWRUDWLRQUHKDEFUHDWLRQ L/DQG8QGHU6DOW 3RQGV VTXDUHIHHW M/DQG&RQWDLQLQJ 6KHOOILVK N)LVK5XQV O/DQG6XEMHFWWR  &RDVWDO6WRUP)ORZDJH VTXDUHIHHW  5HVWRUDWLRQ(QKDQFHPHQW ,IWKHSURMHFWLVIRUWKHSXUSRVHRIUHVWRULQJRUHQKDQFLQJDZHWODQGUHVRXUFHDUHDLQDGGLWLRQWRWKH VTXDUHIRRWDJHWKDWKDVEHHQHQWHUHGLQ6HFWLRQ%ERU%KDERYHSOHDVHHQWHUWKHDGGLWLRQDO DPRXQWKHUH D VTXDUHIHHWRI%9:E VTXDUHIHHWRI6DOW0DUVK 3URMHFW,QYROYHV6WUHDP&URVVLQJV D QXPEHURIQHZVWUHDPFURVVLQJV E QXPEHURIUHSODFHPHQWVWUHDPFURVVLQJV  FLFXEFXELF\\VGDUDUGVGUGGUHGJHHGJHG aVI DFUHV GLUHFWWUHQFKLQJLPSDFW VVUTXDTXDUHHIIWHHHHW ,L,QGQGLFFDDWWHHVVLL]]HHGXQXQGHUHU&&RRDVDVWWDODO%%NQDDQNVVLLQOQODQDQGG%%NDQDQN/DQG/DQG88UQGHQGHUWWKHKH 22FFHDQHDQDDQGQGRURULLQQOODQDQGG//DQGDQG88UQGHQGHU::DWDWHUHULERGERGLHVHVDDQGQG::DWDWHUHUZZDD\\VV REDDERYYHH  FXELF\DUGVGUHGJHG VI ; ; ;  VI ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ C. Other Applicable Standards and Requirements 7KLVLVDSURSRVDOIRUDQ(FRORJLFDO5HVWRUDWLRQ/LPLWHG3URMHFW6NLS6HFWLRQ&DQG FRPSOHWH$SSHQGL[$(FRORJLFDO5HVWRUDWLRQ/LPLWHG3URMHFW&KHFNOLVWV±5HTXLUHG$FWLRQV &05  Streamlined Massachusetts Endangered Species Act/Wetlands Protection Act Review ,VDQ\SRUWLRQRIWKHSURSRVHGSURMHFWORFDWHGLQEstimated Habitat of Rare WildlifeDVLQGLFDWHGRQ WKHPRVWUHFHQW(VWLPDWHG+DELWDW0DSRI6WDWH/LVWHG5DUH:HWODQG:LOGOLIHSXEOLVKHGE\WKH 1DWXUDO+HULWDJHDQG(QGDQJHUHG6SHFLHV3URJUDP 1+(63 "7RYLHZKDELWDWPDSVVHHWKH Massachusetts Natural Heritage AtlasRUJRWR KWWSPDSVPDVVJLVVWDWHPDXV35,B(67B+$%YLHZHUKWP D<HV 1RIf yes, include proof of mailing or hand delivery of NOI to: Natural Heritage and Endangered Species Program Division of Fisheries and Wildlife 1 Rabbit Hill Road Westborough, MA 01581 E 'DWHRIPDS ,IyesWKHSURMHFWLVDOVRVXEMHFWWR0DVVDFKXVHWWV(QGDQJHUHG6SHFLHV$FW 0(6$ UHYLHZ  &05 7RTXDOLI\IRUDVWUHDPOLQHGGD\0(6$:HWODQGV3URWHFWLRQ$FWUHYLHZSOHDVH FRPSOHWH6HFWLRQ&FDQGLQFOXGHUHTXHVWHGPDWHULDOVZLWKWKLV1RWLFHRI,QWHQW 12, OR FRPSOHWH6HFWLRQ&ILIDSSOLFDEOHIf MESA supplemental information is not included with the NOI, by completing Section 1 of this form, the NHESP will require a separate MESA filing which may take up to 90 days to review (unless noted exceptions in Section 2 apply, see below). F6XEPLW6XSSOHPHQWDO,QIRUPDWLRQIRU(QGDQJHUHG6SHFLHV5HYLHZ 3HUFHQWDJHDFUHDJHRISURSHUW\WREHDOWHUHG D ZLWKLQZHWODQG5HVRXUFH$UHD E RXWVLGH5HVRXUFH$UHD SHUFHQWDJHDFUHDJH  SHUFHQWDJHDFUHDJH $VVHVVRU¶V0DSRUULJKWRIZD\SODQRIVLWH  3URMHFWSODQVIRUHQWLUHSURMHFWVLWHLQFOXGLQJZHWODQGUHVRXUFHDUHDVDQGDUHDVRXWVLGHRI ZHWODQGVMXULVGLFWLRQVKRZLQJH[LVWLQJDQGSURSRVHGFRQGLWLRQVH[LVWLQJDQGSURSRVHG WUHHYHJHWDWLRQFOHDULQJOLQHDQGFOHDUO\GHPDUFDWHGOLPLWVRIZRUN  D 3URMHFWGHVFULSWLRQ LQFOXGLQJGHVFULSWLRQRILPSDFWVRXWVLGHRIZHWODQGUHVRXUFHDUHD  EXIIHU]RQH  E 3KRWRJUDSKVUHSUHVHQWDWLYHRIWKHVLWH 6RPHSURMHFWVnotLQ(VWLPDWHG+DELWDWPD\EHORFDWHGLQ3ULRULW\+DELWDWDQGUHTXLUH1+(63UHYLHZ VHH KWWSZZZPDVVJRYHHDDJHQFLHVGIJGIZQDWXUDOKHULWDJHUHJXODWRU\UHYLHZ 3ULRULW\+DELWDWLQFOXGHVKDELWDWIRUVWDWHOLVWHGSODQWV DQGVWULFWO\XSODQGVSHFLHVQRWSURWHFWHGE\WKH:HWODQGV3URWHFWLRQ$FW 0(6$SURMHFWVPD\QRWEHVHJPHQWHG &05 7KHDSSOLFDQWPXVWGLVFORVHIXOOGHYHORSPHQWSODQVHYHQLIVXFKSODQVDUH QRWUHTXLUHGDVSDUWRIWKH1RWLFHRI,QWHQWSURFHVV ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ C. Other Applicable Standards and Requirements (cont’d) F 0(6$ILOLQJIHH IHHLQIRUPDWLRQDYDLODEOHDW KWWSZZZPDVVJRYGIZHOHGIZQKHVSUHJXODWRU\BUHYLHZPHVDPHVDBIHHBVFKHGXOHKWP  0DNHFKHFNSD\DEOHWR³&RPPRQZHDOWKRI0DVVDFKXVHWWV1+(63´DQGmail to NHESPDW DERYHDGGUHVV Projects altering 10 or more acres of land, also submit: G 9HJHWDWLRQFRYHUW\SHPDSRIVLWH H 3URMHFWSODQVVKRZLQJ3ULRULW\ (VWLPDWHG+DELWDWERXQGDULHV I 25&KHFN2QHRIWKH)ROORZLQJ 3URMHFWLVH[HPSWIURP0(6$UHYLHZ $WWDFKDSSOLFDQWOHWWHULQGLFDWLQJZKLFK0(6$H[HPSWLRQDSSOLHV 6HH&05 KWWSZZZPDVVJRYGIZHOHGIZQKHVSUHJXODWRU\BUHYLHZPHVDPHVDBH[HPSWLRQVKWP WKH12,PXVWVWLOOEHVHQWWR1+(63LIWKHSURMHFWLVZLWKLQHVWLPDWHGKDELWDWSXUVXDQWWR &05DQG  6HSDUDWH0(6$UHYLHZRQJRLQJ D 1+(637UDFNLQJ 0DUFK E 'DWHVXEPLWWHGWR1+(63 6HSDUDWH0(6$UHYLHZFRPSOHWHG ,QFOXGHFRS\RI1+(63³QR7DNH´GHWHUPLQDWLRQRUYDOLG&RQVHUYDWLRQ 0DQDJHPHQW 3HUPLWZLWKDSSURYHGSODQ  )RUFRDVWDOSURMHFWVRQO\LVDQ\SRUWLRQRIWKHSURSRVHGSURMHFWORFDWHGEHORZWKHPHDQKLJKZDWHU OLQHRULQDILVKUXQ" D1RWDSSOLFDEOH±SURMHFWLVLQLQODQGUHVRXUFHDUHDRQO\ E<HV 1R ,I\HVLQFOXGHSURRIRIPDLOLQJKDQGGHOLYHU\RUHOHFWURQLFGHOLYHU\RI12,WRHLWKHU 6RXWK6KRUH&RKDVVHWWR5KRGH,VODQGERUGHUDQG WKH&DSH ,VODQGV 'LYLVLRQRI0DULQH)LVKHULHV 6RXWKHDVW0DULQH)LVKHULHV6WDWLRQ $WWQ(QYLURQPHQWDO5HYLHZHU 6RXWK5RGQH\)UHQFK%OYG 1HZ%HGIRUG0$ (PDLO'0)(QY5HYLHZ6RXWK#VWDWHPDXV 1RUWK6KRUH+XOOWR1HZ+DPSVKLUHERUGHU 'LYLVLRQRI0DULQH)LVKHULHV 1RUWK6KRUH2IILFH $WWQ(QYLURQPHQWDO5HYLHZHU (PHUVRQ$YHQXH *ORXFHVWHU0$ (PDLO'0)(QY5HYLHZ1RUWK#VWDWHPDXV $OVRLI\HVWKHSURMHFWPD\UHTXLUHD&KDSWHUOLFHQVH)RUFRDVWDOWRZQVLQWKH1RUWKHDVW5HJLRQ SOHDVHFRQWDFW0DVV'(3¶V%RVWRQ2IILFH)RUFRDVWDOWRZQVLQWKH6RXWKHDVW5HJLRQSOHDVHFRQWDFW 0DVV'(3¶V6RXWKHDVW5HJLRQDO2IILFH ; ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ C. Other Applicable Standards and Requirements FRQW¶G Online Users: ,QFOXGH\RXU GRFXPHQW WUDQVDFWLRQ QXPEHU SURYLGHGRQ\RXU UHFHLSWSDJH  ZLWKDOO VXSSOHPHQWDU\ LQIRUPDWLRQ\RX VXEPLWWRWKH 'HSDUWPHQW  ,VDQ\SRUWLRQRIWKHSURSRVHGSURMHFWZLWKLQDQ$UHDRI&ULWLFDO(QYLURQPHQWDO&RQFHUQ $&(& " D<HV 1R ,I\HVSURYLGHQDPHRI$&(& VHHLQVWUXFWLRQVWR:3$)RUPRU0DVV'(3 :HEVLWHIRU$&(&ORFDWLRQV Note:HOHFWURQLFILOHUVFOLFNRQ:HEVLWH E $&(&  ,VDQ\SRUWLRQRIWKHSURSRVHGSURMHFWZLWKLQDQDUHDGHVLJQDWHGDVDQ2XWVWDQGLQJ5HVRXUFH:DWHU 25: DVGHVLJQDWHGLQWKH0DVVDFKXVHWWV6XUIDFH:DWHU4XDOLW\6WDQGDUGV&05" D<HV 1R  ,VDQ\SRUWLRQRIWKHVLWHVXEMHFWWRD:HWODQGV5HVWULFWLRQ2UGHUXQGHUWKH,QODQG:HWODQGV 5HVWULFWLRQ$FW 0*/F†$ RUWKH&RDVWDO:HWODQGV5HVWULFWLRQ$FW 0*/F†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dditional Information 7KLVLVDSURSRVDOIRUDQ(FRORJLFDO5HVWRUDWLRQ/LPLWHG3URMHFW6NLS6HFWLRQ'DQGFRPSOHWH $SSHQGL[$(FRORJLFDO5HVWRUDWLRQ1RWLFHRI,QWHQW±0LQLPXP5HTXLUHG'RFXPHQWV &05   $SSOLFDQWVPXVWLQFOXGHWKHIROORZLQJZLWKWKLV1RWLFHRI,QWHQW 12, 6HHLQVWUXFWLRQVIRUGHWDLOV Online Users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‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ D. Additional Information FRQW¶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ees )HH([HPSW1RILOLQJIHHVKDOOEHDVVHVVHGIRUSURMHFWVRIDQ\FLW\WRZQFRXQW\RUGLVWULFW RIWKH&RPPRQZHDOWKIHGHUDOO\UHFRJQL]HG,QGLDQWULEHKRXVLQJDXWKRULW\PXQLFLSDOKRXVLQJ DXWKRULW\RUWKH0DVVDFKXVHWWV%D\7UDQVSRUWDWLRQ$XWKRULW\ $SSOLFDQWVPXVWVXEPLWWKHIROORZLQJLQIRUPDWLRQ LQDGGLWLRQWRSDJHVDQGRIWKH12,:HWODQG )HH7UDQVPLWWDO)RUP WRFRQILUPIHHSD\PHQW $SULO  &KHFNGDWH0XQLFLSDO&KHFN1XPEHU   6WDWH&KHFN1XPEHU $SULO  &KHFNGDWH (SVLORQ$VVRFLDWHV,QF  3D\RUQDPHRQFKHFN)LUVW1DPH  3D\RUQDPHRQFKHFN/DVW1DPH ZSDIRUPGRF‡UHY3DJHRI  Massachusetts Department of Environmental Protection %XUHDXRI5HVRXUFH3URWHFWLRQ:HWODQGV WPA Form 3 – Notice of Intent 0DVVDFKXVHWWV:HWODQGV3URWHFWLRQ$FW0*/F† 3URYLGHGE\0DVV'(3 0DVV'(3)LOH1XPEHU 'RFXPHQW7UDQVDFWLRQ1XPEHU %DUQVWDEOH &LW\7RZQ F. Signatures and Submittal Requirements ,KHUHE\FHUWLI\XQGHUWKHSHQDOWLHVRISHUMXU\WKDWWKHIRUHJRLQJ1RWLFHRI,QWHQWDQGDFFRPSDQ\LQJ SODQVGRFXPHQWVDQGVXSSRUWLQJGDWDDUHWUXHDQGFRPSOHWHWRWKHEHVWRIP\NQRZOHGJH,XQGHUVWDQG WKDWWKH&RQVHUYDWLRQ&RPPLVVLRQZLOOSODFHQRWLILFDWLRQRIWKLV1RWLFHLQDORFDOQHZVSDSHUDWWKH H[SHQVHRIWKHDSSOLFDQWLQDFFRUGDQFHZLWKWKHZHWODQGVUHJXODWLRQV&05  D  ,IXUWKHUFHUWLI\XQGHUSHQDOWLHVRISHUMXU\WKDWDOODEXWWHUVZHUHQRWLILHGRIWKLVDSSOLFDWLRQSXUVXDQWWR WKHUHTXLUHPHQWVRI0*/F†1RWLFHPXVWEHPDGHE\&HUWLILFDWHRI0DLOLQJRULQZULWLQJE\ KDQGGHOLYHU\RUFHUWLILHGPDLO UHWXUQUHFHLSWUHTXHVWHG WRDOODEXWWHUVZLWKLQIHHWRIWKHSURSHUW\OLQH RIWKHSURMHFWORFDWLRQ  6LJQDWXUHRI$SSOLFDQW  'DWH  6LJQDWXUHRI3URSHUW\2ZQHU LIGLIIHUHQW  'DWH  6LJQDWXUHRI5HSUHVHQWDWLYH LIDQ\  'DWH For Conservation Commission: 7ZRFRSLHVRIWKHFRPSOHWHG1RWLFHRI,QWHQW )RUP LQFOXGLQJVXSSRUWLQJSODQVDQGGRFXPHQWV WZRFRSLHVRIWKH12,:HWODQG)HH7UDQVPLWWDO)RUPDQGWKHFLW\WRZQIHHSD\PHQWWRWKH &RQVHUYDWLRQ&RPPLVVLRQE\FHUWLILHGPDLORUKDQGGHOLYHU\ For MassDEP: 2QHFRS\RIWKHFRPSOHWHG1RWLFHRI,QWHQW )RUP LQFOXGLQJVXSSRUWLQJSODQVDQGGRFXPHQWVRQH FRS\RIWKH12,:HWODQG)HH7UDQVPLWWDO)RUPDQGDcopyRIWKHVWDWHIHHSD\PHQWWRWKH 0DVV'(35HJLRQDO2IILFH VHH,QVWUXFWLRQV E\FHUWLILHGPDLORUKDQGGHOLYHU\ Other: ,IWKHDSSOLFDQWKDVFKHFNHGWKH³\HV´ER[LQDQ\SDUWRI6HFWLRQ&,WHPDERYHUHIHUWRWKDW VHFWLRQDQGWKH,QVWUXFWLRQVIRUDGGLWLRQDOVXEPLWWDOUHTXLUHPHQWV 7KHRULJLQDODQGFRSLHVPXVWEHVHQWVLPXOWDQHRXVO\)DLOXUHE\WKHDSSOLFDQWWRVHQGFRSLHVLQD WLPHO\PDQQHUPD\UHVXOWLQGLVPLVVDORIWKH1RWLFHRI,QWHQW DocuSign Envelope ID: 77D9469A-89E9-4CF7-8616-4333D4761622   Town of Barnstable NOI Submission Checklist – Chapter 707 !! !" #$"%" &""&" " ’()&*+&+, "- . &$& /*+#/ , 0 .(.&123 ’(), #*+#!(&4 5555556 6( 7 4 . #’(),/-8+ *+#/ , 0 .(.&123 ’ /-8+*+9 (.3/9.3 33 ( )3249,#.336 : 2 )3(4+-"+ ; #(.3/9.3 33 ’() , 8 ’() ! < 5 +"4 # # ’ <#9&)3= "# 4;3>6>=’623?( 864@ !#A4;3>6))>6’2.’ y y y y y Eͬ y y y y -;3>>=’62 3?(" &B 4 55 +.33 7 +#$/7 .337 + C # 9)3=&- && && D &- 7 #&’(), .337 EEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEE <#9 - ( $%&’ &@>4(3 &"& 7" F"G B .33" /" +7"& 2 (%$’ 5&"& 6 ; )!!!’ +6 &/-8+H *!-! #$7&& &B&&& +’7&" + /&&& &.IJ’3K !6&&& y y y y y ^ĞĞŶŽƚĞďĞůŽǁ y y y y y y EKd͗ďƵƚƚĞƌŶŽƚŝĨŝĐĂƚŝŽŶƐǁŝůůďĞĨŽƌǁĂƌĚĞĚƚŽĂůůƉƌŽũĞĐƚĂďƵƚƚĞƌƐŽŶĐĞƉƵďůŝĐŚĞĂƌŝŶŐĚĂƚĞŝƐĞƐƚĂďůŝƐŚĞĚ͘ ;,ĞĂƌŝŶŐĚĂƚĞǁŝůůďĞĚĞƚĞƌŵŝŶĞĚƉĞŶĚŝŶŐĂƉƉƌŽǀĂůŽĨĂƉĞŽĚŽŵŵŝƐƐŝŽŶͿ ^ĞĞŶŽƚĞďĞůŽǁ EKd͗hŶƐƚĂŵƉĞĚƉůĂŶƐĂƌĞĨŽƌƉĞƌŵŝƚƚŝŶŐƉƵƌƉŽƐĞƐŽŶůLJ͘ ++#+&!+# &" !+# 55 - - !7 )326(&)3262&)326;& &L&5 3;3;3.33 & +& +C < , < 7 +" &** +&& = +!++"’ #%’6 .6 % % + && &&&& 7 &% 0 # .33 " % <& ) ,# --$-()( -. (’ ++#+&!+# &" !+# 55 - - 8+-! M @ #-- M@ )%!+&* #&/!&& +’"5 -N EKd͗WĞƌŵŝƐƐŝŽŶƚŽĂĐĐĞƐƐŝƐŶŽƚƌĞƋƵŝƌĞĚĂƐƚŚĞƉƌŽũĞĐƚŝƐůŽĐĂƚĞĚŽŶƚŽǁŶƉĂƌĐĞůĂŶĚƉƵďůŝĐǁĂLJƐ͘y y y y y y y y y Eͬ Eͬ y y Eͬ;ƐĞĞŶŽƚĞďĞůŽǁͿ +) -&& # O /./- 8+/-8+<9&’39- &0"&/# 3’(2= </-8+4/#-8+&% 23=’&&/#3’’.. !7& <+7/<+7&5 -+ *"&(>’!9&B&/#3’=3. !&& 7&<&5 9&..>?+$0 &&/#3’=(’ &+-!4 .@ 8 -N ’7@ #&&&& B&5 /8 #/8#&..>?+$0 &&/#3’=(’ &+-! 4 .@ 8 -N ’7@ ’+74 <& 0& /5& &012345+5416* 7’ %!%%!+8!"**9%+ /!!:*/%%%%+&*9+%%"+ !%+!!%+%!:* < F9,/<9 #G4 + 5# < $#L# < #4/’>&??) 94/.’&’3.; 94#’(& < =&’3.= 9/.;&’3’’ y y Eͬ y y ϮϵƚŚ Ɖƌŝů ϮϬϮϮ ,ŽůůLJĂƌůƐŽŶ:ŽŚŶƐƚŽŶ ,ĂŶƐsĂŶ>ŝŶŐĞŶ͕WĂƌŬŝƚLJtŝŶĚ ,ŽůůLJĂƌůƐŽŶ:ŽŚŶƐƚŽŶ  Attachment A Project Narrative 5526.10/New England Wind 1 Connector 1 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. ATTACHMENT A PROJECT NARRATIVE 1.0 Introduction and Project Overview Park City Wind LLC (the Proponent) is in the process of developing and permitting an offshore wind project with a nameplate generating capacity of approximately 800 megawatts (MW). The offshore wind farm will be located in federal waters, specifically in the northern portion of Bureau of Ocean Energy Management (BOEM) Lease Area OCS-A 0534 which, at its closest point, is approximately 41 miles (66 km) south of the Cape Cod mainland. The New England Wind 1 Connector (NE Wind 1 Connector, the “Project”) is comprised of the Massachusetts-jurisdictional elements of the broader Park City Wind project (i.e., portions of the offshore transmission that are in Massachusetts waters, as well as the onshore transmission, the onshore substation, and the grid interconnection in the town of Barnstable). Figure 1 in Attachment B provides an overview of the NE Wind 1 Connector. This Notice of Intent (NOI) addresses those aspects of the Project that are located within the Town of Barnstable and subject to regulations established under the Massachusetts Wetlands Protection Act (WPA) and Barnstable Wetlands Protection Ordinance. This includes approximately 6.8 miles of Offshore Export Cable Corridor (OECC) within Barnstable’s offshore waters, the landfall site at a town-owned parking lot at Craigville Public Beach, the trenchless crossing of the Centerville River, and those portions of the onshore transmission system that are located within the jurisdiction of the Barnstable Conservation Commission. Specifically, the Proponent seeks an Order of Conditions from the Barnstable Conservation Commission for work in and within 100 feet of Land Under the Ocean, Coastal Dune, Barrier Beach, Riverfront Area (RFA), and Land Subject to Coastal Storm Flowage (LSCSF). The Proponent is seeking approval under the Massachusetts WPA Regulations and the Barnstable Wetlands Ordinance as a Limited Project for alteration of Land Under the Ocean within Barnstable’s offshore waters, and for temporary alterations to Coastal Dune, Barrier Beach, RFA, and LSCSF associated with onshore construction activities (see Section 5.2); this is despite the fact that the Proponent believes the Project does meet the wetland performance standards. All Project- related construction activities and their associated impacts to wetland resource areas in Barnstable are described in this NOI. The majority of the onshore export cable route, including the site of the proposed substation, is located outside of wetland resource areas. 1.1 Current Permitting Status The Park City Wind project and NE Wind 1 Connector are currently under extensive review by a range of federal, state, and regional agencies to ensure that impacts to the marine environment are avoided and minimized. 5526.10/New England Wind 1 Connector 2 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. All proposed elements of the larger Park City Wind project are being reviewed by BOEM and other participating federal and state regulatory agencies under the National Environmental Policy Act (NEPA). This review will include preparation of Draft and Final Environmental Impact Statements developed by an independent third party in consultation with review agencies and stakeholders (the Draft Environmental Impact Statement [DEIS] and Final Environmental Impact Statement [FEIS] will be publicly available documents as part of the federal review). While the federal review processes are underway, state-level environmental review for the NE Wind 1 Connector is being led by the Executive Office of Energy and Environmental Affairs (EEA), Massachusetts Environmental Policy Act (MEPA) Office (which completed its review on January 28, 2022), and the Energy Facilities Siting Board (EFSB). Rigorous environmental reviews will be highly scrutinized by a host of other state and federal permitting and review agencies including the U.S. Army Corps of Engineers (USACE), U.S. Environmental Protection Agency (EPA), Massachusetts Department of Environmental Protection (MassDEP), Massachusetts Division of Marine Fisheries (DMF), and Natural Heritage and Endangered Species Program (NHESP). In addition, portions of the NE Wind 1 Connector will be reviewed by the Cape Cod Commission and Martha’s Vineyard Commission. The principal environmental permits, reviews, and approvals required for the Park City Wind project and NE Wind 1 Connector (as well as their approval status as of this submission) are listed in Table 1-1. By meeting the requirements for each of these review programs, permits, and approvals, the Project will demonstrate compliance with applicable state and local environmental policies. 5526.10/New England Wind 1 Connector 3 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Table 1-1 Environmental Permits, Reviews, and Approvals for the New England Wind 1 Connector and Park City Wind Agency/Regulatory Authority Permit/Approval Status Federal (for Park City Wind) Bureau of Ocean Energy Management (BOEM)1 Construction and Operations Plan (COP) approval/Record of Decision (ROD) COP filed July 2020 National Environmental Policy Act (NEPA) Environmental Review Initiated by BOEM June 30, 2021 Consultation under Section 7 of the Endangered Species Act (ESA) with National Marine Fisheries Service (NMFS) and U.S. Fish and Wildlife Service (USFWS), coordination with states under the Coastal Zone Management Act (CZMA), government-to- government tribal consultations, consultation under Section 106 of the National Historic Preservation Act (NHPA), and consultation with NMFS for Essential Fish Habitat To be initiated by BOEM Facilities Design Report and Fabrication & Installation Report To be filed (TBF) U.S. Environmental Protection Agency (EPA) EPA Permits under Section 316(b) of the Clean Water Act (CWA), including National Pollutant Discharge Elimination System (NPDES) Permit(s) TBF Outer Continental Shelf (OCS) Air Permit TBF U.S. Army Corps of Engineers (USACE) Clean Water Act (CWA) Section 404 Permit Rivers and Harbors Act of 1899 Section 10 Individual Permit Joint application TBF U.S. National Marine Fisheries Service (NMFS) Letter of Authorization (LOA) or Incidental Harassment Authorization TBF U.S. Coast Guard (USCG) Private Aid to Navigation (PATON) authorization TBF Federal Aviation Administration No Hazard Determination (for activities at construction staging areas and vessel transits, if required) TBF 1 In its review of the COP, BOEM must comply with its obligations under the National Environmental Policy Act (NEPA), the National Historic Preservation Act (NHPA), the Magnuson-Stevens Fishery Conservation and Management Act, the Migratory Bird Treaty Act, the Clean Air Act, and the Endangered Species Act (ESA). Thus, BOEM coordinates and consults with numerous other federal agencies including the National Marine Fisheries Service (NMFS), United States Fish and Wildlife Service (USFWS), the Environmental Protection Agency (EPA), and the United States Coast Guard (USGC) during the review process. BOEM also coordinates with the state under the Coastal Zone Management Act (CZMA) to ensure that the project is consistent with the state’s coastal zone management program. 5526.10/New England Wind 1 Connector 4 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Table 1-1 Environmental Permits, Reviews, and Approvals for the New England Wind 1 Connector and Park City Wind (Continued) Agency/Regulatory Authority Permit/Approval Status State/Massachusetts (for the NE Wind 1 Connector) Massachusetts Environmental Policy Act Office (MEPA) Certificate of Secretary of Energy and Environmental Affairs (EEA) on Final Environmental Impact Report Environmental Notification Form filed June 11, 2020, Draft Environmental Impact Report (DEIR) filed March 19, 2021 (Certificate received June 25, 2021), Final Environmental Impact Report (FEIR) filed December 15, 2021 (Certificate received January 28, 2022). Energy Facilities Siting Board (EFSB) G.L. c. 164, § 69 Approval Filed May 28, 2020 Massachusetts Department of Public Utilities (DPU) G.L. c. 164, § 72, Approval to Construct G.L. c. 40A, § 3 Zoning Exemption Filed May 28, 2020 Massachusetts Department of Environmental Protection (MassDEP) Chapter 91 Waterways License and Dredge Permit Water Quality Certification (Section 401 of the CWA) Joint Application TBF Massachusetts Department of Transportation (MassDOT) Highway Access Permits (Barnstable) TBF Massachusetts Board of Underwater Archaeological Resources (MBUAR) Special Use Permit 17-003 (issued to archaeologist, not Park City Wind LLC) Permit renewal approved February 26, 2021 Natural Heritage and Endangered Species Program (NHESP) Conservation and Management Permit (if needed) TBF (if needed) MESA Determination issued April 1, 2022 with conditions so the Project will not result in a Take of state-listed species. Massachusetts Historical Commission (MHC) State Archaeologist Permit #4006 (950 C.M.R. § 70.00) (issued to archaeologist, not Park City Wind LLC) Permit #4006 for Reconnaissance Survey received May 12, 2020. Permit #4006 amended and extended March 2, 2021 (survey complete). 5526.10/New England Wind 1 Connector 5 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Table 1-1 Environmental Permits, Reviews, and Approvals for the New England Wind 1 Connector and Park City Wind (Continued) Agency/Regulatory Authority Permit/Approval Status State/Massachusetts (for the NE Wind 1 Connector) Massachusetts Division of Marine Fisheries (DMF) Letter of Authorization and/or Scientific Permit (for surveys and pre-lay grapnel run) TBF Massachusetts Office of Coastal Zone Management (CZM) / Rhode Island Coastal Resources Management Council (CRMC) Federal Consistency Determination (15 CFR 930.57) Filed with COP as Appendix III-S Regional (for portions of the NE Wind 1 Connector within regional jurisdiction) Cape Cod Commission (CCC) Development of Regional Impact (DRI) Review (Barnstable County) TBF Martha’s Vineyard Commission (MVC) DRI Review (Dukes County) TBF Local (for portions of the NE Wind 1 Connector within local jurisdiction) Barnstable Conservation Commission Order of Conditions (Massachusetts Wetlands Protection Act and, as applicable, municipal wetland non zoning bylaws) This application. Barnstable DPW and/or Town Council Street Opening Permits/Grants of Location TBF Barnstable Planning/Zoning Zoning approvals (if necessary) TBF Edgartown Conservation Commission Order of Conditions (Massachusetts Wetlands Protection Act [WPA] and, as applicable, municipal wetlands non zoning bylaws) for OECC within Edgartown waters Filed March 23, 2022 Nantucket Conservation Commission Order of Conditions (Massachusetts WPA and, as applicable, municipal wetland non zoning bylaws) for OECC within Nantucket waters Filed March 7, 2022 2.0 Project Purpose and Public Benefits The purpose of the Project is to deliver approximately 800 MW of clean, renewable wind energy to the New England electrical grid. By doing so, the Project will serve the public interest by increasing the reliability and diversity of the regional energy supply. The NE Wind 1 Connector and Park City Wind are expected to create a range of environmental and economic benefits for southeastern Massachusetts, the Commonwealth as a whole, and the entire New England region. These benefits will extend across the design, environmental review, and permitting phase, the procurement, fabrication, and construction/commissioning phase, the multi-decade operating phase, as well as the future decommissioning effort. Project benefits are expected to include: i Clean renewable energy at large scale and a high-capacity factor: The location of the associated WTGs well offshore in a favorable wind regime, coupled with the efficiency of the WTGs, will enable the Project to deliver substantial quantities of power on a reliable basis, including during times of peak grid demand. WTGs for Park City Wind will be among 5526.10/New England Wind 1 Connector 6 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. the most efficient models currently available for offshore use. It is expected that the WTGs will be capable of operating with an annual capacity factor of approximately 50%. Based on EPA data 2 and assuming a Project generating capacity of approximately 800 MW, WTGs of this efficiency and capability will reduce ISO-NE CO2e emissions by approximately 1.59 million tpy. This is the equivalent of removing approximately 310,000 automobiles from the road. In addition, nitrogen oxide (NOx) emissions across the New England grid are expected to be reduced by approximately 850 tpy with sulfur dioxide (SO2) emissions being reduced by approximately 450 tpy. i Reducing winter energy price spikes: The Project adds high and stable winter capacity factor offshore wind generation to the region, increasing resources available to meet electric demand needs with offshore wind-generated energy, freeing up natural gas resources to be used for necessary home heating demands. The Project will therefore be unaffected by the risk of potential fossil fuel constraints and will help alleviate price volatility. The Project could reduce the need to run the gas- and oil-burning Canal Units 1 and 2 on Cape Cod, especially during winter peak events when winds are high and conditions ideal for wind energy generation. i Improving the reliability of the electric grid in Southeastern Massachusetts: The Project will connect to the bulk power system on Cape Cod, and thus will increase the supply of power to Barnstable County and other parts of southeastern Massachusetts, an area which has experienced significant recent (and planned) generation unit retirements. Because of its interconnection location and generation type, adding an additional approximately 800 MW of offshore wind generation to the current power generation portfolio will provide fuel diversification and enhance the overall reliability of power generation and transmission in the region and in particular the southeast Massachusetts area, which has seen, and will continue to see, substantial changes in generation capacity. This will mitigate future costs for ensuring reliable service for Massachusetts customers. i Additional economic benefits for the region: Project construction will generate substantial economic benefits, including opportunities for regional maritime industries (tug charters, other vessel charters, dockage, fueling, inspection/repairs, provisioning). i New employment opportunities: The Proponent is committed to spurring and facilitating the creation, development, growth, and sustainability of a long-term offshore wind industry in New England, including a robust local supply chain, a well-trained local workforce throughout development, construction, and operations activities, local port facilities capable of fabrication and construction of key project components, and 2 Based on avoided emission rates from EPA’s Emissions & Generation Resource Integrated Database eGRID2018(v2) released March 2020. 5526.10/New England Wind 1 Connector 7 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. advanced manufacturing capabilities, all of which will cement New England as a leader in offshore wind. The Proponent estimates the Project will generate over 4,700 direct full- time equivalent (FTE) job years and 2,100 indirect FTE job years over its lifetime, primarily in Connecticut and Massachusetts. i Support for Massachusetts policies: The Project is entirely consistent with the Commonwealth’s Global Warming Solutions Act (GWSA) goals because supplying emissions-free energy to the New England electric grid will displace fossil fuel sources, including in Massachusetts, which would otherwise operate to supply that power. The Proponent is currently in late-stage discussions with the Town of Barnstable for an Host Community Agreement (HCA) for the Project and expects the HCA for the Project will contain very similar or identical economic terms as those in the 2018 HCA for Vineyard Wind Connector. On October 21, 2021, the Barnstable Town Council authorized the Town Manager to finalize and execute the HCA with the Proponent. Assuming the relevant terms are identical, the Project’s HCA would guarantee that, in addition to property tax assessments, the Project would pay a total Host Community Payment of $16 million, plus an additional $60,000 (adjusted upward annually by 2.5%) for each year the Project is in operation beyond 25 years. In addition to HCA payments and property tax payments to Barnstable for the Project, additional revenues are also anticipated for the Commonwealth and municipalities in the form of higher tax payments resulting from Project activities and employment (including personal income taxes, sales taxes, corporate and payroll taxes, and real and personal property taxes) in every Project phase. A more extensive discussion of Project benefits was provided in Section 1.7 of the FEIR. The FEIR can be found at https://www.parkcitywind.com/permitting. 3.0 Existing Conditions within the Town of Barnstable 3.1 Offshore Export Cable Corridor (OECC) Offshore Project components within Barnstable waters are limited to installation of two offshore export cables along an approximately 6.6-mile (10.6-km) stretch of the OECC as well as the approximately 0.2-mile (0.3-km) offshore-to-onshore transition via horizontal directional drilling (HDD) at the landfall site. The OECC was thoroughly evaluated and approved for the Vineyard Wind Connector, and it remains largely the same for the NE Wind 1 Connector. One difference is the OECC has been widened by approximately 985 feet (300 m) to the west, bringing its typical width to approximately 3,800 feet (1,150 m). Since the two cables from the Vineyard Wind Connector will already be installed within the previously identified OECC, this widening will provide greater flexibility throughout the route design process as part of ongoing efforts to avoid and minimize impacts to sensitive habitats. The areas of widening were surveyed in 2020. The NE Wind 1 Connector includes two offshore export cables, both of which will be located within the OECC. In addition, the Proponent has performed a comprehensive assessment of the geophysical and geotechnical conditions along the route, including the presence of seabed features and considerations such as sand waves, magnetic anomalies, coarse deposits, rocks or 5526.10/New England Wind 1 Connector 8 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. boulders, water depths, and seabed slopes. Within the OECC, the two export cables will be installed with sufficient separation to allow for safe installation and any future repair work, if required. The OECC within Barnstable waters is shown on Figure 2 in Attachment B. Offshore wind projects are unique infrastructure that utilize rapidly changing technologies deployed in a dynamic marine environment. The high-energy marine environment can cause features like shoals to be in a constant state of change, resulting in corresponding water depth changes. Experience in the offshore wind industry in Europe as well as offshore cable installations in the U.S. has demonstrated that use of an installation corridor can provide flexibility in the engineering and installation stages to maximize the likelihood of successful cable burial while also avoiding and minimizing environmental impacts. Geological conditions within the OECC are well understood, and the site geology and conditions are suitable for cable installation. Through the OECC survey work completed as part of Vineyard Wind/Vineyard Wind Connector, supplemented by additional surveys in 2020, a large amount of survey data has been collected and the Proponent has a strong understanding of the OECC in terms of potential environmental impacts and construction feasibility. Prior to 2020 surveys, more than 2,307 nautical miles (4,272 km) of geophysical trackline data, 123 vibracores, 83 cone penetrometer tests, 82 benthic grab samples with still photographs, and 50 underwater video transects had already been gathered in support of OECC characterization. Further data collection was performed for the OECC expansion areas in 2020. Using all these accumulated data, the Proponent has conducted a comprehensive geotechnical evaluation of the shallow subsurface conditions present along the OECC and has determined that cable installation is feasible. While geological conditions vary within the corridor, including limited locations with more challenging conditions for cable installation, conditions are overall within acceptable risk levels. In addition, reconnaissance survey work for Vineyard Wind/Vineyard Wind Connector, which included coverage of the western portion of Muskeget Channel and routes to the east of Horseshoe Shoal in Nantucket Sound, did not identify areas where conditions appeared more favorable for cable installation. To the contrary, such reconnaissance survey work identified features outside the OECC such as shoals, large concentrations of boulders, deep channels, and high currents that would make cable installation and maintenance in an alternate location more challenging. These factors would increase health and safety risk during installation and maintenance, risk of not achieving sufficient burial depths, and risk of cable exposure. The Proponent has also assessed the OECC for installation feasibility, which includes ensuring that water depths are suitable for fully loaded cable installation vessels, slopes are workable for typical cable installation tools, sufficient room is available for anchoring, etc. Based on these detailed geotechnical and installation feasibility analyses, the Proponent has determined that the identified cable corridor is the most suitable for cable installation and the needs of Park City Wind/NE Wind 1 Connector. 5526.10/New England Wind 1 Connector 9 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Results from the marine surveys performed since 2017 have been used to identify the proposed OECC. This selection was addressed in detail in the MEPA environmental review process (Section 2.1.3.1 of the DEIR and Section 2.1.1 of the FEIR), and reflected selection of the shortest offshore route with the fewest environmental impacts while remaining technically suitable for cable installation. The principal technical and environmental considerations and constraints factoring into the geography of the OECC include: 1. Feasibility of cable installation, including required spacing from other cables; 2. Burial risk assessment/work to limit possibilities of cable failure; 3. Avoiding and/or minimizing impacts to special, sensitive, or unique (SSU) areas mapped in the Massachusetts OMP; 4. Avoiding and/or minimizing anchorage areas and areas with mapped shipwrecks and boulders; 5. Environmental and/or permitting constraints and avoidance of impacts; 6. Minimizing cable length to reduce transmission losses and cost; 7. Adequate capacity delivered to the grid connection point; 8. Available landfall locations; 9. Maintaining a water depth of at least 20 feet, and avoiding shoals; 10. The route should not turn more than 30 degrees at a time, with a minimum turn radius of 165 feet (50 m); 11. Avoiding slopes where the seafloor bathymetry changes dramatically; 12. Crossing large seabed slopes and existing offshore cables in a perpendicular, or nearly perpendicular, orientation; and 13. Crossing navigation corridors in a perpendicular orientation. The offshore cable corridor within Barnstable Conservation Commission jurisdiction is shown on Figure 2. The total length of the corridor within Barnstable waters is approximately 6.8 miles (6.6 miles [10.6 km] of cable burial and 0.2 miles [0.3 km] of HDD). The Project will avoid core habitat for whales, and the corridor will avoid most hard/complex bottom habitat mapped in the Massachusetts Ocean Management Plan (OMP) (see below). 5526.10/New England Wind 1 Connector 10 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 3.1.1 Special, Sensitive, and Unique (SSU) Habitats The Massachusetts OMP identifies “special, sensitive, and unique” (SSU) habitats to which impacts should be avoided and minimized, where practicable. For cable projects generally, these SSU areas include hard/complex bottom, eelgrass, and marine mammal habitats such as core habitat for the North Atlantic Right Whale (no such core habitat is mapped within Barnstable waters). Some habitats are known to change and move over time (e.g., complex bottom formed by sand wave fields) while others are prime habitats despite seasonal and long-term changes in organism abundance (e.g., eelgrass). As described above, the OECC will avoid most hard/complex bottom habitat mapped in the OECC (see Figure 3). The Proponent’s marine surveys have been used to refine the OMP mapping of hard bottom and complex bottom based on higher-resolution survey data, with results depicted on Figure 3 as well as the map set provided in Attachment C. Within Barnstable, as shown on Figure 3, the preliminary cable alignments within the OECC predominantly avoid hard bottom, but they are unable to avoid a broad area of complex seafloor/bedforms that covers most of the corridor towards its southern end in Barnstable waters. The discussion below addresses hard bottom and complex bottom as well as eelgrass mapped within the OECC in Barnstable waters based on the Proponent’s marine survey results. 3.1.1.1 Hard/Complex Seafloor This broad characterization of the seafloor was first developed by the Massachusetts Office of Coastal Zone Management (CZM) and is documented in the “Regional Sediment Resource Management Work Group Report – 2014 Massachusetts Ocean Management Plan Update” (CZM, 2014). Defined by CZM in this report, complex seafloor is “a morphologically rugged seafloor characterized by high variability in bathymetric aspect and gradient.” CZM (2014) determined the complex seafloor areas by utilizing a USGS 30-meter by 30-meter low-resolution bathymetry dataset and calculated areas of high rugosity using a Vector Ruggedness Measure (VRM) tool, based on a method developed by Sappington et al. (2007) with a 9x9-cell neighborhood size. The values produced by the VRM analysis range from 0 to 1, with 0 indicating no seabed complexity and 1 indicating complete seabed complexity. The seabed was classified as complex for VRM values greater than 3/8 standard deviation from the mean value of the whole dataset (CZM, 2014). Using the CZM (2014) analysis as a guide, which is consistent with the hard/complex bottom revised for the 2021 OMP, the Proponent performed an analysis of multibeam depth sounding data. A VRM was performed on the 0.5-meter by 0.5-meter high-resolution bathymetry collected along the OECC using a 9-cell search radius. Polygons were then created from the VRM grids by clipping the extents to include only values greater than the mean value plus 3/8 standard 5526.10/New England Wind 1 Connector 11 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. deviation which resulted in a cutoff of 0.0035 and greater to indicate a complex seafloor. Results of the ruggedness analysis on the 2018 dataset show much more detail and complexity due to the data point spacing considered. Smaller, localized features exhibiting high enough slope gradients and sharp bathymetry aspects are in some areas individually mapped. Results indicate increased seafloor ruggedness is associated with the bedform habitat, hard bottom habitat, and biogenic structures/surface organics habitat. An overall boundary for the hard/complex seafloor characterization presented in the OMP is thus the combination of all three of these benthic habitats. For the purposes of the NE Wind 1 Connector, the Proponent has separated areas of bedforms (i.e., complex bottom) from hard bottom, since these benthic environments are distinctly different habitats. 3.1.1.2 Hard Bottom Habitat Hard bottom areas in portions of Nantucket Sound include high concentrations of coarse material (>50 % gravel, cobbles, boulders in a sand matrix) which, even though considered an unconsolidated sediment surface, form a relatively hard substrate to which sessile benthic organisms can attach. Most of these are associated with glacial moraine deposits and consist of rock piles and scattered individual rocks (i.e., boulders) of varying abundance on the seafloor. Some areas are predominantly gravel and cobbles with the sand matrix and a sparse distribution of boulder-sized material. No bedrock outcrops exist within the OECC. As shown on Figure 3 and in the plan set depicting results from the marine surveys within Barnstable waters (see Attachment C), there are some small areas of hard bottom that the preliminary cable alignments avoid. The cable alignments are unable to avoid a broad area of complex seafloor/bedforms that covers most of the corridor towards its southern end in Barnstable waters. However, it is important to note that while some temporary impacts to complex seafloor/bedforms are unavoidable, almost all of the OECC will remain unaffected by the cable installation; rather, two narrow strips of seabed, one for each cable alignment, will be impacted by the cable installation. 3.1.1.3 Complex Bottom As shown on Figure 3 and in Attachment C, within Barnstable waters the OECC almost entirely avoids areas of complex bottom except for an area toward the southern reach of the OECC in Barnstable waters where an area of complex seafloor/bedforms covers most of the corridor width. In this area and elsewhere along the OECC, bedform fields (i.e., ripples, megaripples, and sand waves) of varying sizes are present and are morphologically dynamic. Due to the mobility of the sediments in this habitat, development of infaunal communities is greatly reduced compared to more stable seabed areas. While this equates to a lower productive infaunal benthic regime, the bottom morphology and dynamics of the fields is reportedly attractive to finfish. The areal extent of these bedforms is constantly changing with subtle environmental shifts in water depths, 5526.10/New England Wind 1 Connector 12 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. sediment grain size, and current flow. This is a laterally extensive habitat due to the predominantly sandy seafloor and tidal currents flowing over the bottom and constantly reworking sediment. Some areas of Nantucket Sound have active sand waves that can exceed 12 feet (3.7 m) in height. Marine survey work has enabled the Proponent to assess these areas, which may require some pre-cable-laying dredging to ensure that the necessary burial depth can be achieved and maintained. The stretch of the OECC where sand wave dredging may be needed is largely coincident with areas mapped as complex bottom as shown on Figure 3. It is important to note that dredging, if performed, would not occur along the entire stretch where sand waves may be present; rather, dredging would only be performed to remove the tops of each sand wave to the extent needed at the time of construction to ensure sufficient burial within the stable seabed. Dredging will be performed as close in time to cable installation as possible to avoid mobile sand waves re-covering the dredged area. A number of possible sand wave dredging techniques are under consideration and are described in detail in Section 4.1.2.4. For both offshore export cables combined, the Proponent’s engineers anticipate that the length of dredging in Barnstable waters could be approximately 2.0 miles (3.2 km). It is important to note that since sand waves are mobile features with shifting morphology, this length of dredging is an estimate. 3.1.1.4 Eelgrass Eelgrass (Zostera marina) beds form an important habitat in the coastal environment that provides refuge and sustenance for a large number and variety of species, as well as serving as a critical component of sediment and shoreline stabilization. Preliminary routing for the Project considered data from MassDEP’s Eelgrass Mapping Project as well as the OMP, and the Proponent has performed specific eelgrass surveys within the installation corridor. The 2018 marine survey documented one previously unidentified area of eelgrass within Centerville Harbor, southeast of the Craigville Public Beach Landfall Site. This area was first identified by video survey, in which sparse patches of eelgrass were noted around Spindle Rock. A subsequent diver investigation provided a thorough mapping of the area. This patch of eelgrass is co-located with an area of hard bottom (a rock pile), where patches of eelgrass intertwined with macroalgae inhabit the discontinuous sandy bottom in and around the rock pile. During 2018 surveys, the eelgrass in this area exhibited the bright green coloring common for healthy eelgrass during the growing season. As shown on Figure 3, the HDD trajectory will enable the Project to entirely avoid impacts to this area of eelgrass as well as the co-located hard bottom. As a result, the preliminary cable alignments completely avoid eelgrass along the entire OECC, including in Barnstable waters. 5526.10/New England Wind 1 Connector 13 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 3.1.2 Shellfish Habitat The Division of Marine Fisheries (DMF) has mapped areas throughout the Commonwealth as suitable shellfish habitat for Bay Scallop, Surf Clam, Quahog, Soft Shell Clam and Blue Mussel. These are believed to be suitable for these species of shellfish based on the expertise of DMF and local Shellfish Constables, input from commercial fishermen, and information contained in maps and studies of shellfish in Massachusetts. DMF shellfish suitability areas include sites where shellfish have been observed since the mid-1970s but may not currently support any shellfish, and therefore represent potential habitat areas. As shown on Figure 4, the Project’s OECC and preliminary cable alignments almost entirely avoid shellfish suitability areas in Barnstable waters. The transition from offshore cable burial to the HDD will occur close to the boundary for mapped suitable habitat for Surf Clam (Spisula solidissima) located in the nearshore area of Centerville Harbor. The use of HDD will avoid almost all impacts to the mapped suitable habitat by using HDD to pass beneath most of the nearshore Surf Clam habitat without disturbing the surface of the seafloor. However, it is estimated that typical cable installation would occur through approximately 200 linear feet of that habitat. The actual length could be more or less than 200 linear feet based on the final HDD design. 3.1.3 Rare Species Habitat The Massachusetts Natural Heritage and Endangered Species Program (NHESP) has mapped all state waters within Nantucket Sound and Muskeget Channel as priority habitat of state-listed rare species (Massachusetts Natural Heritage Atlas, 15th Edition, 2021). As a result, the portion of the OECC that passes within Barnstable waters will necessarily cross priority habitat (see Figure 5 in Attachment B). The Proponent is consulting with the NHESP in accordance with the Massachusetts Endangered Species Act (MESA) (321 CMR 10.14) to ensure that impacts to offshore rare species are avoided or minimized to greatest extent practicable. In addition, NHESP has established Priority Habitat along the Centerville Harbor shoreline for Piping Plover that includes the beach and some of the dunes adjacent to the Craigville Public Beach parking lot (see Figure 6 in Attachment B). At this location, the Project will utilize HDD to avoid any disturbance to mapped habitat, and in consultation with NHESP the Proponent has developed a Piping Plover Protection Plan for construction activities at the landfall site (refer to Attachment G). Project construction on land at the Craigville Public Beach Landfall Site will remain entirely outside of mapped habitat, and the HDD will be performed entirely within existing paved surfaces. Furthermore, since the proposed cable installation method at the landfall site is HDD and would extend underneath the beach, there will be no disturbance to any areas of mapped Piping Plover habitat. In discussions with NHESP, potential noise disruption to existing nests was raised as a concern, and a mitigation option was discussed with the agency. NHESP suggested that if the HDD could begin before April 1 or after August 31, then a pair of birds would be aware of the noise prior to selecting a nesting location. As a result, the Proponent has made the commitment that 5526.10/New England Wind 1 Connector 14 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. HDD activities at the landfall site will begin in advance of April 1, or will not begin until after August 31, to avoid and minimize noise impacts to Piping Plover during the breeding season. (HCA provisions for the Project are anticipated to restrict work at the landfall site during the summer months.) The Centerville River crossing and the onshore duct banks are located outside of mapped habitat. The Proponent submitted a MESA Checklist pursuant to 321 CMR 10.18 for review in March 2022. On April 1, 2022, the NHESP issued a MESA Determination that with compliance with the Piping Plover Protection Plan, the Project will avoid a Take (see Attachment L). Pursuant to 310 CMR 10.37, the Proponent will submit a copy of this NOI to the NHESP. 3.2 Craigville Public Beach Landfall Site Since the Project’s early planning stages, Craigville Public Beach has been regarded as an excellent cable landfall site because it is stable, located in an area with favorable nearshore water depths, and has a large, paved parking lot that can accommodate construction staging and operations. It also has direct inland egress by way of sufficiently wide public streets to the grid interconnection point at the existing Eversource West Barnstable Substation. The Craigville Public Beach Landfall Site is located within a 3.5-acre paved parking area associated with a public beach that is owned and managed by the Town of Barnstable. The landfall site is located in the central part of the Centerville Harbor bight in an area where the shoreline is relatively stable. Adjoining land uses include homes along the north side of Craigville Beach Road, a private beach club (Craigville Beach Club) and associated parking to the west, a private bath house and parking to the east (owned by the nearby Christian Campground), and some open space. The area is most heavily used during the summer season. The Craigville Public Beach Landfall Site has adequate staging area and favorable route options to the proposed substation site. Representative photographs of the Craigville Public Beach Landfall Site are provided in Attachment D. The paved parking lot will be the staging area for HDD, which will accomplish the offshore-to- onshore transition of the two export cables while avoiding any impacts to the coastal beach or nearshore areas. HDD is described in greater detail in Section 4.2.1, and HDD engineering plans are provided in Attachment F. An area of coastal dune is located just north of the parking lot in the narrow area between the parking lot and Craigville Beach Road. Observed dune vegetation includes Seaside Goldenrod (Solidago sempervirens) and American Beach Grass (Ammophila breviligulata). The coastal dune and other coastal wetland resource areas present at the Craigville Public Beach Landfall Site are depicted in Figure 7. The detailed duct bank route is shown on the engineering plans in Attachment E. As described in Section 5.3.2, approximately 585 square feet of the Coastal Dune 5526.10/New England Wind 1 Connector 15 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. will be temporarily disturbed during installation of the proposed duct bank between the paved parking lot and Craigville Beach Road, although the dune will be restored according to the dune restoration plan provided as Attachment I. 3.3 Onshore Transmission Route The onshore transmission route begins just inland from the Craigville Public Beach Landfall Site (described in Section 3.2). Wetland resources along the onshore duct bank route are described in Section 3.3.1, and the Centerville River crossing is specifically described in Section 3.3.2. 3.3.1 Wetlands along the Duct Bank Route The onshore duct bank route will temporarily disturb coastal wetland resource areas in the vicinity of the Craigville Public Beach Landfall Site (see Figures 7 and 8). In this area, the Project will pass beneath approximately 0.2 miles (1,100 linear feet) of a barrier beach system located between Nantucket Sound and the Centerville River estuary which includes roadways, residential properties, and parking lots. Within the barrier beach system, installation of the buried duct bank will occur almost entirely within the paved surfaces of Craigville Beach Road and the paved parking lot at the landfall site. The only unpaved areas to be disturbed within the barrier beach are a narrow strip of remnant Coastal Dune located between the paved parking lot and Craigville Beach Road and a previously developed residential property at 2 Short Beach Road, which will be used for staging a trenchless crossing of the Centerville River (see Section 3.3.2 for additional information about the Centerville River crossing). The duct bank route will also cross approximately 0.4 miles (2,000 linear feet) of LSCSF in the vicinity of the landfall site. This includes the portion of the Project located within the barrier beach system as well as segments inland of the Centerville River estuary. Within LSCSF, duct bank installation will take place in previously altered areas, and the Project will have no permanent impacts to this resource since the underground duct bank will not alter existing topography or flood storage capacity. Approximately 0.1 miles (730 linear feet) of Riverfront Area (RFA) will be crossed in the vicinity of the Centerville River. As described above, work within RFA will be limited to previously developed and degraded areas including the roadbed of Craigville Beach Road and the residential property located at 2 Short Beach Road. No naturally vegetated areas of RFA will be altered either permanently or temporarily by the proposed duct bank installation beneath the Centerville River. Other wetland resource areas are also present at the Centerville River, which ebbs and flows with each tidal cycle. These include Land Containing Shellfish, Land Under the Ocean, areas of Salt Marsh along the toe of the riprap embankments that flank the north and south bridge approaches, as well as Coastal Bank represented by the embankments and bridge abutments. The upper boundary of the salt marsh was delineated by Epsilon scientists on May 28 and June 15, 2020. 5526.10/New England Wind 1 Connector 16 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. North of the Centerville River crossing, the onshore duct bank will be installed within existing roadway layouts (beneath pavement or within 10 feet of pavement) where direct impacts to wetland resource areas will be avoided. However, one segment along Shootflying Hill Road will pass within the state or locally jurisdictional 100-foot buffer zone of freshwater wetland resource areas including Land Under Water, Inland Bank, and Beach associated with Wequaquet Lake (see Figure 8). As elsewhere, the duct bank will be installed within the existing roadway layout beneath pavement or within 10 feet of pavement and will have no permanent impacts on the wetland resource areas. A detailed multi-sheet graphics set illustrating wetlands along the Preferred Route is provided as Figure 8. Although the Proponent anticipates utilizing the preferred route as described above, at this time there is a possibility that Variant 2 of the preferred route could be utilized instead. This variant is shown on Figure 8. It passes through the same wetland resource areas as the preferred route and also the 100-foot buffer zones of freshwater wetlands located further inland. As shown on Figure 8, this variant will pass through an additional approximately 300 feet of LSCSF and 400 linear feet of RFA associated with a culverted stream along South Main Street near the Weaver Road intersection. The duct bank in these areas will be installed within the roadway layout beneath pavement or within 10 feet of pavement and will not result in any direct impacts to the resource areas. Variant 2 will also pass through the 100-foot buffer zone of wetlands located on either side of the paved roadway in this same area, but appropriate erosion and sedimentation controls will avoid any impacts to these resources. 3.3.2 Centerville River Crossing The onshore transmission route will cross the Centerville River approximately a quarter mile north of the landfall site, where Craigville Beach Road crosses the river with an existing two-lane bridge. Near the Craigville Beach Road bridge, the river is approximately 260 feet wide, although it is significantly constricted by rip-rapped approaches and abutments on either side of the bridge, which has a clear span of only 75 feet (23 m). A fringe of salt marsh occurs along the riverbanks on either side of road, and a 200-foot-wide Riverfront Area extends from each riverbank. The bridge, reconstructed in 2002, is a fixed-span structure and its relatively low profile allows for the passage of only small boats. This low profile also means the existing bridge deck lies within the 100-year floodplain. The bridge deck is approximately 50 feet (15 m) wide and accommodates two lanes of traffic, with two sidewalks and a separate fishing platform on its south side. The existing bridge deck cannot support the additional weight of the cables and it is not feasible to maintain existing hydraulic clearance beneath the bridge with the addition of cables, which would be installed under the bridge. For those reasons the Project is not proposed within the existing bridge deck or attached to the structure to maintain reliability and avoid potential risk during storm conditions. While determining the most appropriate method for crossing the 5526.10/New England Wind 1 Connector 17 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Centerville River in this location, Project engineers assessed the viability of multiple design options, including replacement of the bridge superstructure, trenchless techniques (microtunnel, HDD, and direct pipe), and construction of a new utility bridge parallel to the existing bridge. The Proponent also discussed options for the Centerville River crossing with the Town of Barnstable and the Massachusetts Department of Transportation (MassDOT). Based on those consultations and engineering considerations, microtunnel has been selected as the proposed crossing technique. Microtunnel is a trenchless crossing technique that will avoid any impacts to the river itself and will leave the existing bridge unchanged, as opposed to installation of a new independent utility bridge or replacement of the existing bridge. Wetlands impacts associated with the microtunnel are described below and are summarized in Table 3-1. Table 3-1 Temporary Wetland Resource Area Impacts for Centerville River Crossing Microtunnel (square feet) Crossing Technique Temporary Impacts Barrier Beach Land Under the Ocean Salt Marsh Riverfront Area Coastal Beach Microtunnel 9,400 0 0 9,400 0 Microtunnel is a pipe jacking operation that utilizes a microtunnel boring machine (MTBM) pushed into the earth by hydraulic jacks in preparation for insertion of a concrete casing (as opposed to HDD, which drills a curved trajectory through which a conduit is subsequently installed) (see Section 4.2.2.2 for a more detailed discussion of microtunnel construction). All activities would be outside the river and riverbanks themselves but would temporarily affect approximately 9,400 square feet of the 200-foot RFA and barrier beach associated with equipment set up and staging; microtunnel would have no permanent impacts to either resource area. The work would also be located within LSCSF and within the regulatory buffer zone of salt marsh and land under the ocean, but again the activity would have no permanent impacts. The microtunnel operation is depicted on Figure 9 and in the engineering plans in Attachment H. This trenchless construction method will avoid impacts to other wetland resource areas located adjacent to the Centerville River including Salt Marsh, Land Under the Ocean, Land Containing Shellfish, and Coastal Bank. Each of these resource areas are shown on Figure 7. 4.0 Proposed Construction Activities and Impacts 4.1 Offshore Cable Installation This section describes the methods of cable installation that could be used to install the two proposed offshore export cables within the OECC in Barnstable waters. It also includes a description of the anticipated impacts from cable installation and associated activities (e.g., vessel anchoring). 5526.10/New England Wind 1 Connector 18 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 4.1.1 General Offshore Installation Methods The entirety of the two offshore export cables, including the length within Barnstable waters, will have a target burial depth of 5 to 8 feet (1.5 to 2.5 meters) below stable seabed, which Project engineers have determined is more than twice the burial depth that is required to protect the cables from potential anchor strikes or fishing activities. Several possible techniques may be used during cable installation to achieve the target depth (see description below). Generally, jetting methods are better suited to sands or soft clays, whereas a mechanical plow or mechanical trenching tool is better suited to stiffer soil conditions but is also effective in a wider range of soil conditions. While the actual offshore export cable installation method(s) will be determined by the cable installer based on site-specific environmental conditions and the goal of selecting the most appropriate tool for achieving adequate burial depth, the Proponent will prioritize the least environmentally impactful cable installation alternative(s) that is/are practicable for each segment of cable installation. The majority of the export cables are expected to be installed using simultaneous lay-and-bury via jetting techniques (e.g., jet-plow or jet trenching) or mechanical plow. However, the various installation methods identified below are retained as options to maximize the likelihood of achieving sufficient burial depth while minimizing the need for possible cable protection measures and accommodating varying weather conditions. The two most common methods are described below under “Typical Techniques.” Additional techniques that may be used more rarely are described below under “Additional Possible Specialty Techniques.” These specialty methods may be needed in areas of coarser or more consolidated sediment, rocky bottom, or other difficult conditions to ensure adequate burial depth is achieved (though it is worth noting that the OECC alignment avoids and minimizes passage through areas of hard bottom to the extent feasible). Typical Techniques i Jetting techniques (e.g., jet-plow or jet-trencher): Based around a seabed tractor, a sled, or directly suspended from a vessel, the tool typically has one or two arms that extend into the seabed (or alternatively a plow share that runs through the seabed) equipped with nozzles which direct pressurized seawater into the seafloor. As the tool moves along the installation route, the pressurized seawater fluidizes the sediment allowing the cable to sink under its own weight to the appropriate depth or be lowered to depth by the tool. Once the arm or share moves on, fluidized sediment will naturally settle out of suspension, backfilling the narrow trench. Depending on the actual jet-plow equipment used, the width of the fluidized trench could vary between 1.3 and 3.3 feet (0.4 – 1 m). While jet-plowing will fluidize a narrow swath of sediment, it is not expected to result in significant side cast of materials from the trench. Offshore cable installation will result in some temporary elevated turbidity, but this is expected to remain relatively close to the installation activities (see Section 4.1.3 for a discussion of sediment dispersion modeling). 5526.10/New England Wind 1 Connector 19 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. i Mechanical plowing: A mechanical plow is pulled by a vessel or barge and uses a cutting edge(s) and moldboard, possibly with water jet assistance, to penetrate the seabed while feeding the cable into the trench created by the plow. While the plow share itself would likely be only approximately 1.6 feet (0.5 m) wide, a 3.3-foot (1-m) wide disturbance area is also conservatively assumed for this tool. The narrow trench will infill behind the tool, either by slumping of the trench walls or by natural infill, usually over a relatively short period of time. Other Possible Specialty Techniques i Mechanical trenching: Typically used only in more resistant sediments, a rotating chain or wheel with cutting teeth or blades cuts a trench into the seabed. The cable is laid behind the trencher and the trench collapses and backfills naturally over a period of time. i Shallow-water cable installation vehicle: While any of the above typical techniques could be used in shallow water, the Project envelope also includes specialty shallow-water tools if needed. This system would use either of the Typical Techniques described above but is deployed from a vehicle that operates in shallow water where larger cable-laying vessels cannot efficiently operate. The cable is first laid on the seabed, and then a vehicle passes over or alongside the cable while operating an appropriate burial tool to complete installation. The vehicle is controlled and powered from a shallower-draft vessel that holds equipment and operators above the waterline. i Pre-pass jetting: Prior to cable installation, a pre-pass jetting run using a jet-plow or jet trencher may be conducted along targeted sections of the cable route with stiff or hard sediments. A pre-pass jetting run is an initial pass along the cable route by the cable installation tool that loosens the sediments without installing the cable. The pre-pass jetting run maximizes the likelihood of achieving sufficient burial during the subsequent pass by the cable installation tool when the cable is installed. Impacts from the pre-pass jetting run are largely equivalent to cable installation impacts from jetting described under “Typical Techniques” above. i Pre-trenching: A trench is excavated by a plow or other device, and the sediment is placed next to the trench. The cable is then laid in the trench. Separately or simultaneous to laying the cable, the sediment is returned to the trench to cover the cable. It is unlikely that the Project will use a pre-trench method, as site conditions are not suitable since sand would simply fall back into the trench before the cable-laying could be completed. Pre-trenching is typically used in areas of very stiff clays, where a displacement plow is used to create a wide trench within the seabed into which the cable is laid. 5526.10/New England Wind 1 Connector 20 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. i Pre-lay plow: In limited areas of resistant sediments or high concentrations of boulders, a larger tool may be necessary to achieve cable burial. One option is a robust mechanical plow that would push boulders aside while cutting a trench into the seabed for subsequent cable burial and trench backfill. Similar to pre-trenching, if this tool is needed it would only be used in limited areas to achieve sufficient cable burial. i Boulder relocation: Any boulders identified along the cable alignments will need to be relocated prior to cable installation, facilitating installation without any obstructions to the burial tool and better ensuring sufficient burial. Boulder relocation is accomplished either by means of a grab tool suspended from a crane onboard a vessel that lifts individual boulders clear of the route, or by using a plow-like tool which is towed along the route to push boulders aside. Boulders will be shifted perpendicular to the cable route; no boulders will be removed from the area. i Precision installation: In situations where a large tool is not able to operate, or where another specialized installation tool cannot complete installation, a diver, or Remotely Operated Vehicle (ROV) may be used to complete installation. The diver or ROV may use small jets and other small tools to complete installation. i Jetting by controlled flow excavation: Jetting by controlled flow excavation uses a pressurized stream of water to push sediments to the side. The controlled flow excavation tool draws in seawater from the sides and then jets this water out from a vertical down pipe at a specified pressure and volume. The down pipe is positioned over the cable alignment, enabling the stream of water to fluidize the sediment around the cable, which allows the cable to settle into the trench. This process causes the top layer of sediments to be side cast to either side of the trench. This method will not be used as the conventional burial method for the offshore export cables, but may be used in limited locations, such as to bury splice joints or to bury the cable deeper and minimize the need for cable protection where initial burial of a section of cable does not achieve sufficient depth. Typically, a number of passes are required to lower the cable to the minimum sufficient burial depth, resulting in a wider disturbance than use of a jet-plow or mechanical plow. Jetting is not to be confused with a jet-plow or jet trencher used for typical cable installation described above. Jetting can also be used for dredging small sand waves. Cable burial will temporarily displace marine sediments, but in normal operations these displaced sediments return to the ocean floor in the wake of the cable installation vehicle generally within a few meters of the furrow created by the cable installation. Particle sediment monitoring studies 5526.10/New England Wind 1 Connector 21 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. recently completed for the Block Island Wind Farm’s offshore cable installation found that displaced sediments were an average of 12.5 feet (3.8 m) from the trench with a thickness of 2.8 inches (7 cm).3 For any of the offshore export cable installation methodologies described above, the trench would be expected to backfill naturally after passage of the installation tool since surveys have identified only granular material (not clays) along the OECC. Where cobbles are present on the seafloor, they are mixed with granular material (e.g., sand), and therefore even though cobbles may be present, the sediment is expected to behave as a frictional material, resulting in natural backfilling of the trench. Given the high-energy marine environment along the OECC, this trench backfilling is likely to occur in a short period of time; this process was most recently evidenced in the Martha’s Vineyard Hybrid Cable Project installed from Falmouth to Tisbury (on Martha’s Vineyard) over an approximately seven-month period in 2013-2014. In accordance with normal industry practice, a pre-lay grapnel run will be made to locate and clear obstructions such as abandoned fishing gear and other marine debris in advance of cable installation. Operations for the pre-lay grapnel run will consist of a vessel towing equipment that will hook and recover obstructions such as fishing gear, ropes, and other debris from the seafloor. The Proponent estimates this activity will begin any time up to two months prior to cable installation. Any abandoned fishing gear recovered will be disposed of or returned to its owner in accordance with requirements of the Massachusetts DMF and other relevant Massachusetts regulations. The proposed offshore cables will be deployed from a turntable mechanism aboard a cable ship or cable barge and installed along a surveyed alignment. This alignment will be within the OECC to enable the avoidance or minimization of impacts. For the integrity of the cable, installation is ideally performed as a continuous action along the entire cable alignment up to splice joints. The route engineering process is extensive to avoid and minimize impacts to areas of hard bottom and complex bottom, for example, and to maximize the likelihood of successful cable burial. While a straight-line route is, under ideal circumstances, the most efficient, this route engineering process includes micro-siting around features such as boulders or other obstacles. The pre-lay survey will be the final opportunity to make any additional micro-siting alterations to the intended cable alignment before installation, and as such is the final step of major route planning. Because the cable alignment is the product of careful route engineering and the length of available cable is finite, real-time micro-siting during cable installation is limited. Such micro-siting would only occur if a significant challenge arose such as an unforeseen obstacle. The specific, as-built cable alignment will be recorded by the cable installation contractor during installation to record the precise location (x and y) of each offshore export cable as well as the achieved burial depth (z). 3 James Elliott, K. Smith, D.R. Gallien, and A. Khan. 2017. Observing Cable Laying and Particle Settlement During the Construction of the Block Island Wind Farm. Final Report to the U.S. Department of the Interior, Bureau of Ocean Energy Management, Office of Renewable Energy Programs. OCS Study BOEM 2017-027. 225 pp. 5526.10/New England Wind 1 Connector 22 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Cable burial tools (e.g., jet-plow, mechanical plow) can be mounted on a sled pulled by the cable- laying vessel or can also be mounted on a self-propelled underwater tracked vehicle. The tracked vehicle would run along the seafloor using a power feed from the cable-laying vessel. This type of vehicle is routinely used for wind energy cable projects in Europe and has proven effective in dynamic marine environments similar to the proposed Project route. Typical cable installation speeds are expected to range from 100 to 200 meters per hour, and it is expected that installation activities for the offshore export cables will occur 24 hours per day. It is anticipated that installation activities for the offshore export cables will require continuous construction once begun. During installation, the cable will be deployed from a turntable on the installation vessel or barge and buried beneath the seafloor. For the integrity of the cable, this activity is ideally performed as a continuous action along the entire cable alignment up to splice joints. Although the Proponent is considering the use of dynamic positioning (DP) vessels, many portions of the OECC are too shallow for DP cable-laying vessels. As a result, anchored cable-laying vessels are assumed to be necessary along the entire length of the OECC, as discussed in Section 4.1.2.2. However, the Proponent will use DP vessels to the maximum extent practicable to minimize actual impacts from anchoring during construction. The Proponent’s preferred installation approach is to install the offshore export cables sequentially. Given that installation of both cables at the same time would require two separate vessel spreads, at considerable expense and with additional logistical challenges, it is unlikely that both cables would be installed at the same time. The proposed offshore export cables will be installed within largely the same OECC as Vineyard Wind Connector’s offshore export cables. The cables will typically be separated by a distance of approximately 165 to 330 feet (50 to 100 m) to provide appropriate flexibility for routing and installation and to allow room for maintenance or repairs. This separation distance could be further adjusted, pending ongoing routing evaluation, to account for local conditions such as deeper waters, micro-siting for sensitive habitat areas, or other environmental or technical reasons. Spacing will be adequate to minimize the risk of damaging previously installed cable (e.g., the first cable of the pair) while providing sufficient space for future maintenance and repair activities, should they be necessary. 4.1.2 Anticipated Offshore Project Impacts Table 4-1 provides the most current estimates for seabed impacts associated with the installation of the two proposed offshore export cables in Barnstable waters. As described in Section 3.1, results from multiple seasons of marine surveys have enabled the Proponent to refine the mapping of hard bottom, complex bottom, and eelgrass within the OECC, and the Proponent’s engineers have defined preliminary cable alignments within the OECC to avoid and minimize impacts to hard bottom and complex bottom (the Project will not impact eelgrass or core habitat of the North Atlantic Right Whale). 5526.10/New England Wind 1 Connector 23 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Table 4-1 Impacts to Land Under the Ocean from Installation of Two Offshore Export Cables within Barnstable Waters Offshore Export Cable Corridor Characteristics Total Length (statute miles)1 13.2 (2 cables along 6.8 miles of the OECC, minus ~0.2-mile HDD for each cable) Trench impact zone (acres)2 5.3 Disturbance zone from tool skids/tracks (acres)3 16.0 Direct dredging impacts (acres)4 10.8 Anchoring (acres)5 3.7 Cable Protection (acres)6 0.2-0.6 Nearshore Grounding (acres)7 4.8 1 Route lengths provided in statute miles, with 1 mile = 0.87 nautical miles. This length is based on the length of OECC within Barnstable waters. 2 Based on information from the Proponent’s engineers, depending on the tool used for cable installation (e.g., jet-plow, mechanical plow, etc.), the direct trenching impact area will vary between 1.3 and 3.3 feet (0.4 – 1 m) in width. The impact area provided in the table reflects the most conservative 3.3-foot (1-m) impact width. 3 Depending on the tool used for cable installation (e.g., jet-plow, mechanical plow), each skid/track on the installation tool will have the potential to cause minor disturbance along an area approximately 5 feet (1.5 m) wide, although the functional impact is expected to be minor. The impact area identified in the table reflects the temporary impact from two skids/tracks, and therefore assumes a 10-foot-wide (3-m-wide) disturbance zone. 4 Direct dredging impacts are calculated based on the estimated length of dredging and assumed sideslopes of approximately 1:3. Since the dredging area will overlap with the 3.3-foot (1-m) wide trench impact zone and 10-foot (3-m) wide skid disturbance zone, these areas have been subtracted from the dredging impact area to avoid double-counting impacts. See Section 4.1.2.4 for more details. 5 See Section 4.1.2.2. 6 Although the Proponent’s priority is to achieve sufficient burial depth and avoid cable protection, some cable protection may be required. The estimated length of cable protection in Barnstable waters is approximately 0.16 miles (0.26 km). The area of potential impact from cable protection is provided as a range, since the impact width may vary between 10 feet (3 m) and 30 feet (9 m) depending on the method utilized (see Section 4.1.2.3). 7 See Section 4.1.2.2. Anticipated impacts associated with specific operations required to complete the offshore export cable installations in Barnstable waters are discussed in the following sections. For all portions of the OECC, recolonization and recovery to pre-construction species assemblages is expected given the similarity of nearby habitat and species. Nearby, unimpacted seafloor will likely act as refuge area and supply a brood stock of species, which will begin recolonizing disturbed areas post-construction. Recovery timeframes and rates in a specific area depend on disturbance, sediment type, local hydrodynamics, and nearby species virility.4 Previous research conducted on benthic community recovery after disturbance found that recovery to pre- 4 Dernie, K. M., Kaiser, M. J., & Warwick, R. M. (2003). Recovery rates of benthic communities following physical disturbance. Journal of Animal Ecology, 72 (6),1043-1056. 5526.10/New England Wind 1 Connector 24 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. construction biomass and diversity values took two to four years.5 Other studies have observed differences in recovery rates based on sediment type, with sandy areas recovering more quickly (within 100 days of disturbance) than muddy/sand areas.6 4.1.2.1 Cable Installation Tool Offshore export cable installation tools are described in detail in Section 4.1.1. A variety of tools may be used for portions of the OECC, many of which are specialized and would be used only in limited areas where specific conditions are encountered. Typical techniques include jetting techniques (e.g., jet-plow or jet trenching) or a mechanical plow, either of which would have a temporary trench disturbance up to approximately 3.3 feet (1 m) wide. In addition to the trench impact on the seafloor, the cable installation tool may move along the seafloor on skids or tracks. These skids or tracks, each up to approximately 5 feet (1.5 m) wide, will slide over the surface of the seafloor, and as such have the potential to disturb benthic habitat; however, they are not expected to dig into the seabed, and therefore the impact is expected to be minor. Since the cable installation will affect a corridor that will pass similar habitats on adjacent sides, the area affected by cable burial or skids/tracks on the installation tool is expected to recolonize relatively quickly. As described in Section 4.1.3, while cable installation activities will result in some temporary elevated turbidity and localized sediment dispersion in the water column, the sediment, which is briefly fluidized by the cable installation tool, will quickly settle out of the water column. A BOEM study published in March 2017 assessed impacts from cable-laying activities associated with construction of the Block Island Wind Farm.7 That study identified formation of a temporary 2.7-inch-high “overspill levee” on either side of the cable placement. The overspill levee consisted of material deposited outside of the trench during jet-plow activities. The BOEM study indicated that overspill levees were observed an average distance of 12.5 feet (3.8 m) from the centerline of the trench (for an average total impact width of 25 feet) at an average thickness of 2.7 inches (7 cm). Importantly, the study described the overspill levees as very temporary features that were only apparent for a few days following cable installation, and that they were gone within one to two weeks. The study authors noted: 5 Van Dalfsen, J. A., & Essink, K. (2001). Benthic community response to sand dredging and shoreface nourishment in Dutch coastal waters. Senckenbergiana marit, 31(2),329-32. 6 (1) Freiwald, A., Fosså, J.H., Grehan, A., Koslow, T., Roberts, J.M. (2004). Cold-water Coral Reefs. UNEP-WCMC, Cambridge, UK; and (2) Rogers, A. (2004). The biology, ecology and vulnerability of deep-water coral reefs. International Union for Conservation of Nature and Natural Resources. 10 pp. 7 James Elliott, K. Smith, D.R. Gallien, and A. Khan. 2017. Observing Cable Laying and Particle Settlement during the Construction of the Block Island Wind Farm. Final Report to the U.S. Department of the Interior, Bureau of Ocean Energy Management, Office of Renewable Energy Programs. OCS Study BOEM 2017-027. 225 pp. 5526.10/New England Wind 1 Connector 25 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. We attribute the ability to discern the overspill levees to surveying during jet-trenching and within a few days after the jet-trenching occurred from the mainland cable lay… We have noted that on post-lay surveys conducted 1 to 2 weeks after trenching, that overspill levees are rarely distinguishable.8 Given the dynamic marine environment, the Proponent anticipates that the trench area, regardless of which cable installation method is used, will be quickly reworked by currents, refilling possible low portions of the trench as quickly as they would remove any potential “overspill levees”. The Proponent is committed to developing an appropriate benthic habitat monitoring plan (BHMP) for the Project in consultation with state and federal agencies. In October 2021, the Proponent consulted with agency representatives from CZM, MassDEP, and DMF to specifically discuss a framework for benthic habitat monitoring of the cables proposed for NE Wind 1 Connector/Park City Wind; the framework was presented in Section 2.1.4 of the FEIR. The Proponent will continue to work cooperatively with state and federal agencies during permitting to develop a final plan intended to document habitat and benthic community disturbance and recovery following construction. The Proponent anticipates this plan will be memorialized in the Section 401 Water Quality Certification (WQC) to be issued by MassDEP. The Proponent will prioritize the least environmentally impactful cable installation alternative(s) that is/are practicable for each segment of cable installation. In addition to selecting an appropriate tool for the site conditions, the Proponent will work to minimize the likelihood of insufficient cable burial. For example, if the target burial depth is not being achieved, operational modifications may be required. Subsequent attempts with a different tool (such as controlled flow excavation) may be required where engineering analysis indicates subsequent attempts may help achieve sufficient burial. 4.1.2.2 Anchoring In certain locations, the Proponent is assessing the potential use of Dynamic Positioning (DP) vessels, but many portions of the OECC are too shallow for DP cable-laying vessels. Because of the shallow waters in Barnstable, conservatively, anchored cable-laying vessels are expected to be used along the entire length of the OECC in Barnstable waters. Anchored vessels will avoid sensitive seafloor habitats to the greatest extent practicable. Contractors will be provided with a map of sensitive habitats prior to construction with areas to avoid and shall plan their mooring positions accordingly. Vessel anchors will be required to avoid known eelgrass beds and will avoid other sensitive seafloor habitats and SSU areas (e.g., hard, or complex bottom) as long as it does not compromise the vessel’s safety or the cable installation. Where it is considered impossible or impracticable to avoid a sensitive seafloor habitat when anchoring, use of mid-line anchor buoys will be considered, where feasible and considered safe, as a potential measure to reduce and 8 James Elliott, K. Smith, D.R. Gallien, and A. Khan. 2017. Observing Cable Laying and Particle Settlement during the Construction of the Block Island Wind Farm. Final Report to the U.S. Department of the Interior, Bureau of Ocean Energy Management, Office of Renewable Energy Programs. OCS Study BOEM 2017-027. p.46. 5526.10/New England Wind 1 Connector 26 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. minimize potential impacts from anchor line sweep. Mid-line buoys are placed somewhere along the length of an anchor line to support the weight of the line and hold a portion of the line off the seabed. By suspending the anchor lines, mid-line buoys prevent the line from dragging and scouring the seafloor, which minimizes anchor sweep and associated impacts. Vessel operators will determine when the use of mid-line anchor buoys is considered infeasible and/or unsafe. The discussion below presents a conservative estimate of potential anchoring impacts in Barnstable. Project engineers estimate approximately 323 square feet (30 m2) of disturbance from each anchor (assuming an approximately 10-ton anchor), such that a vessel equipped with nine anchors would disturb approximately 2,900 square feet (270 m2) per each anchoring set.9 A nine-point anchor spread provides greater force on the cable burial tool than a spread with fewer anchors, enabling greater burial depth, and the assumptions herein include a larger anchor to accommodate larger installation vessels. In addition, anchored vessels may deploy up to two spud legs at each anchoring location to secure the cable-laying vessel while its anchors are being repositioned. Each deployment of two spuds would affect approximately 108 square feet (10 m2) of seafloor, making the total disturbance per anchoring set approximately 3,008 square feet (280 m2). Potential impacts from anchoring are summarized in Table 4-1, and the calculation of impacts from anchoring is shown in Table 4-2. Anchoring will not be performed in eelgrass. Table 4-2 Estimated Anchoring Impacts from Installation of 2 Offshore Export Cables in Barnstable Waters. Impact from Anchoring Length in Barnstable waters (miles) 13.2 (both cables combined minus HDD length) Disturbance per anchoring set 3,008 sf # of repositioned anchoring sets* 53 Total temporary impact 3.7 acres * Assumes an anchored installation vessel may need to reposition every approximately 1,312 feet (400 m). In addition to the anchoring impacts presented in Table 4-2, to install the cable close to shore using tools that are best optimized to achieve sufficient cable burial, the cable laying vessel may temporarily ground nearshore, impacting an area of up to 2.4 acres (9,750 m2) per cable (4.8 acres total). These temporary potential impacts are included in Table 4-1. Any anchoring, spud leg deployment, or grounding will occur within surveyed area of the OECC. 9 The impacts from anchor sweep are not quantified at this time due to the difficulty of estimating potential anchoring practices at this planning stage. 5526.10/New England Wind 1 Connector 27 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 4.1.2.3 Cable Protection The Proponent’s priority will be to achieve adequate burial depth of the two offshore export cables and to avoid the need for any cable protection. However, it is possible that achieving adequate burial depth may be unsuccessful in areas where the seafloor is composed of consolidated materials, making complete avoidance of cable protection measures unlikely. In the event sufficient burial depth cannot be achieved, alternative cable protection methods may be necessary. The Proponent will seek to avoid and/or minimize the use of such cable protections, and cable protection will only be used where necessary, thus minimizing potential impacts. Except for limited areas where the sufficient cable burial is not achieved and placement of cable protection on the seafloor is required, offshore export cables are not anticipated to interfere with any typical fishing practices. Should cable protection be required, it will be designed to minimize impacts to fishing gear to the extent feasible, and fishermen will be informed of the areas where protection is used. Any type of cable protection has the potential to snag fishing gear, but such protection is designed to minimize the risk of such snagging. If needed, the methods for cable protection will be: i Rock placement: Rocks could be laid on top of the cable to provide protection. If rocks were to be placed, they would be installed in a controlled and accurate manner on the seafloor using a dynamic positioning fall-type vessel. Rocks used for cable protection would be sized for site-specific conditions; where feasible, this protection will consist of rocks approximately 2.5 inches (6.4 cm) in diameter or larger.10 The target range in rock sizes used in this type of cable protection is typically between approximately 2 and 6 inches (50-150 mm) in diameter. i Gabion rock bags: This method involves rocks encased in a net material (e.g., a polyester net) that can be accurately deployed on top of the cable and subsequently recovered, if necessary, for temporary or permanent cable protection. Each bag is equipped with a single lifting point to enable its accurate and efficient deployment and recovery. These rock bags have been deployed in other high-energy marine environments such as the North Sea, and the net material used for the rock bags is designed to have an approximately 50-year lifespan. These bags typically contain gravel approximately 0.8 inches (20 mm) in diameter, since this allows the bag to somewhat conform to the shape of the exposed cable. i Concrete mattresses: These “mattresses” are prefabricated flexible concrete coverings consisting of high-strength concrete profiled blocks cast around a mesh material (e.g., ultra-violet stabilized polypropylene rope) that holds the blocks together. This mattress construction provides flexibility, enabling the mattress to settle over the contours of the 10 Some rocks may be fragmented into smaller pieces during handling, transport, and installation. 5526.10/New England Wind 1 Connector 28 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. cable and seafloor. The mesh in this application would be designed to have a decades- long lifespan. The mattress may also include aerated polyethylene fronds, which will float (resembling seaweed) and encourage sediments to be deposited on the mattress. i Half-shell pipes or similar (only for cable crossings or where the cable is laid on the seafloor): These products are made from composite materials and/or cast iron with suitable corrosion protection and are fixed around the cable to provide mechanical protection. Half-shell pipes or similar solutions are not used for remedial cable protection but could be used at cable crossings or where cable must be laid on the surface of the seabed. The half-shell pipes do not ensure protection from damage due to fishing trawls or anchor drags (although they will offer some protection, they will not prevent damage). Project engineers estimate that approximately 0.16 miles (0.26 km) of cable protection may be required along both offshore export cable alignments, combined, within Barnstable waters. Assuming concrete mattresses are used, the Proponent’s engineers have determined that cable protection of approximately 10 feet (3 m) wide will be sufficient to protect the cable. Should rock placement be used for cable protection, a greater width of approximately 30 feet (9 m) would be needed to account for sideslopes.11 If gabion bags are utilized, any width can be installed by using multi-compartment bags. However, at this time the Proponent’s engineers do not anticipate needing a width greater than 10 feet using gabion bags (i.e., the same width as the concrete mattresses) unless perhaps they are utilized temporarily at the seaward end of the HDD conduit prior to cable pull-back. The impact calculations for cable protection, presented in Table 4-1, show the range of possible impacts based on the varying widths of cable protection methods. The Proponent intends to avoid or minimize the need for cable protection to the greatest extent feasible through careful site assessment and thoughtful selection of the most appropriate cable installation tool to achieve sufficient burial. Areas requiring cable protection, if any, will be the only locations where post-installation conditions at the seafloor may permanently differ from existing conditions; however, such cable protection would only be expected within hard bottom areas, and the cable protection itself would function as hard bottom. 4.1.2.4 Sand Wave Dredging As described in Section 3.1, some portions of Nantucket Sound have areas of complex bottom composed of active sand waves, which have been assessed over multiple seasons of marine surveys. Sand waves are dynamic features with changing morphology that move across the 11 There are currently no anticipated cable crossings for the proposed Project. Should a cable crossing become necessary, cable protection of up to 30 feet (9 m) wide may be necessary. In addition, based on the actual conditions encountered at splice joint locations, cable protection width may vary, but if wider than 9 feet (3 m) the cable protection at splice joints is expected to fall within total cable protection estimates. 5526.10/New England Wind 1 Connector 29 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. seafloor. As a result, where sand waves are large, it may be necessary to perform pre-cable-laying dredging to remove the tops of these features along the cable alignment to ensure sufficient burial within the underlying stable seabed. The stretch of the OECC where sand wave dredging may be needed is largely coincident with areas mapped as complex bottom as shown on Figure 3. It is important to note that dredging, if performed, would not occur along the entire stretch where sand waves may be present; rather, dredging would only be performed to remove the tops of each sand wave to the extent needed at the time of construction to ensure sufficient burial within the stable seabed. Dredging will be performed as close in time to cable installation as possible to avoid mobile sand waves recovering the dredged area. Dredging will be limited to only the extent required to achieve adequate cable burial depth during cable installation. Where dredging is necessary, it is conservatively assumed that the dredged area will typically be approximately 50 feet (15 m) wide at the bottom (to allow for equipment maneuverability) with approximately 1:3 sideslopes for each of the two cables. The depth of dredging will vary with the height of sand waves, and hence the dimensions of the sideslopes will likewise vary with the depth of dredging and sediment conditions. This dredge corridor includes the up to 3.3-foot-wide (1-m-wide) cable installation trench and the up to 10-foot-wide (3-m- wide) temporary disturbance zone from the tracks or skids of the cable installation equipment. For both offshore export cables combined, the Proponent’s engineers anticipate that the length of sand wave dredging in Barnstable waters could be approximately 2.0 miles (3.2 km) and the area impacted by dredging in Barnstable waters could be approximately 10.8 acres (inclusive of sideslopes but excluding the overlapping impacts from trenching and tool skids). The estimated volume of dredged material in Barnstable waters is up to approximately 23,800 cubic meters (31,000 cubic yards). Due to the morphology of the sand wave features, and their mobility across the seafloor, even small changes in the cable alignments can result in changes to the potential dredge volumes. Actual dredge volumes will depend on the final cable alignments and cable installation method; a cable installation method that can achieve a deeper burial depth will require less dredging. The average dredge depth is expected to be approximately 1.6 feet (0.5 m) and may range up to a maximum of approximately 17 feet (5.25 m) in localized areas. With respect to potential habitat impacts, sand wave areas are intrinsically dynamic and unstable, and while dredging will be avoided and minimized wherever possible, those areas are typically sub-optimal areas for benthic organisms. Dredging could be accomplished by several techniques. European offshore wind projects have typically used a TSHD. A TSHD vessel contains one or more drag arms that extend from the vessel, rest on the seafloor, and suction up sediments. Dredges of this type are also commonly used in the U.S. for channel maintenance, beach nourishment, and other uses. For the Project, a TSHD would be used to remove enough of the top of a sand wave to allow subsequent cable installation within the stable seabed. Where a TSHD is used, it is anticipated that the TSHD would dredge 5526.10/New England Wind 1 Connector 30 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. along the cable alignment until the hopper is filled to an appropriate capacity, then the TSHD would sail several hundred meters away and deposit the dredged material within an area of the surveyed corridor that also contains sand waves (see Figure 3). A second dredging technique involves jetting by controlled flow excavation. Controlled flow excavation uses a pressurized stream of water to push sediments to the side. The controlled flow excavation tool draws in seawater from the sides and then propels the water out from a vertical downpipe at a specified pressure and volume. The downpipe is positioned over the cable alignment, enabling the stream of water to fluidize the sediments around the cable, which allows the cable to settle into the trench. This process causes the top layer of sediments to be side cast to either side of the trench; therefore, controlled flow excavation would both remove the top of the sand wave and bury the cable. Typically, a number of passes are required to lower the cable to the minimum sufficient burial depth. A TSHD can be used in sand waves of most sizes, whereas the controlled flow excavation technique is most likely to be used in areas where sand waves are less than 6.6 feet (2 m) high. Therefore, the sand wave dredging could be accomplished entirely by the TSHD on its own, or the dredging could be accomplished by a combination of controlled flow excavation and TSHD, where controlled flow excavation would be used in smaller sand waves and the TSHD would be used to remove the larger sand waves. No dredging is proposed in hard-bottom areas (e.g., boulders, cobble bottom). The only dredging proposed for the Project is where large sand waves, features that can be considered “complex” due to their bathymetric relief, necessitate pre-cable-laying dredging to ensure that the necessary burial depth can be achieved. As noted previously, sand waves, although they do provide bathymetric variability, are seafloor features that change quickly and hence do not enable the formation of complex benthic communities. 4.1.3 Sediment Dispersion and Turbidity To gain a thorough understanding of the sediment dispersion resulting from the Project’s cable installation operations, a Hydrodynamic and Sediment Dispersion Modeling Study was prepared by RPS and was presented in Section 8.2.1 of the Project’s DEIR, which was provided to the Barnstable Conservation Commission. The DEIR can also be found at https://www.parkcitywind.com/permitting. The Proponent requests that the more detailed information in the MEPA filing be incorporated by reference into this submission. Results of the study are summarized below: The modeling was performed to characterize the effects associated with the offshore cable installation activities. The effects were quantified in terms of the above-ambient total suspended solids (TSS) concentrations as well as seabed deposition of sediments suspended in the water column during cable installation activities. 5526.10/New England Wind 1 Connector 31 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. The Hydrodynamic and Sediment Dispersion Modeling Study shows that impacts from cable installation activities are expected to be localized and short term, as most of the mass settles out quickly and is not transported for significant distances by the currents. Above-ambient TSS concentrations stemming from cable installation for the various model scenarios remain relatively close to the cable alignment, are constrained to the bottom of the water column, and are short- lived. Above-ambient TSS concentrations substantially dissipate within one to two hours and fully dissipate in less than four hours for most of the model scenarios. Similarly, for the vertical injector model scenario, above-ambient TSS concentrations substantially dissipate within one to two hours but required up to six hours to fully dissipate, likely due to the relatively slower installation rate and deeper trench (greater volume disturbed per unit length). Above-ambient TSS concentrations greater than 10 mg/L typically stay within approximately 650 feet (200 m) of the cable alignment. Importantly, all suspended sediments are expected to settle out within a matter of hours (less than 4-6) from disturbance during typical cable installation. Simulations of typical cable installation parameters (without sand wave removal) in the OECC indicated that deposition of 1 mm (0.04 in) or greater (i.e., the threshold of concern for demersal eggs) was constrained to within approximately 330 feet (100 m) from the route centerline and maximum deposition was typically less than 5 mm (0.20 in) (the threshold of concern for shellfish), though there was a small isolated area associated with the vertical injector model scenario with deposition between 5 to 10 mm (0.2 to 0.4 in). For context, BOEM stated in the DEIS for the Vineyard Wind project that “suspended sediment concentrations between 45 and 71 mg/L can occur in Nantucket Sound under natural tidal conditions, and increases in suspended sediment concentrations due to jet-plow are within the range of variability already caused by tidal currents, storms, trawling, and vessel propulsion.”12 Further, BOEM concluded that it expects only minor impacts on water quality due to suspended sediment during installation, dredging, and cable-laying because of the brief duration and small area of impact. For all portions of the OECC, recolonization and recovery to pre-construction species assemblages is expected given the similarity of nearby habitat and species. Nearby, unimpacted seafloor will likely act as refuge area and supply a brood stock of species, which will begin recolonizing disturbed areas post-construction. Recovery timeframes and rates in a specific area depend on disturbance, sediment type, local hydrodynamics, and nearby species virility.13 Previous research conducted on benthic community recovery after disturbance found that recovery to pre- 12 Vineyard Wind Offshore Wind Energy Project, Draft Environmental Impact Statement, U.S. Department of the Interior, Bureau of Ocean Energy Management, Office of Renewable Energy Programs, December 2018. 13 Dernie, K. M., Kaiser, M. J., & Warwick, R. M. (2003). Recovery rates of benthic communities following physical disturbance. Journal of Animal Ecology, 72 (6),1043-1056. 5526.10/New England Wind 1 Connector 32 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. construction biomass and diversity values took two to four years.14 Other studies have observed differences in recovery rates based on sediment type, with sandy areas recovering more quickly (within 100 days of disturbance) than muddy/sand areas.15 In summary, results of the Hydrodynamic and Sediment Dispersion Modeling Study demonstrate that impacts will be short-term, as excess TSS concentrations are expected to only persist for a few hours and deposition is expected to typically be less than 5 mm, which is less than the sensitivity threshold for benthic organisms. Conservative impact assumptions show that impacts on fish and shellfish will be limited in area and duration and will allow for rapid recovery to pre- installation conditions. The Project will use cable installation techniques that minimize sediment disturbance and dispersion consistent with the best available practices. 4.2 Onshore Construction 4.2.1 HDD Construction Methodology HDD is the primary means of minimizing Project-related impacts to the beach, intertidal zone, and nearshore areas, as well as ensuring that the cables remain sufficiently buried and permanently out of the human environment at the shoreline. HDD is a trenchless installation technique that will avoid disturbance to the shoreline and nearshore areas by negating the need to open- excavate existing coastal wetland resource areas; it will also avoid disturbing recreational use of the beach. At the landfall site, the proposed HDD would be approximately 1,000 to 1,200 feet (300-365 meters) long and angled offshore to avoid an area of hard bottom and co-located eelgrass (see Figure 3). Although the HDD trajectory is still undergoing engineering refinement, it is estimated that the trajectory will result in the HDD passing at a depth of approximately 40 feet below the ground surface at MHW. Plan and profile views of the proposed HDD are provided in the engineering plans in Attachment F, and the HDD construction layout is shown in Figure 10. HDD would be performed in the off-season using a staging area in the paved Town-owned Craigville Public Beach parking lot west of the bath house. The entire parking lot east of the bath house, and a significant portion of the parking lot west of the bath house, would remain available during construction. The Proponent will work with the Town of Barnstable to ensure that acceptable access is available to the beach during construction. 14 Van Dalfsen, J. A., & Essink, K. (2001). Benthic community response to sand dredging and shoreface nourishment in Dutch coastal waters. Senckenbergiana marit, 31(2),329-32. 15 (1) Freiwald, A., Fosså, J.H., Grehan, A., Koslow, T., Roberts, J.M. (2004). Cold-water Coral Reefs. UNEP-WCMC, Cambridge, UK; and (2) Rogers, A. (2004). The biology, ecology and vulnerability of deep-water coral reefs. International Union for Conservation of Nature and Natural Resources. 10 pp. 5526.10/New England Wind 1 Connector 33 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 4.2.1.1 HDD Construction Sequence and Schedule The construction sequence for installation via HDD at the landfall will consist of the following methods: 1. Entry Pit: Land-based HDD rigs are typically staged behind a shallow entry pit, which for this Project will measure approximately 10 by 20 feet for each drill path entry point. The entry pit will provide the contractor with access to the proper trajectory for drilling and will also serve as a reservoir for drilling fluids (i.e., a slurry consisting predominantly of water and bentonite, a naturally occurring, inert and non-toxic clay) used to convey soil cuttings from the borehole. 2. Installation of Temporary Surface Casing: A steel pipe, 54 inches or 60 inches in diameter, will be installed along the entry tangent of the HDD bore for a distance of approximately 100 feet through the shallow, relatively loose formation. This will provide a stable corridor for tooling to enter the bore as well as for the drilling fluids and cuttings to be conveyed to the entry pit reservoir. Upon installation of the HDPE conduit, the surface casing will be removed. 3. Pilot Hole: A small pilot hole (typically eight to twelve inches in diameter) will be drilled from the entry pit to a pre-determined location offshore, where the offshore cable installation will terminate. The pilot hole will be drilled at an entry angle of typically 8 to 18 degrees such that it arcs down beneath the nearshore coastal resources and extends to a minimum depth of approximately 40-50 feet below the ground surface at MHW. The path of the pilot hole will follow a tangent trajectory, maintaining a constant depth of cover beneath the seafloor, before starting to ascend toward the desired exit point on the seafloor that will be the transition point between the offshore cable installation and the seaward end of the HDD. Drilling fluid (a bentonite slurry) will be used to stabilize the borehole, convey soil cuttings out of the bore, cool and lubricate the drill bit, stem, and other downhole tooling, and will also serve to seal the wall of the borehole. 4. Surfacing of HDD Pilot Hole: After completion of the borehole, the drill rod will be advanced for a short distance so it can be located by divers. At the HDD exit point, a temporary receiving pit will be excavated. Given the coarse-grained nature of sediments at the HDD exit hole location and the small diameter of the pilot hole, little turbidity is expected as the drill head reaches the seafloor surface. Although not anticipated (because injection of bentonite fluid will be halted prior to the drilling head reaching the seafloor), a small amount of bentonite clay could be released at the exit point of the HDD operation, and the contractor may install silt curtains at the exit point; alternatively, where the pilot hole exits the seafloor, the contractor may lower a gravity cell that would capture any incidental bentonite drilling fluid released from the end of the HDD drill. Bentonite clay is an inert, naturally occurring substance and is appropriate for use in 5526.10/New England Wind 1 Connector 34 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. sensitive environments because it poses minimal environmental risks; for this reason, bentonite is commonly used for the HDD process. Nevertheless, the contractor will minimize the amount of bentonite near the exit hole. 5. Reaming and HDPE Conduit Insertion: After the pilot hole has been established, divers will replace the cutter head on the end of the drill rod with a reamer. Upsizing of the bore hole can be achieved by forward or reverse reaming of the pilot hole. The reaming head will enlarge the pilot hole to the necessary diameter, typically 1.5 times the outside diameter of the conduit, ahead of the pull-back of the HDPE conduit into the underground bore. The HDPE pipe lengths can be thermally fused and staged offshore. The leading head of the HDPE conduit is then attached to the pullback assembly, consisting of a reamer and a swivel, and pulled into the borehole by the HDD rig. Cuttings from the reaming/pull-back effort will be pumped from the HDD drill pit back to HDD settling tanks, then passed to a reclaim/cuttings separation tank. Filtered water will be released if it meets water quality requirements, and waste cuttings solids will be properly and legally disposed of as solid waste or landfill material. 6. Cable Insertion and Transition: Upon conclusion of the reaming and conduit pullback, the end of the conduit will remain exposed on the seafloor. If there will be significant time between conduit installation and cable insertion (e.g., as a result of a time-of-year or other seasonal restriction), the conduit may be temporarily protected by filling the receiving pit with concrete mattresses, rock bags, or similar material that can be easily removed when it is time to insert the cable, after which the seabed will to return to its pre-installation conditions. The conduit will likely have a messenger wire passing through it with a cap on each end until the cable is installed. Divers will assist with the messenger line retrieval/operations and perform cable pull-in monitoring while the offshore cable is inserted into the installed conduit and pulled through the conduit to the land connection. The seaward end of the conduit would then be reburied beneath the seafloor, likely using divers will with hand-jets (i.e., a narrow, high-pressure stream of water) or through other control flow methods. Thermal grout may be used to fill the interstitial space between the offshore export cable and the cable conduit to enhance the thermal characteristics of the cable (i.e., to enhance heat dissipation from the cable). Use of a cap/boot will prevent grout from entering the marine environment. 7. Disposal of drill cuttings and drill fluids: The HDD installation method will produce a slurry of two co-mingled byproducts: drill cuttings and excess drill fluids (water and bentonite clay). During drilling, this slurry will be collected from the reservoir pit and will be processed through a filter/recycling system where drill cuttings (solids) will be separated from reusable drill fluids. Non-reusable material consisting of drill cuttings and excess drill fluids will be trucked to an appropriate disposal site. This material is typically classified as clean fill, and it is anticipated that will be the case for this Project. The 5526.10/New England Wind 1 Connector 35 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. material may have an elevated water content, which could require transport to occur in sealed trucks. Typical disposal sites for this type of clean fill include gravel pits or farm fields/pastures. 8. Landward Manholes and Infrastructure: Each offshore cable will be pulled back through the conduit installed via HDD, from which it will enter one of two proposed transition vaults or bays, where it will transition to onshore cabling. 9. Site Restoration: The contractor will restore the location of the entry pit to match existing conditions. Any paved areas that have been disturbed will be properly repaved, per the Proponent’s HCA with the Town of Barnstable. The temporary receiving pit will be filled back in with the same material once the offshore export cable has been brought to land, thereby restoring the ocean bottom to pre-installation conditions. Throughout HDD operations, the Proponent will ensure shore-side site security, and traffic control which will be coordinated with Town officials. As described in Section 3.1.3, the Proponent has assembled a PPPP that proposes the same HDD schedule as will be utilized for the Vineyard Wind Connector (see Attachment G). This schedule, which was formulated in consultation with NHESP to avoid and minimize noise impacts to Piping Plover during the breeding season, will begin HDD activities before April 1 or after August 31. (The HCA with Barnstable is anticipated to further restrict work in the late summer after August 31, limiting it to later in the year.) Representative photographs of the Craigville Public Beach parking lot and adjacent areas are provided in Attachment C. Work will be done in the off-season (i.e., not during the busy summer months). Given the nature of HDD activities, the operation works best if pursued in 12-hour shifts. A summary of the estimated time requirements for drilling 1,000 to 1,200 feet is shown in Table 4-3 below. In summary, the duration of two drill paths of approximately 1,000 to 1,200 feet (300 to 365 m) at the landfall site, including set-up, staging, drilling, and shutdown & demobilization, would be approximately 16 weeks, depending on the drilling conditions and weather encountered. Estimated time requirements could be more, or less, depending upon geotechnical inputs, final engineering design, and associated drilling and construction requirements. 5526.10/New England Wind 1 Connector 36 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Table 4-3 Landfall Site HDD Installation Schedule Time (in weeks) Weeks per Drill Path (assumes 12-hours per shift, 6 shifts per week) 6 Expected Number of Drill Paths 2 Total Weeks, on Site Drilling Activity 12 Mobilization/Demobilization/Staging (weeks) 4 Total Estimated Time at HDD Site (weeks) 16 4.2.1.2 Management of Drilling Fluids and HDD Contingency Plan for Seepage HDD is a well-known and commonly utilized installation technique for this type of project, and with proper construction management the risk of drilling fluid release is very low. As described above, it is important to note that the Project will use a drilling fluid composed of bentonite clay or mud. This benign, naturally occurring material will pose little to no threat to water quality or ecological resources in the rare instance of seepage around the HDD operations. The HDD installation method will produce a slurry of two co-mingled byproducts: drill cuttings and excess drill fluids (bentonite clay or mud). During drilling, this slurry will be collected from the reservoir pit and will be processed through a recycling system where drill cuttings (solids) will be separated from reusable drill fluids. Once the drilling fluid cannot be recycled any further, the non-reusable material consisting of drill cuttings and excess drill fluids will be trucked to an appropriate disposal site. This material is typically classified as clean fill, and it is anticipated that will be the case for this Project. The material may have an elevated water content, which could require transport to occur in sealed trucks. Typical disposal sites for this type of material include gravel pits or land farmed as upland field or pasture. Effective construction management contingency plan procedures during HDD operations will minimize construction-period disturbances for nearby land uses and will also minimize the already-remote potential for drilling fluid seepage (i.e., frac-out). Drilling fluid seepage can be caused by pressurization of the drill hole beyond the containment capacity of the overburden soil material. Providing adequate depth of cover for the HDD installation can substantially reduce this potential impact and as described above, the Project will use a drilling fluid composed of bentonite clay or mud that will pose little to no threat to water quality or ecological resources should seepage occur. Nonetheless, the Proponent will adhere to operational standards to minimize the chances of drilling fluid seepage. The trajectory of the HDD installation has been a primary consideration for contingency planning and prevention of drilling fluid seepage, as well as installation of a temporary surface casing for the first approximately 100 feet of each HDD trajectory as described in Section 4.2.1.1. The HDD drill hole will descend from the HDD pit location to a depth of more than 40 feet below the 5526.10/New England Wind 1 Connector 37 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. seafloor before rising toward the exit hole on the seafloor where installation will transition to cable burial. The geometry of the drill hole profile can also affect the potential for drilling fluid seepage. In a profile that makes compound or tight-radii turns, down-hole pressures can build, thus increasing the potential for drilling fluid seepage. The proposed drilling profile, with its smooth and gradual vertical curves, will avoid this potential effect. In addition, horizontal curvature of the HDD route has been avoided to minimize the potential for pressure buildup caused by drill hole geometry. The drilling crew will be responsible for executing the HDD operation, including actions for detecting and controlling drilling fluid seepage. The process and actions of the drilling crew will be closely supervised. HDD is a technically advanced process, and the Proponent will ensure that the drill crews have the proper training and oversight to minimize the potential for drilling fluid seepage and to respond to seepage promptly and competently should it occur. Each drilling situation is unique, in that the behavior of subsurface material is highly variable and can be difficult to predict. No in-hole monitoring equipment can detect drilling fluid seepage, only pressure and monitoring of actual drilling fluid volume returns, and therefore a combination of factors must be properly interpreted to assess conditions that have the potential to cause seepage. A seep occurs when the path of least resistance for the pressurized drilling fluid to flow into the subsurface materials immediately surrounding the down-hole tooling is less than the path along the borehole. This situation is most common during pilot hole drilling, when the annulus between the borehole and the drill pipe is the smallest. The most obvious sign of a drilling fluid seepage is the loss of drilling fluid circulation at the drilling pit. One of the functions of drilling fluid is to seal the hole to maintain down-hole pressure. The loss of returning drilling fluid is a sign that pressure is not being maintained in the drill hole and seepage is possibly occurring. If there is a reduction in the quantity of drilling fluid returning to the drill site (i.e., loss of circulation), this could be a warning sign. However, some reduction in the volume of returning drilling fluid is also normal during the drilling process, when a loose sand or gravel layer may be encountered that would require additional drilling fluids to fill voids in the substrate. Consequently, drilling fluid loss in and of itself is not an indication of a potential seepage, but rather the loss of drilling fluid in combination with other factors may indicate a potential seepage. For example, if there is a loss of drilling fluid and the return cuttings do not show a large quantity of gravel, this could indicate a loss of containment pressure within the borehole. Detecting a potential seep prior to it occurring is dependent upon the skill and experience of the drilling crew. For this reason, the Project will utilize a specially assigned drill crew. The drilling crew will monitor certain aspects of the drilling operation to detect fluid loss, including but not necessarily limited to the following: i Drilling pit returns, where a sudden loss of drilling fluid would indicate that fluid may be lost to geological materials or a release at the seafloor surface; 5526.10/New England Wind 1 Connector 38 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. i Down-hole pressure, which will be compared to the calculated confining pressure during pilot hole drilling; i Returning drilling fluid volumes and rates, which will be compared to the volumes and rates of drilling fluid pumped down-hole; and i Pump pressures and flow rates. The drill crew will be responsible for immediately notifying the Project Manager if seepage occurs. The Project Manager will immediately assess the situation and estimate the quantity of drilling fluid lost and the square footage of area potentially affected. If drilling fluid seepage is detected, the drilling crew will take immediate corrective action, securing the affected area and immediately implementing the project mitigation plan as appropriate. The primary factor causing seepage would be pressure from the drilling fluid pumps, so the most direct corrective action will be to stop the rig pumps. By stopping the pumps, pressure in the drill hole will quickly dissipate, and with no pressure in the hole seepage will cease. Pumps will be stopped as soon as seepage is suspected or detected. In the event of seepage, the Proponent will notify MassDEP. Corrective actions for conditioning the drill hole should seepage occur differ with specific issues encountered during a particular HDD operation. Common corrective actions include, but are not limited to: i Transitioning the down-hole tooling in a drill hole closer to the entry or exit location to reestablish drilling fluid returns, and “swabbing” out the drill hole; i Modifying drilling pressures and/or pumping rates to account for an unanticipated or changing soil formation; i Pumping drilling fluid admixtures into the drill hole at the location of seepage to solidify or gel the soil; and i Suspending drilling operations for a period of time to allow the drill hole to set up. 4.2.2 Duct Bank Construction and Centerville River Crossing Duct bank construction is described in Section 4.2.2.1, while the Centerville River crossing is described in Section 4.2.2.2. 4.2.2.1 Duct Bank Construction and Cable Installation Installation of the onshore export cables will occur in two stages: the first stage will consist of installing the concrete duct bank and splice vaults that will house the onshore export cables and associated infrastructure; the second stage will consist of pulling/installing the export cables through the duct bank conduits and completing splices and terminations. Construction of the 5526.10/New England Wind 1 Connector 39 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. onshore cable duct bank system will be performed via open trenching with equipment such as excavators and backhoes. All work will be performed in accordance with local, state, and federal safety standards, as well as any Project-specific local requirements. The duct bank will contain six single-core cables consisting of a copper or aluminum conductor covered by solid XLPE insulation and separate fiber optic cables. The cables will not contain any fluids. Each onshore export cable will have its own 8 to 10-inch-diameter PVC or HDPE conduit within the concrete duct bank. This duct bank, shown in typical cross-section in Figure 11, will be an array of PVC or HDPE pipes or sleeves encased in concrete. Up to eight conduits spaced approximately 12 inches apart will be installed within the duct bank to accommodate onshore conductors and spare conduits, with additional smaller conduits for fiber optic communications cables; grounding will be accommodated within the duct bank trench. For the majority of the onshore route, these conduits will be arrayed four conduits wide by two conduits deep, with the total duct bank measuring approximately 5 feet (1.5 m) wide and 2.5 feet (0.8 m) deep. To accommodate this 4x2 duct bank array, the top of the trench will be approximately 9 to 11 feet wide. A more upright design arrayed two conduits wide and four conduits deep is also possible, which would measure approximately 2.5 feet (0.8 m) wide and 5 feet (1.5 m) deep (see Table 4-4). Depending on the configuration of existing subsurface utilities, this duct bank arrangement could be modified along short stretches to enable deeper burial depth to respect utility separation requirements. Table 4-4 Summary of Duct Bank and Trench Dimensions (feet) Duct Bank Trench Conduit Layout Width Depth Depth Width at Bottom Width at Top (0.3 side slope) Width at Top (0.5 side slope) 4x2 (flat) 5 2.5 5.5 5.5 8.8 11 2x4 (upright) 2.5 5 8 3 7.8 11 The target depth of cover in all cases will be at least three feet, although if required in some instances (e.g., at certain utility crossings) the minimum cover will be 2.5 feet. In locations where splicing is necessary, which is likely to occur in only one or two locations within Barnstable Conservation Commission jurisdiction (see duct bank engineering plans in Attachment E), the excavated area will be approximately 20 feet wide by 50 feet long to accommodate a splice vault, which is typically 8 feet wide by 34 feet long and up to 9 feet deep (internal dimensions). Splice vaults will be installed as two-piece preformed concrete chambers and will be located approximately every 1,500 to 2,500 feet along the onshore route. Where the onshore route is particularly straight, the distance between splice vaults may be as great as 3,000 feet (the approximate length of export cable that can be effectively transported by truck and pulled through conduit within the manufacturer’s tension specifications). These splice vaults will 5526.10/New England Wind 1 Connector 40 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. accommodate cable splicing and cross-bonding of cable metallic sheaths. A splice vault will be required for each circuit, resulting in pairs of splice vaults being installed along the onshore route; due to their size, the positions of the two splice vaults will be staggered (see the duct bank engineering plans provided in Attachment E). Onshore construction is expected to proceed at an average rate of approximately 80 to 200 feet per day depending on several factors including existing utility density. Proposed trenching within Conservation Commission jurisdiction will occur within the paved parking lot and the existing roadway layout of Craigville Beach Road, where the work will take place within LSCSF, a narrow strip of Coastal Dune separating the paved parking lot from the paved roadway, and RFA and buffer zone to Salt Marsh associated with the Centerville River. The Proponent will restore the short strip of Coastal Dune to preconstruction conditions. A second area of Conservation Commission jurisdiction occurs along Shootflying Hill Road in the vicinity of Wequaquet Lake where work will be required within the buffer zone of Bordering Vegetated Wetlands, Land Under a Water Body, Inland Bank, and Beach. For the temporary impacts to Coastal Dune just north of the parking lot, the Proponent will restore the area as shown in the Dune Restoration Plan provided in Attachment I. The trench will be backfilled with a combination of Flowable Thermal Backfill (FTB), native material (typically sand and gravel), or road base under roadway areas to original grade. FTB, a thermally approved concrete mix, will be placed above the thermal concrete-encased duct bank if final cable engineering determines it necessary; FTB is an inert mix of stone, sand, and cement that is designed to dissipate heat generated by underground electric transmission cables. Compared with the thermal concrete used to encase the duct bank, FTB is a lower- strength material; as such, FTB is “excavatable,” whereas the thermal concrete around the ducts is more solid. During installation, FTB will flow to fill trench voids and bond with the trench sidewalls. Once hardened, FTB will support loads from vehicular traffic above, and eliminate possibility of future settlement. The final backfill in roadway areas will be town- and/or state- required road sub-base graded material upon which base course and finish course pavements will be placed. In landscaped areas, the final backfill above the FTB will typically be a sandy loam, which can be seeded. During construction, traffic will be managed in accordance with TMPs developed in consultation with Town of Barnstable officials. The typical duct bank construction sequence will include the following steps: 1. Survey and mark splice vault and duct bank locations. 2. Set up erosion and siltation controls, including silt sacks or similar protection for existing storm drains. 5526.10/New England Wind 1 Connector 41 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 3. Set up traffic management measures in coordination with local police and public works officials. 4. Pipe will be delivered on flatbed trucks, stockpiled in a local staging area or along the road if space is available, and advanced ahead of the trench. 5. Trench excavation should advance at a rate of 80 to 200 feet per day. 6. Excavated material will be hauled away in trucks daily and recycled or disposed of in accordance with state regulations. 7. At the landfall site, fusing or joining of continuous PVC or HDPE pipe is planned to be completed in advance of the trench excavation, and will be waiting for assembly into a duct bank array (above ground). 8. Duct pipe is proposed to be assembled into the duct bank array in advance, with required spacers (above ground) then lowered into the trench with slings via heavy equipment. 9. After the duct bank array is secure, concrete trucks will backfill the array in place. 10. Trench areas that are not backfilled by day’s end will be secured with steel plates set in place to cover and protect the trench overnight. Openings in the shoulder will be protected and barricaded to ensure traffic and pedestrian safety. 11. While new trench excavation advances, backfill will be placed above new concrete- encased sections from the prior day’s work. Backfill will be brought to required grade, and the trench will be secured with steel plates again overnight. 12. Subject to local permit conditions, temporary pavement will be placed at completed trench sections as soon as there is enough work to occupy a paving crew for a full day’s work. Final restoration will be performed in accordance with requirements of the HCA. 13. Clean up work area and remove erosion controls. All work will conform to MassDOT and Town specifications for new road construction. Roadways will be restored to “like new” condition or an alternative mutually agreed upon with the Town and consistent with Town policies and procedures. 4.2.2.2 Centerville River Crossing The onshore transmission system will be installed beneath the Centerville River and adjacent areas of Salt Marsh via microtunnel, a trenchless crossing technique that will avoid any direct impacts to these resource areas. The microtunnel operation will require staging and building 5526.10/New England Wind 1 Connector 42 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. demolition/site preparation within the buffer zone of Salt Marsh. Upon completion of the installation, the area of buffer zone disturbed by construction staging will be restored to pre- existing or better conditions. Microtunnel Methodology Microtunnel is a pipe jacking operation that utilizes a microtunnel boring machine (MTBM) pushed into the earth by hydraulic jacks in preparation for insertion of a concrete casing (as opposed to HDD, which drills a curved trajectory through which a conduit is subsequently installed). A concrete casing pipe is lowered into the shaft and inserted between the jacking frame and the MTBM or previously jacked pipe. Slurry lines and power and control cable connections are made, and the pipe and MTBM are advanced along the planned alignment. This process is repeated until the MTBM reaches the reception shaft. Upon completion of the tunnel, the equipment is removed, the carrier pipeline/conduits are pulled through the concrete casing pipe utilizing rollers or an alternative method, and the annular space is grouted. To accomplish the Centerville River crossing, a single approximately 430-foot (130-m) long microtunnel drive would be used to install a 48-inch-diameter reinforced concrete pipe under the river. The reinforced concrete pipe would house eight 8-inch flexible polyvinyl chloride (FPVC) power conduits and three 2-inch HDPE conduits for communication and ground cables, as well as a number of grout lines. The annular space would be grouted using thermal cellular grout to dissipate heat. An approximately 30-foot-diameter (inside diameter) jacking shaft and staging area would be located within the buffer zone to salt marsh on the southwest side of the Centerville River Bridge, on property identified as 2 Short Beach Road, to align with the staging area for microtunnel and to minimize impacts on the traveling public on Craigville Beach Road (see Figure 9 as well as the engineering plans provided in Attachment H). The Proponent has an exclusive option to purchase the 2 Short Beach Road property. A minimum depth of 10 feet (3 m) of cover between the top of the casing and the bottom of the Centerville River is needed to complete the microtunnel drive and maintain tunnel face stability. A receiving shaft to recover the MTBM will be located north of the river, entirely within the Town of Barnstable roadway layout and outside of any wetland resource areas or associated buffer zones. The final location of the receiving shaft will be coordinated with the Town of Barnstable to avoid any conflicts with proposed components of the future sewer projects planned for this area. An auger bore or open cut excavation could be used to transition the cable at depth up to the duct bank depending on geotechnical and hydrogeological conditions, duct bank connection locations, and the available staging area. The use of auger boring is shown on the engineering plans in Attachment H. While using an auger bore is a more technically complex approach, it minimizes dewatering requirements and footprint in the roadway compared with open-cut excavation. If permitted, open-cut excavation is a likely more cost-effective approach for constructing the two transition sections. 5526.10/New England Wind 1 Connector 43 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. All activities would be outside the river and riverbanks themselves, but equipment set-up and staging would temporarily affect approximately 9,400 square feet of the 200-foot Riverfront Area and barrier beach (both previously disturbed); microtunnel would have no permanent impacts to either resource area. The work would also be located within Land Subject to Coastal Storm Flowage and within the regulatory buffer zone to salt marsh and land under the ocean, but again the activity would have no permanent impacts. This trenchless construction method will avoid impacts to other wetland resource areas located adjacent to the Centerville River including Salt Marsh, Land Under the Ocean, Land Containing Shellfish, and Coastal Bank. Microtunnel would have a smaller construction footprint compared to HDD because it avoids the need to have a pipe string laydown area; however, construction could be somewhat longer in duration than HDD. An existing four-inch gas main on the west side of the bridge may conflict with the proposed microtunnel installation operation. In the event that the microtunnel alignment cannot be designed to be installed safely beneath the existing main, it would be relocated prior to the execution of the microtunnel. If this is the case, the Proponent will work with the relevant utility to minimize or eliminate service interruptions to gas customers. Management of Soil Cuttings Microtunneling was selected as the preferred methodology with the intention of preventing accidental release of drilling slurry or soil cuttings to the Centerville River or to the ground surface when not under the river. While there are several types of trenchless technologies that could achieve the river crossing installation, in this instance it is important to select the most applicable trenchless method for maintaining a low depth of cover while crossing under the river. Microtunneling uses technology to limit the amount of soil and groundwater coming into the tunnel to establish a successful installation. In addition, the pressure used to perform the excavation only requires the counterbalance of the active earth pressure and hydrostatic pressure along the microtunnel drive. A safe operating pressure exists and will be used to prevent accidental release of soil cuttings or drilling slurry. Microtunneling counteracts the earth and hydrostatic pressure and creates an equalized pressure at the face of the tunnel, where the cutterhead is located. The cutterhead rotates to excavate the soil while maintaining sufficient face stability by limiting the size of the openings on the microtunnel tunnel boring machine cutterhead. Pressure is monitored real-time by the microtunnel boring machine (MTBM) operator and can be recorded throughout the length of the microtunnel drive. A continuous loop slurry system transports the excavated material such as soil cutting and drilling slurry back to the launch shaft where the slurry is separated from the solid soil particles and reused. A slurry separation plant is used to remove soil from the drilling slurry, and the spoils are then transported offsite and disposed of at an approved landfill. The contractor will be required to test the spoils prior to disposal to confirm the appropriate landfill is used. 5526.10/New England Wind 1 Connector 44 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Drilling slurry engineering parameters will be managed by the contractor. The MTBM will be monitored using a datalogger to record operating pressures and ensure the operating pressures at the bore face are within the acceptable operating range to prevent accidental release of soil cuttings or drilling slurry. The contractor will also be required to develop an appropriate slurry mix/drilling mud based on anticipated ground conditions. Although drilling fluid release is not anticipated and the contractor will be required to develop acceptable operation face pressures and adhere to those during construction, the contractor will also be required to develop a contingency plan to address accidental release of drilling fluid. 4.2.3 Anticipated Impacts to Coastal Resource Areas from Onshore Construction By using HDD to extend approximately 1,000 feet offshore from the Craigville Public Beach parking lot, the Project will avoid impacts to Coastal Beach and minimize impacts to Land Under the Ocean. The HDD staging area within the parking lot will temporarily occupy approximately one acre of LSCSF (see Figures 7, 8, and 10), though Project activities will not permanently alter the elevation or topography of the site. In addition, the duct bank will pass beneath approximately 0.2 miles (1,100 linear feet) of a barrier beach system, where installation will occur almost entirely within the paved surfaces of Craigville Beach Road and the parking lot. Assuming an 11-foot-wide trench for duct bank installation, this activity will temporarily affect approximately 0.3 acres (12,100 square feet). As described in Section 3.1.1, the duct bank route will also cross approximately 0.4 miles (2,000 linear feet) of previously altered LSCSF in the vicinity of the landfall site. Again assuming an 11- foot-wide trench for duct bank installation, this activity will temporarily affect approximately 0.5 acres (22,000 square feet). The Project will have no permanent impacts to this resource since the underground duct bank will not alter existing topography or flood storage capacity. Approximately 0.1 miles (730 linear feet) of RFA will be crossed in the vicinity of the Centerville River, resulting in a temporary impact of approximately 0.2 acres (8,000 square feet). The microtunnel operation will also require staging, building demolition/site preparation, and excavation of an entry pit within the buffer zone of Salt Marsh, but there will be no direct impacts to the salt marsh itself (see Section 5.3.4). In addition, approximately 0.2 miles (1,460 linear feet) of buffer zone associated with Wequaquet Lake and associated Bordering Vegetated Wetlands will be temporarily disturbed within the layout of Shootflying Hill Road. Assuming a trench width of 11 feet, this temporary disturbance will affect approximately 0.4 acres (16,000 square feet). As described above in Section 4.2.2, the proposed duct bank will also be installed beneath a short stretch of a narrow linear Coastal Dune located between the paved Craigville Beach parking lot and Craigville Beach Road (see Figure 7). In this location, a 30-foot-wide construction corridor will be needed to accommodate the approximately 11-foot-wide trench and associated construction equipment. This activity will temporarily impact approximately 585 square feet of the Coastal Dune. Following installation of the duct bank, the Proponent will restore this area of Coastal Dune as shown in the Dune Restoration Plan provided in Attachment I. 5526.10/New England Wind 1 Connector 45 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 5.0 Regulatory Compliance Project work will be located in the following coastal wetland resource areas subject to protection under the Massachusetts WPA and associated regulations (310 CMR 10.00), and the Barnstable Wetlands Protection Bylaw and Regulations 16: i Land Subject to Coastal Storm Flowage (LSCSF); i Riverfront Area (RFA); i Land Under the Ocean; i Coastal Dune/Barrier Beach; i Land Containing Shellfish; and i Salt Marsh. Since HDD will be used for the first approximately 1,000 to 1,200 feet (300-365 meters) of offshore export cable installation from the landfall site, the Project will avoid impacts to the following coastal wetland resource areas: i Coastal Beach; and i Estimated Habitats of Rare Wildlife (Piping Plover nesting habitat). Pursuant to the Massachusetts WPA, the Proponent is submitting this NOI to the Barnstable Conservation Commission for the portion of the Project within the Commission’s jurisdiction (i.e., for impacts to wetland resource areas within Barnstable’s municipal boundaries). It is not anticipated that the Project will have any significant permanent impacts to protected resource areas or their presumed interests. Project construction will have some limited and unavoidable impacts to certain resource areas, but these will be temporary and minimized with appropriate construction methods and mitigation measures. As shown on Figure 5, the entire route of the OECC in Barnstable waters passes through Natural Heritage and Endangered Species Program (NHESP) Priority Habitats for State-Protected Rare Species and Estimated Habitats for Rare Wildlife; these habitats are identified for foraging seabirds. Accordingly, the Proponent will submit a copy of this NOI to the NHESP pursuant to the Massachusetts WPA Regulations (310 CMR 10.37). Potential coastal wetlands impacts related to installation of the offshore export cables, and the mitigation measures intended to avoid or minimize such impacts, are discussed below for each of the above-referenced resource areas. 16 A portion of the duct bank installation along Craigville Beach Road is also within the 100-foot buffer zone of the Coastal Dune located at the northwest corner of the Covell’s Beach parking lot. 5526.10/New England Wind 1 Connector 46 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 5.1 Water-Dependent Projects The Massachusetts Waterways Regulations (310 CMR 9.00) state that facilities ancillary to an offshore wind farm should be characterized as water-dependent, which acknowledges that such projects are unable to be located away from the water. The specific section of those Regulations (310 CMR 9.12(2)(e) is excerpted below: (e) In the case of a facility generating electricity from wind power (wind turbine facility), or any ancillary facility thereto, for which an EIR is submitted, the Department shall presume such facility to be water-dependent if the Secretary has determined that such facility requires direct access to or location in tidal waters and cannot reasonably be located or operated away from tidal or inland waters, based on a comprehensive analysis of alternatives and other information analyzing measures that can be taken to avoid or minimize adverse impacts on the environment, in accordance with M.G.L. c. 30, §§ 61 through 62I. The Project is water-dependent because to accomplish the purpose of establishing electric transmission facilities linking the offshore wind farm and onshore electric grid, the proposed offshore export cables must unavoidably cross waterways. During environmental review of the very similar Vineyard Wind Connector project, the EEA Secretary concluded in the February 1, 2019 FEIR Certificate: “Consistent with 310 CMR 9.12(2)(e), I have determined that the project is water-dependent because the facility requires location in tidal waters and cannot reasonably be located or operated away from tidal waters.” For further clarity, the WPA Regulations provide a definition of “water-dependent uses,” which is excerpted here from 310 CMR 10.04. Water-dependent Uses mean those uses and facilities which require direct access to, or location in, marine, tidal or inland waters and which therefore cannot be located away from said waters, including but not limited to: marinas, public recreational uses, navigational and commercial fishing and boating facilities, water-based recreational uses, navigation aids, basins and channels, industrial uses dependent upon waterborne transportation or requiring large volumes of cooling or processing water which cannot reasonably be located or operated at an upland site, crossings over or under water bodies or waterways (but limited to railroad and public roadway bridges, tunnels, culverts, as well as railroad tracks and public roadways connecting thereto which are generally perpendicular to the water body or waterway), and any other uses and facilities as may further hereafter be defined as water-dependent in 310 CMR 9.00” (emphasis added). A finding of water dependency is relevant for certain aspects of this filing. 5.2 Limited Project Status Under the Massachusetts WPA, certain activities are afforded Limited Project status (310 CMR 10.04), which allows permitting authorities to allow projects that are inherently unable to meet wetland performance standards. The Proponent believes the Project does meet the wetland 5526.10/New England Wind 1 Connector 47 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. performance standards, but nonetheless requests a determination that the Project is afforded Limited Project Status. Specific activities that qualify for Limited Project status are listed in the Massachusetts WPA Regulations at 310 CMR 10.04 and 310 CMR 10.53. Water-dependent projects such as the NE Wind 1 Connector are one such category of Limited Projects in this section of the Regulations: 310 CMR 10.53(3) Limited Projects. (l) The construction, reconstruction, operation or maintenance of water dependent uses; provided, however that: 1. any portion of such work which alters a bordering vegetated wetland shall remain subject to the provisions of 310 CMR 10.55, 2. such work in any other resource area(s) found to be significant to flood control or prevention of storm damage shall meet the performance standards for that interest(s), and 3. adverse impacts from such work in any other resource area(s) shall be minimized regarding the other statutory interests for which that resource area(s) is found to be significant. Accordingly, the Project should be regarded as a “Limited Project” under the Massachusetts WPA Regulations. Regardless, the Proponent believes the Project does meet the wetland performance standards. 5.3 Wetland Resource Areas and Performance Standards Portions of the proposed work in Barnstable that will be located within LSCSF, RFA, Salt Marsh, Coastal Dune/Barrier Beach, Land Containing Shellfish, or Land Under the Ocean fall under the jurisdiction of the Barnstable Conservation Commission under the Massachusetts WPA and associated regulations (310 CMR 10.00) as well as the Barnstable Wetland Protection Bylaw, Ch. 237 and related Wetland Protection Regulations. The entire OECC in Barnstable waters will also pass through NHESP-mapped Priority Habitat for State-Protected Rare Species and Estimated Habitat for Rare Wildlife (see Figure 5). Accordingly, the Proponent will submit a copy of this NOI to the NHESP pursuant to the Massachusetts WPA Regulations (310 CMR 10.37). Cable installation will have some unavoidable and temporary impacts to these resource areas, but these impacts will be minimized with appropriate construction methods and mitigation measures and meet the applicable state performance standards, as well as the criteria in the Barnstable Wetlands Protection Bylaw and related Regulations. Specific Project-related impacts to Land Under the Ocean related to installation of the offshore export cables are quantified in Table 4-1. In addition, as described in Section 4.2, the Project’s onshore activities within the Commission’s jurisdictional area will include: (1) approximately 0.5 acres (22,000 square feet) of temporary alteration to LSCSF due to duct bank installation within Craigville Beach Road and the Craigville Public Beach parking lot; (2) approximately 0.3 acres (12,100 square feet) of temporary alteration of a barrier beach system due to duct bank installation within Craigville Beach Road and the Craigville Public parking lot; (3) approximately 0.2 acres (8,000 square feet) of temporary alteration of RFA in the vicinity of the Centerville River; (4) approximately 200 square feet of 5526.10/New England Wind 1 Connector 48 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. temporary alteration to Coastal Dune due to duct bank installation in the narrow area between the parking lot and Craigville Beach Road; and (5) approximately 1 acre of temporary occupation of LSCSF within the paved Craigville Public Beach parking lot for HDD staging. In addition, any proposed work within the buffer zones of inland resource areas that are located along Shootflying Hill road in the vicinity of Wequaquet Lake is also subject to the jurisdiction of the Barnstable Conservation Commission. The relevant performance standards for RFA, Land Under the Ocean, Coastal Dune/Barrier Beach, Land Containing Shellfish, and Salt Marsh are discussed below. There are no performance standards established for LSCSF, although it is worth noting that Project activities will not result in any permanent alteration of elevation or topography, will not increase impermeable surface, and will not affect storm damage prevention or flood control. 5.3.1 Riverfront Area The Massachusetts WPA Regulations define RFA as the area of land located within a specified distance, usually 200 feet, of the banks of perennial rivers and streams. RFA may include overlap with other resource areas and their buffer zones, but the RFA itself has no buffer zone. For the Centerville River crossing, the RFA within the layout of Craigville Beach Road extends roughly from 200 feet south of the south bridge abutment to 200 feet north of the north bridge abutment. Some projects have been granted exemptions from the performance standards that would otherwise apply to certain activities located in RFA. Included in the list of exempted activities are those that are necessary to construct a project that is required to obtain a Chapter 91 license (see 310 CMR 10.58(6)(i)). The Project will require a Chapter 91 license for the proposed crossing of the Centerville River, and is therefore not subject to the performance standards applicable to RFA. Regardless the Project will satisfy the performance standards for the other resource areas present at the Centerville River crossing, including Land under the Ocean and Salt Marsh. 5.3.2 Land Under the Ocean The Massachusetts WPA Regulations require that projects located within Land Under the Ocean satisfy certain general performance standards when the resource is found to be significant to the protection of marine fisheries, protection of wildlife habitat, storm damage prevention, or flood control (310 CMR 10.25 (3) through (7)). Of relevance to this Project, 310 CMR 10.25(5) states: (5) Projects not included in 310 CMR 10.25(3) or (4) [relating to dredging projects for navigational purposes] which affect nearshore areas of land under the ocean shall not cause adverse effects by altering the bottom topography so as to increase storm damage or erosion of coastal beaches, coastal banks, coastal dunes, or salt marshes. Use of HDD will avoid offshore cable installation activities within approximately 1,000 to 1,200 feet of the shoreline, thus avoiding nearshore impacts. Installation of the offshore export cables will require the temporary disturbance of two narrow strips of seafloor to achieve sufficient burial depth (see Section 4.1 for a more detailed discussion of offshore export cable installation). Cable 5526.10/New England Wind 1 Connector 49 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. burial will temporarily displace some sediments that do not immediately re-settle back into the fluidized trench, but these displaced sediments will return to the seafloor in the wake of the cable installation tool generally within a few meters of the furrow created by cable installation. Particle sediment monitoring studies completed for the Block Island Wind Farm’s offshore cable installation found that displaced sediments were an average distance from the trench centerline of 12.5 feet (3.8 meters) at a thickness 2.8 inches (7 cm).17 Such a minor alteration to the bottom topography would not alter water circulation or sediment transport patterns, and would not increase erosion of coastal beaches, coastal banks, coastal dunes, or salt marshes. Discontinuous sand wave dredging may be required in areas where currents have created large, mobile sand waves. These sand waves are located along the southernmost stretch of the OECC in Barnstable waters, in an area just east of Wreck Shoal and almost 3 miles from the nearest coastal beach, coastal bank, coastal dune, or salt marsh. Where the offshore cable installation must cross a sand wave, it will be necessary to provide additional burial depth to achieve sufficient coverage beneath the stable seabed surface and prevent the cable from being exposed as the sand wave advances across the seafloor. Where large sand waves are encountered, it may be necessary to carve a notch into the sand waves of sufficient width and depth so the cable installation tool can proceed through it, installing the cables beneath the stable seabed. The Project’s dredging methods and related impacts are discussed and quantified in Section 4.1. Any dredging required for offshore cable installation through sand waves will occur within narrow corridors in areas relatively far from shore (greater than 1 mile); therefore, regardless of the dredge method selected through sand waves, installation of the offshore export cables is not expected to increase the risk of erosion in coastal areas. The impacts will be modest and in compliance with performance standards. Also potentially relevant to this Project, 310 CMR 10.25(6) states: (6) Projects not included in 310 CMR 10.25(3) which affect land under the ocean shall if water-dependent be designed and constructed, using best available measures, so as to minimize adverse effects, and if non-water-dependent, have no adverse effects, on marine fisheries habitat or wildlife habitat caused by: (a) alterations in water circulation; (b) destruction of eelgrass (Zostera marina) or widgeon grass (Rupia maritina) beds; (c) alterations in the distribution of sediment grain size; 17 James Elliott, K. Smith, D.R. Gallien, and A. Khan. 2017. Observing Cable Laying and Particle Settlement During the Construction of the Block Island Wind Farm. Final Report to the U.S. Department of the Interior, Bureau of Ocean Energy Management, Office of Renewable Energy Programs. OCS Study BOEM 2017-027. 225 pp. 5526.10/New England Wind 1 Connector 50 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. (d) changes in water quality, including, but not limited to, other than natural fluctuations in the level of dissolved oxygen, temperature or turbidity, or the addition of pollutants; or (e) alterations of shallow submerged lands with high densities of polychaetes, mollusks or macrophytic algae. The Project is water-dependent as defined in the Massachusetts Waterways Regulations at 310 CMR 9.12(2)(b)10, which includes infrastructure facilities used to deliver electricity to the public from an offshore facility located outside the Commonwealth. As a water-dependent use, the Project must be designed and constructed using best available measures to minimize adverse effects. The Project’s water-dependency is discussed in Section 5.1. As described in Section 4.0 of this NOI as well as in the MEPA documents incorporated by reference, the proposed cable installation methods are well documented as environmentally conscious operations with minimal temporary impacts to the seafloor and water quality. Installation of the export cables will require some displacement of marine sediments to achieve desired cable burial, but in most areas the method of installation will result in minimal alteration to seafloor topography. More alteration will be required in high-energy areas where large sand waves are encountered, but these high-energy areas are characterized by constantly changing bathymetry, and any alteration due to the Project is expected to be temporary. None of the affected areas will be altered to the extent that any significant changes occur to water circulation or sediment grain size distribution. The OECC has been sited to avoid areas of eelgrass or widgeon grass, and the installation methodologies will minimize impacts to benthic organisms. In addition, under 310 CMR 10.25(7), projects with certain adverse effects are presumed impermissible: (7) Notwithstanding the provisions of 310 CMR 10.25(3) through (6), no project may be permitted which will have any adverse effect on specified habitat sites of rare vertebrate or invertebrate species, as identified by procedures established under 310 CMR 10.37. The NHESP has mapped all of Nantucket Sound as priority habitat of state-listed rare species (Massachusetts Natural Heritage Atlas, 15th Edition, 2021). As a result, the OECC will necessarily cross priority habitat within Barnstable waters (see Figure 5). The Proponent has been consulting with NHESP in accordance with the Massachusetts Endangered Species Act (MESA, 321 CMR 10.14) to ensure that impacts to offshore rare species are avoided or minimized to greatest extent practicable. The Proponent has completed a MESA checklist pursuant to 321 CMR 10.18 with regard to priority habitat within state waters, and the checklist was submitted to NHESP for review in March 2022. The Piping Plover Protection Plan was attached to the Checklist (see also 5526.10/New England Wind 1 Connector 51 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Attachment G). On April 1, 2022, the NHESP issued a MESA Determination that with compliance with the Piping Plover Protection Plan, the Project will avoid a Take (see Attachment L). Pursuant to 310 CMR 10.37, the Proponent will submit a copy of this NOI to the NHESP. 5.3.2 Coastal Dune/Barrier Beach The performance standards for Coastal Dune and Barrier Beach state that any alteration of a coastal dune or within 100 feet of a coastal dune must not have an adverse effect on the dune. In other words, to satisfy the performance standard the Project must not result in a greater than negligible change in the dune that diminishes its ability to perform specified functions (i.e. provide storm damage prevention, flood control, or protection of wildlife habitat). These performance standards for projects affecting coastal dunes and adjacent lands are found at 310 CMR 10.28(3) through (6) and are excerpted below: (3) Any alteration of, or structure on, a coastal dune or within 100 feet of a coastal dune shall not have an adverse effect on the coastal dune by: (a) affecting the ability of waves to remove sand from the dune; (b) disturbing the vegetative cover so as to destabilize the dune; (c) causing any modification of the dune form that would increase the potential for storm or flood damage; (d) interfering with the landward or lateral movement of the dune; (e) causing removal of sand from the dune artificially; or (f) interfering with mapped or otherwise identified bird nesting habitat. HDD activities will be staged from the paved Craigville Public Beach parking lot, some of which is located within 100 feet of a Coastal Dune. However, HDD activities will in no way impair dune functions. Approximately 585 square feet of the Coastal Dune will be disturbed during installation of the proposed duct bank between the paved parking lot and Craigville Beach Road. Although construction will temporarily alter the grade of the dune, the impact will be temporary and the dune will be restored according to the dune restoration plan provided as Attachment I. It should be noted that while the Coastal Dune that will be disturbed is not functioning as a coastal dune in that it is physically disconnected from the beach and sits in between a paved parking lot and a paved town road, the Proponent will provide restoration measures that treat the area as if it were a functioning coastal dune. (4) Notwithstanding the provisions of 310 CMR 10.28(3), when a building already exists upon a coastal dune, a project accessory to the existing building may be permitted, provided that such work, using the best commercially available measures, minimizes the 5526.10/New England Wind 1 Connector 52 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. adverse effect on the coastal dune caused by the impacts listed in 310 CMR 10.28(3)(b) through (e). Such an accessory project may include, but is not limited to, a small shed or a small parking area for residences. It shall not include coastal engineering structures. There is no existing structure on the dune, and the Project does not propose any accessory projects. (5) The following projects may be permitted, provided that they adhere to the provisions of 310 CMR 10.28(3): (a) pedestrian walkways, designed to minimize the disturbance to the vegetative cover and traditional bird nesting habitat; (b) fencing and other devices designed to increase dune development; and (c) plantings compatible with the natural vegetative cover. The area of Coastal Dune that will be temporarily disturbed by duct bank installation will be restored with compatible sand and planted with American beach grass and other native plants appropriate for landscape to promote dune development. (6) Notwithstanding the provisions of 310 CMR 10.28(3) through (5), no project may be permitted which will have any adverse effect on specified habitat sites of Rare Species, as identified by procedures established under 310 CMR 10.37. The Project is located within specified Priority Habitat of rare wetlands wildlife. The Proponent has consulted with the NHESP and will continue to comply with all time-of-year restrictions and other conditions deemed necessary by the NHESP for the installation and maintenance of the Project. 5.3.3 Land Containing Shellfish Offshore export cable installation may result in some localized impact to shellfish and other organisms in the direct path of the installation tool, and within the water column from water withdrawals. Soon after disturbance, recolonization and recovery to pre-construction species assemblages is expected given the similarity of nearby habitats and species, the limited area of disturbance, and the mobility of the organisms in some or all life stages. Nearby, unaffected areas will likely act as refuge areas and supply a brood stock of species, which will begin recolonizing 5526.10/New England Wind 1 Connector 53 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. disturbed areas post-construction. A post-construction marine survey conducted in 2015 within six weeks of installation of a submarine cable from Falmouth to Tisbury on Martha’s Vineyard found that benthic disturbances only occurred along some parts of the cable route.18 As described in Section 4.1.2.2, anchoring may be required along the entire OECC to enable the use of installation tools capable of achieving the target burial depth. Anchors would disturb the substrate and leave a temporary irregularity in the seafloor resulting in some localized mortality of infauna. In addition, portions of the seafloor would be swept by an anchor cable as the installation equipment moves along the cable. The Proponent will implement a monitoring plan to document disturbance and recovery of marine habitat along the cable installation corridor. A monitoring program focusing on benthic habitat and communities will be performed to measure potential impacts and the recovery of these resources comparable to controls outside the area of construction. The Massachusetts WPA Regulations require that projects located in resource areas that are determined to be significant to the protection of land containing shellfish and therefore marine fisheries shall satisfy certain general performance standards (310 CMR 10.34 (4) through (6) and (8)). These performance standards are excerpted below: (4) Except as provided in 310 CMR 10.34(5), any project on land containing shellfish shall not adversely affect such land or marine fisheries by a change in the productivity of such land caused by: (a) alterations of water circulation; (b) alterations in relief elevation; (c) the compacting of sediment by vehicular traffic; (d) alterations in the distribution of sediment grain size; (e) alterations in natural drainage from adjacent land; or (f) changes in water quality, including, but not limited to, other than natural fluctuations in the levels of salinity, dissolved oxygen, nutrients, temperature or turbidity, or the addition of pollutants. The Project is not anticipated to result in any permanent alterations to water circulation, relief elevation, or distribution of sediment grain size. There will be no change to natural drainage from adjacent land, and no compacting of sediments from vehicular traffic or installation gear. Offshore export cable installation will result in some temporary impacts to shellfish in the area 18 Epsilon Associates, Inc. and CR Environmental, Inc. 2015. Martha’s Vineyard Hybrid Submarine Cable Post- Construction Marine Survey Report. Prepared for Comcast and NSTAR Electric Company. 5526.10/New England Wind 1 Connector 54 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. immediately along the installation path, but these impacts are regarded as negligible given that the area of potential affect is incrementally small in comparison to the wide area of habitat present in the Project vicinity. (5) Notwithstanding the provisions of 310 CMR 10.34(4), projects which temporarily have an adverse effect on shellfish productivity but which do not permanently destroy the habitat may be permitted if the land containing shellfish can and will be returned substantially to its former productivity in less than one year from the commencement of work, unless an extension of the Order of Conditions is granted, in which case such restoration shall be completed within one year of such extension. The Proponent has assembled a benthic habitat monitoring framework and remains in active consultations with state and federal agencies (including the Massachusetts Office of Coastal Zone Management [CZM], Division of Marine Fisheries [DMF], Massachusetts Department of Environmental Protection [MassDEP], Bureau of Ocean Energy Management [BOEM], and the National Marine Fisheries Service [NMFS]) to develop a Benthic Habitat Monitoring Plan (BHMP) out of that framework. The BHMP will document habitat and benthic community disturbance and recovery as a result of construction and installation. The Proponent expects the BHMP will be memorialized in the Water Quality Certification (WQC) that will be issued by MassDEP. (6) In the case of land containing shellfish defined as significant in 310 CMR 10.34(3)(b) (i.e., those areas identified on the basis of maps and designations of the Shellfish Constable), except in Areas of Critical Environmental Concern, the issuing authority may, after consultation with the Shellfish Constable, permit the shellfish to be moved from such area under the guidelines of, and to a suitable location approved by, the Division of Marine Fisheries, in order to permit a proposed project on such land. Any such project shall not be commenced until after the moving and replanting of the shellfish have been commenced. The Proponent will work with the DMF and the shellfish constable for the Town of Barnstable to minimize impacts to shellfish habitat but is not proposing to relocate shellfish prior to cable installation. (8) Notwithstanding the provisions of 310 CMR 10.34(4) through (7), no project may be permitted which will have any adverse effect on specified habitat of rare vertebrate or invertebrate species, as identified by procedures established under 310 CMR 10.37. The Massachusetts NHESP has mapped all state waters within Nantucket Sound and Muskeget Channel as priority habitat of state-listed rare species (Massachusetts Natural Heritage Atlas, 15th Edition, 2021). As a result, the OECC will necessarily cross priority habitat within Barnstable waters. The Proponent is consulting with the NHESP in accordance with the MESA (321 CMR 10.14) to ensure that impacts to offshore rare species are avoided or minimized to greatest extent practicable. The Proponent has completed a MESA checklist pursuant to 321 CMR 10.18 with regard to priority habitat within state waters, and the checklist was submitted to NHESP for review 5526.10/New England Wind 1 Connector 55 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. in March 2022. On April 1, 2022, the NHESP issued a MESA Determination that with compliance with the Piping Plover Protection Plan, the Project will avoid a Take (see Attachment L). Pursuant to 310 CMR 10.37, the Proponent will submit a copy of this NOI to the NHESP. 5.3.4 Salt Marsh The onshore transmission system will be installed beneath the Centerville River and adjacent areas of Salt Marsh via microtunnel, a trenchless crossing technique that will avoid any direct impacts to these resource areas. The microtunnel operation will require staging, building demolition/site preparation, and excavation of an entry pit within the buffer zone of Salt Marsh. For the entry pit, a caisson or similar water-tight shaft construction methodology will minimize the required dewatering during shaft construction and microtunnel operation. Upon completion of the installation, the area of buffer zone disturbed by construction staging will be restored to pre-existing or better conditions. Construction methods for microtunneling are described in detail in Section 4.2.2.2, including drill slurry management methods. Performance standards for Salt Marsh are found in the Massachusetts Wetlands Protection Act Regulations at 310 CMR 10.32 (3) through (6), which is excerpted below. (3) A proposed project in a salt marsh, on lands within 100 feet of a salt marsh, or in a body of water adjacent to a salt marsh shall not destroy any portion of the salt marsh and shall not have an adverse effect on the productivity of the salt marsh. Alterations in growth, distribution and composition of salt marsh vegetation shall be considered in evaluating adverse effects on productivity. 310 CMR 10.32(3) shall not be construed to prohibit the harvesting of salt hay. The Project will have no direct impacts to salt marsh. Temporary staging will minimize ground disturbance and erosion and sediment controls will also allow for any separation of dewatering from the salt marsh. (4) Notwithstanding the provisions of 310 CMR 10.32(3), a small project within a salt marsh, such as an elevated walkway or other structure which has no adverse effects other than blocking sunlight from the underlying vegetation for a portion of each day, may be permitted if such a project complies with all other applicable requirements of 310 CMR 10.21 through 10.37. This standard is not applicable, as the Project does not to propose introducing any elevated walkway or other structure that might block sunlight from underlying vegetation. (5) Notwithstanding the provisions of 310 CMR 10.32(3), a project which will restore or rehabilitate a salt marsh, or create a salt marsh, may be permitted in accordance with 310 CMR 10.11 through 10.14, 10.24(8), and/or 10.53(4). This standard is not applicable, as the Project does not propose restoration, rehabilitation, or creation of a salt marsh. 5526.10/New England Wind 1 Connector 56 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. (6) Notwithstanding the provisions of 310 CMR 10.32(3) through (5), no project may be permitted which will have any adverse effect on specified habitat sites of Rare Species, as identified by procedures established under 310 CMR 10.37. This standard is not applicable, as the Centerville River crossing is not located within any specified habitat of Rare Species. 5.4 Interests Protected under Barnstable Wetlands Protection Bylaw The Project and associated activities contribute to the protection of wetland functions and values identified in the WPA and The Town of Barnstable Wetlands By-Law, Chapter 237. The bylaw specifically addresses fourteen values, as discussed below. 1. Protection of public and private water supply: Construction activities proposed in or within 100 feet of wetland resource areas will not affect public or private water supplies. The cables and duct bank will not contain any fluids or hazardous materials. A Stormwater Pollution Prevention Plan will be prepared in accordance with the U.S. EPA’s general permit for construction activities and will be implemented during construction to properly manage construction activities. The Proponent’s objective is to minimize the potential for erosion and sedimentation impact during Project construction by managing stormwater and effectively restoring any disturbed areas. The Proponent will meet these objectives by implementing various erosion and sediment control measures that will: o Minimize the quantity and duration of soil exposure; o Protect areas of critical concern during construction by redirecting and reducing the velocity of runoff; and o Establish vegetation where required as soon as possible following final grading. Temporary erosion control barriers will be installed prior to initial disturbance of soil and will be inspected on a daily basis in areas of active construction or equipment operation and on a weekly basis in areas with no construction or equipment operation. These temporary erosion control barriers will be maintained as necessary to contain soil and sediment within the permitted work limits. Any silt fence used as a construction-period control will be installed as directed by the manufacturer and applicable permit conditions. Accumulated sediment will be removed and the fence inspected to ensure it remains embedded in the soil as directed. Sufficient silt fence will be stockpiled onsite for emergency use and maintenance. Hay/straw bales used for stormwater management will be anchored in place with at least two wooden stakes and will be replaced or damaged or allowing water to flow underneath; properly placed and staked straw wattles or fiber rolls may be used in lieu of hay bales in certain circumstances. 5526.10/New England Wind 1 Connector 57 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. Nearly all vehicle fueling and all major equipment maintenance will be performed off-site at commercial service stations or a contractor’s yard. A few pieces of large, less mobile equipment (e.g., excavators, paving equipment) will be refueled as necessary on-site. Any such field refueling will not be performed within 100 feet of wetlands waterways, or within 100 feet of known private or community potable wells, or within any Town water supply Zone I area. 2. Protection of groundwater supply: The Project will protect groundwater supply through the implementation of a Stormwater Pollution Prevention Plan during construction to properly manage construction activities. 3. Flood control: The Project will not permanently change existing grades, and therefore will not affect existing flood storage capacity (see Section 5.3). 4. Storm damage prevention: The Project will not affect resources that protect properties from storm damage. Following the temporary disturbance of a narrow strip of Coastal Dune located between the paved Craigville Public Beach parking lot and Craigville Beach Road, the Proponent will restore this area of Coastal Dune as shown in the Dune Restoration Plan provided as Attachment I. 5. Prevention of pollution: The Project will prevent pollution through the implementation of a Stormwater Pollution Prevention Plan during construction to properly manage construction activities, and by otherwise using appropriate construction techniques discussed in Section 4.2. There will be no fluids in the cable or vaults. 6. Protection of land containing shellfish: As discussed in Section 3.1.2 and shown on Figure 4, the Project’s OECC and preliminary cable alignments almost entirely avoid shellfish suitability areas in Barnstable waters. The transition from offshore cable burial to the HDD will occur close to the boundary for mapped suitable habitat for Surf Clam (Spisula solidissima) located in the nearshore area of Centerville Harbor. The use of HDD will avoid almost all impacts to the mapped suitable habitat; it is estimated that typical cable installation may occur through less than approximately 200 linear feet of that habitat. 7. Protection of shellfish and fisheries: As discussed in Section 4.1.2, direct trenching impacts for the two offshore export cables will be limited to two narrow, approximately 3.3-foot (1-meter) wide, strips of seabed. Given the narrow width of disturbance, and since immediately adjacent habitats will remain unaffected, it is anticipated that the affected area will recover quickly, as observed for other cable projects in Nantucket Sound (e.g., the Martha’s Vineyard Hybrid Cable Project between Falmouth and Tisbury in 2015). The Proponent will continue to consult with the relevant federal and state agencies to refine the Project construction schedule to avoid and minimize impacts to marine species. 5526.10/New England Wind 1 Connector 58 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 8. Protection of wildlife habitat: As discussed in Section 3.1.3, the Project will avoid disturbance of the priority habitat associated with Craigville Public Beach by installing the cable using HDD and by initiating the HDD activities prior to April 1 or after August 31 (later per HCA). Furthermore, since the onshore route utilizes existing corridors (e.g., roadway layouts and existing utility ROWs), it will not adversely affect wildlife habitat. 9. Erosion and sedimentation control: The Project will control erosion through the implementation of a Stormwater Pollution Prevention Plan. 10. Recreation: The Project will have a minimal impact on recreational activities, and all construction activities at the landfall site and in public roadways will be completed outside of the busy summer season. In addition, the Proponent will maintain public access to parking lot at the landfall site during the construction period. Finally, the Proponent will repave the parking lot upon completion of construction. 11. Aesthetics: Within the jurisdiction of the Barnstable Conservation Commission, the Project will have no visual impacts outside of the construction period since the offshore export cables and the onshore duct bank will be entirely underground. 12. Effects on agriculture: The Project will not affect any areas of existing agriculture. 13. Effects on aquaculture: The Project will not affect any areas of existing aquaculture. 14. Effects on historic interests: No direct impacts to terrestrial historic resources are anticipated. Avoidance, minimization, and mitigation measures for submarine historical and archaeological resources within the Project area will be determined in consultation with the Massachusetts Historical Commission (MHC) and Massachusetts Board of Underwater Archaeological Resources (MBUAR) through the NEPA process. 6.0 Mitigation Measures The Project will result in unavoidable temporary impacts to offshore wetland resource areas (Land Under the Ocean) as discussed and quantified in Sections 3 and 4. These impacts have been avoided and minimized through thoughtful selection of route and installation methods, and mitigation for impacts will be provided as appropriate. Perhaps most importantly, the alignment of the OECC is the product of an extensive consideration of alternatives and is itself intended to avoid and minimize potential impacts to sensitive resources, including SSU areas (i.e., eelgrass, hard bottom, complex bottom, and core habitat of the North Atlantic Right Whale). Wherever possible, the Project will avoid sensitive habitats, and where impacts cannot be avoided, the Project will attempt to minimize their extent through cable installation methodology and scheduling. The Proponent, through consultations with state and federal agencies, has considered the timing of export cable installation and potential TOY restrictions, there are two critical schedule considerations for the Project: 5526.10/New England Wind 1 Connector 59 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. 1. Safe operating conditions for cable-laying vessels. Cable-laying vessels can only safely operate in certain wave conditions. To ensure the welfare of the vessel and its crew, the Proponent can only conduct cable-laying if there is a greater than 50% probability of obtaining the required weather conditions during the installation activity. An extensive analysis of historic weather conditions indicates it is statistically likely to obtain safe weather conditions for cable-laying during the period of approximately April to September. Scheduling work within safe weather conditions is critical for the Project because, if weather conditions exceed the limiting operational conditions for the cable and safe working limits for the vessel, then the crew may have to undertake a controlled abandonment of the cable, whereby the cable will be cut and placed on the seabed so the vessel can seek refuge. In this instance, the cable would then have to be spliced. Such a repair joint would take approximately six days to complete, which would then seriously compromise the progress of the operation since it would require a favourable weather window both for the repair joint and the remaining cable-laying activity. 2. Sequencing the Project to begin to deliver power by 2026. Offshore export cable installation is currently anticipated in 2025-2026, so that the process of WTG commissioning (which is partially dependent on having power from the offshore export cable(s) can start and some power can be delivered 2026. Therefore, the definition of TOY restrictions for export cable installation arises from consideration of the safe operational conditions for cable-laying vessels and the need to provide power on schedule in addition to environmental considerations. Extensive discussions with federal and state agencies, including but not limited to NMFS and DMF, regarding TOY restrictions occurred for Vineyard Wind/Vineyard Wind Connector. The outcome of those discussions resulted in a set of TOY restrictions that are also reasonable to apply to Park City Wind/NE Wind 1 Connector given the similarities between the projects. Final determination of TOY restrictions for the NE Wind 1 Connector is not complete and the Proponent will continue to consult with regulatory agencies regarding relevant TOY restrictions for all aspects of Project construction. At this time, the Proponent is proposing the following TOY restrictions based on Vineyard Wind Connector and ongoing consultations with permitting and resource agencies: i HDD activities at the landfall site will begin in advance of April 1, or will not begin until August 31, to avoid and minimize noise impacts to Piping Plover during the breeding season per the Massachusetts Endangered Species Act (MESA) Determination issued by NHESP on April 1, 2022 (see Attachment G for the Piping Plover Protection Plan [PPPP]). i Activities at the landfall site where offshore cables will transition from offshore to onshore cables will not be performed from May 15 through September 15 unless authorized by the Town of Barnstable or otherwise defined in the HCA. 5526.10/New England Wind 1 Connector 60 Attachment A – Project Narrative Notice of Intent – Barnstable, MA Epsilon Associates, Inc. i Cable installation of the sections of cable that pass through the portion of Nantucket Sound with an active squid fishery (specifically, from the landfall site to a distance of approximately 24-27 km offshore) will occur between July and March, but will avoid April through June. This installation schedule will avoid cable installation during the spring months in Nantucket Sound and avoid and minimize impacts to the squid fishery. i Finally, to comply with federal protections for the Northern long-eared bat, the Proponent does not plan to perform tree removal activities from June 1 through July 31. As with Vineyard Wind Connector, the Proponent expects these TOY restrictions will be memorialized during permitting. The Proponent expects that the final TOY restrictions in state waters will be incorporated into the Project’s 401 Water Quality Certification (WQC). In addition, the Proponent has selected installation techniques that will minimize the amount of seafloor disturbance during installation of the offshore export cables (see Section 4.1). Based on post-installation monitoring of a similar submarine cable project in Nantucket Sound, cable burial is expected to have no long-term impact on the benthic habitat, and the affected area of the seafloor is expected to be fully restored within a relatively short time. As an example, a post- construction marine survey conducted in 2015 within six weeks of installation of the Martha’s Vineyard Hybrid Cable Project from Falmouth to Tisbury on Martha’s Vineyard found that benthic disturbances visible only along portions of the cable route. Mitigation for unavoidable impacts to marine resources will be provided in accordance with provisions established under the Massachusetts OMP and its implementing regulations (301 CMR 28.00). Those regulations specify that projects subject to the OMP are required to pay an Ocean Development Mitigation Fee intended to compensate the Commonwealth for unavoidable impacts on public interests and rights in the Planning Area and to support planning, management, restoration, or enhancement of marine resources and uses. A fee proposal was included in the Proponent’s FEIR, and the Secretary’s Certificate on the FEIR contained the final fee determination. For onshore construction, the Project avoids and minimizes potential impacts to wetlands by following existing roadway layouts. This means the temporary impacts to LSCSF, RFA, and Barrier Beach will be entirely within paved areas or previously disturbed areas (i.e., roadway shoulder or, in the case of RFA, a previously developed residential parcel). Furthermore, the use of microtunnel to achieve the Centerville River crossing will avoid any direct impacts to the river itself or to salt marsh.