HomeMy WebLinkAboutSubmitted by Felicia Penn Geotechnical Report 1
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
2.4 Subsurface Conditions
The subsurface description in this report is based on a limited number of test pits and one (1)
boring and is intended to highlight the major soil strata encountered during our test pits and
boring. The subsurface conditions are known only at the actual test pit and boring locations.
Variations may occur and should be expected between test pit and boring locations. The test pit
and boring logs represent conditions that we observed at the time of our test pits and boring, and
were edited, as appropriate, based on the results of the laboratory test data and inspection of the
soil samples in the laboratory. The strata boundaries shown in our test pit and boring logs are
based on our interpretations and the actual transitions may be gradual. Graphic soil symbols are
for illustration only.
The soil strata encountered in the test pits and boring were as follows, starting at the ground
surface.
Topsoil – A layer of topsoil was encountered at the ground surface in all explorations and
extended to depths ranging between 0.5 and 1.7 feet beneath the ground surface.
Subsoil – A layer of subsoil was encountered in boring B-4 and in test pit TP-1, and extended to
depths of 3 and 4.5 feet beneath the ground surface, respectively. The samples in the subsoil
were described as silty sand or poorly graded sand. The fines content ranged in the subsoil up to
30 percent. The subsoil contained between 10 and 25 percent fine to coarse gravel. The subsoil
contained traces of organic soil and roots.
Fill – Fill was encountered beneath the topsoil or subsoil in all explorations except in test pit TP-
1 and boring B-4, and extended to depths ranging 3.5 and 4.5 feet beneath the ground surface.
The samples in the fill were mostly described as poorly graded sand or well graded sand. In one
(1) test pit, the fill was described as silty sand. The fines content ranged in the fill up to15
percent and the gravel content ranged between 10 and 40 percent. The fill contained traces of
organic soil and roots. The fill may be deeper at locations not explored by LGCI.
Sand – A layer of sand was encountered beneath the topsoil or subsoil in all test pits and in the
boring, and extended to the test pit and boring termination depths. The samples in this layer were
described as poorly graded sand with up to 10 percent fines and up to 15 percent gravel.
The standard penetration tests SPT N-values in this layer ranged between 9 and 27 blows per
foot (bpf) with most values higher than 11 bpf, indicating mostly medium dense sand.
2.5 Groundwater
Groundwater was not encountered in the test pits, and was encountered at a depth of 14 feet
during drilling and 19.9 feet beneath the ground surface at the end of drilling in boring B-4 as
shown in Table 2 and in the boring log.
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
7
The groundwater information reported herein is based on observations made during or shortly
after the completion of drilling and excavation, and may not represent the actual groundwater
2
conditions, as additional time may be required for the groundwater levels to stabilize.
The groundwater information presented in this report only represents the conditions encountered
at the time and location of the explorations. Seasonal fluctuation should be anticipated.
2.6 Laboratory Test Data
LGCI submitted two (2) soil samples collected from the test pits for grain-size analysis. The
results of the grain-size analysis are provided in the test data sheets included in Appendix D and
are summarized in the table below.
Grain-Size Analysis Test Results
Test Pit
No.
Sample
No.
Stratum Sample
depth (ft.)
Percent
Gravel
Percent
Sand
Percent
Fines
TP-1
TP-9
Grab
Grab
Subsoil
Fill
0.8 – 4.5
1.4 – 4.5
14.5
28.0
60.3
60.3
25.2
11.7
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
8
3. EVALUATION AND RECOMMENDATIONS
3.1 General
Based on our understanding of the proposed residential development, our observation of the
explorations, and the results of our laboratory testing, there are a few issues that we would like to
highlight for consideration and discussion.
3.1.1 Surficial Topsoil and Subsoil
The surficial topsoil and subsoil are not suitable to support the proposed
3
buildings and should be entirely removed from under the proposed
building footprints. The removal should extend over an area extending
beyond the zone of influence of the footings and at a minimum 2 feet
outside the proposed building footprint, whichever is greater. The zone
of influence is defined as the zone beneath a line starting at the bottom
outer edge of the footings and extending outward and downward at a
slope of 1H:1V. In paved areas, we recommend entirely removing the
surficial topsoil from within the proposed paved areas. We recommend
removing the subsoil to the top of the natural sand, to the top of the
existing fill, or to a minimum depth of 18 inches beneath the bottom of
the proposed pavement, whichever occurs first. Where the subsoil
extends to depths greater than 18 inches beneath the bottom of the
proposed pavement, the subsoil deeper than 18 inches beneath the
bottom of the proposed pavement may remain in place provided that it is
improved in accordance with the recommendations in Section 4.1. The
removal should extend 5 feet outside the limits of improvement areas.
3.1.2 Existing Fill
The existing fill is not suitable to support the proposed buildings an d
should be entirely removed from within the proposed building
footprints. We anticipate that the removal will extend to depths of about
4.5 feet beneath the ground surface. The removal should extend
over an area extending beyond the zone of influence of the footings and
at a minimum 2 feet outside the proposed building footprint, whichever
is greater.
The zone of influence is
defined as the zone beneath a line starting at the bottom outer edge of the footings and
extending outward and downward at a slope of 1H:1V. The fill may be deeper at locations
not explored by LGCI, especially near the brooks. We recommend engaging LGCI to
perform additional explorations at the site to further delineate the limits and thickness of the
existing fill.
The existing fill may remain in place within the proposed parking lots and driveways after it
is improved in accordance with the recommendation in Section 4.1.
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
4
9
3.1.3 Shallow Foundations and Slab-on-grade
After the surficial topsoil, subsoil, and existing fill are entirely removed from
within the proposed building footprint, the proposed building may be supported on
shallow footings bearing in the natural sand. Due to the susceptibility of the natural
sand to disturbance, we recommend placing footings on minimum of 6 inches of
Structural Fill. The proposed slab may be designed as a slab-on-grade supported on
Structural Fill placed directly on top of the natural sand.
Our recommendation for footing design and slab-on-grade are presented in Section
3.2 and 3.3, respectively.
3.1.4 Reuse of Onsite Materials
The subsoil is too silty and may not be used as backfill may be used in
landscaped areas; however, the contractor is cautioned that when wet,
the subsoil will become very soft and difficult to handle. l under
roadways and buildings. It
The natural sand is generally poorly
graded and while it may be used as Ordinary Fill (see Section 4.3), it will require to be
wetted and will require significant effort to achieve the required relative compaction.
Additional recommendations for fill materials and reuse, including amendment/improvement,
of onsite materials are presented in Sections 4.3 and 4.4.
3.2 Foundation Recommendations
3.2.1 Footing Design
• For footings supported on a minimum of 6 inches of Structural Fill placed directly over
the natural sand after removing the surficial topsoil, the subsoil, and the existing fill, we
recommend a net allowable bearing pressure of 4 kips per square foot (ksf).
• Footing subgrades should be prepared in accordance with the recommendations in Section
4.1.
• All foundations should be designed in accordance with The Commonwealth of
Massachusetts State Building Code 780 CMR, ninth Edition (MSBC 9th Edition).
• Exterior footings and footings in unheated areas should be placed at a minimum depth of 4
feet below the final exterior grade to provide adequate frost protection. Interior footings
in heated areas may be designed and constructed at a minimum depth of 2 feet below
finished floor grades.
• Wall footings should be designed and constructed with continuous, longitudinal steel
reinforcement for greater bending strength to span across small areas of loose or soft soils
that may go undetected during construction.
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
10
• A representative of LGCI should be engaged to observe that the subgrade has been
prepared in accordance with our recommendations.
3.2.2 Settlement Estimate
5
For footings designed using the net allowable bearing pressure recommended above, we
anticipate that the settlement will be about 1 inch and that the differential settlement of the
footings will be 3/4 inch or less, over 25 feet. Total and differential settlements of these
magnitudes are usually considered tolerable for the anticipated construction. As the design
progresses and the settlement estimates are refined, the tolerance of the proposed structure
to the predicted total and differential settlements should be assessed by the structural
engineer.
3.3 Concrete Slab Considerations
• Floor slabs can be constructed as slabs-on-grade bearing on a minimum of 12 inches of
Structural Fill placed directly on top of the natural sand. The subgrade of the slabs should be
prepared as described in Section 4.1.
• To reduce the potential for dampness in the proposed floor slabs, the
project architect may
consider placing a vapor barrier beneath the floor slabs. The vapor
barrier should be protected
from puncture during construction of the slabs.
• For the design of the floor slabs bearing on the materials described above, we recommend
using a modulus of subgrade reaction, ks1, of 80 tons per cubic foot (tcf). Please note that the
values of ks1 are for a 1 x 1 square foot area. These values should be adjusted for larger areas
using the following expression:
where:
ks = Coefficient of vertical subgrade reaction for loaded area,
ks1 = Coefficient of vertical subgrade reaction for 1 x 1 square foot area, and
B = Width of area loaded, in feet.
Please note that cracking of slabs-on-grade can occur as a result of heaving or compression of the
underlying soil, but also as a result of concrete curing stresses. To reduce the potential for
cracking, the precautions listed below should be closely followed for construction of all slabs-on-
grade:
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
11
• Construction joints should be provided between the floor slab and the walls and columns
in accordance with the American Concrete Institute (ACI) requirements, or other
applicable code.
• Backfill in interior utility trenches should be properly compacted.
• In order for the movement of exterior slabs not to be transmitted to new foundations or
superstructures, exterior slabs such as approach slabs and sidewalks, should be isolated
from the superstructure.
3.4 Under-slab Drains
Based on the current groundwater levels observed in the explorations, we anticipate that under-
slab drainage systems will not be required under the proposed buildings.
3.5 Seismic Design
In accordance with Section 1613 of MSBC 9th Edition and International Building Code (2015
6
IBC) and based on the boring data, the seismic criteria for the site are as follows:
• Site Class: D
• Spectral Response Acceleration at short period (Ss): 0.152g
• Spectral Response Acceleration at 1 sec. (S1): 0.055g
• Site Coefficient Fa (Table 1613.5.3(1)): 1.6
• Site Coefficient Fv (Table 1613.5.3(2): 2.4
• Adjusted spectral response SMS: 0.242 g
• Adjusted spectral responses SM1: 0.132 g
Based on the boring information, we believe the site soils are not susceptible to liquefaction.
3.6 Lateral Pressures for Wall Design
3.6.1 Lateral Earth Pressures
Lateral earth pressures recommended for design of below grade building walls, if any, or site
retaining walls are provided below.
Coefficient of Active Earth Pressure, KA: 0.33
Coefficient of At-Rest Earth Pressure, Ko: 0.50
Coefficient of Passive Earth Pressure, Kp: 3.0
Total Unit Weight : 125 pcf
Note: The values in the table are based on a friction angle for the backfill of 30 degrees and
neglecting friction
between the backfill and the wall. The design active and passive coefficients are based on
horizontal surfaces
(non-sloping backfill) on both the active and passive sides, and a vertical wall face.
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
12
• Exterior walls of below ground spaces, and retaining walls braced at the top to restrain
movement/rotation, should be designed using the “at-rest” pressure coefficient.
• We recommend placing free-draining material within the 3 feet
immediately behind
retaining walls. We recommend providing weep holes in site walls to
promote drainage
where possible, or a pipe should be placed at the base of the wall to
collect the
groundwater. Groundwater collected by the wall drains should be
discharged in a lower
area if gravity flow is possible.
• Passive earth pressures should only be used at the toe of the wall where special measures
or provisions are taken to prevent disturbance or future removal of the soil on the
passive side of the wall, or in areas where the wall design includes a key. In any case,
the passive pressures should be neglected in the top 2 feet.
• Where a permanent vertical uniform load will be applied on the active side immediately
7
adjacent to the wall, a horizontal surcharge load equal to half of the uniform vertical
load should be applied over the height of the wall. At a minimum, a temporary
construction surcharge of 100 psf should be applied uniformly over the height of the
wall.
• We recommend using an ultimate friction factor of 0.45 between the natural sand and
the bottom of the wall. Below grade walls should be designed for minimum factors of
safety of 1.5 for sliding and 2.0 for overturning.
3.6.2 Seismic Pressures
In accordance with MSBC 9th Edition, Section 1610, a lateral earthquake force equal to
0.100*(Ss)*(Fa)**H2 should be included in the design of walls (for horizontal backfill),
where Ss is the maximum considered earthquake spectral response acceleration (defined in
Section 3.5), Fa is the site coefficient (defined in Section 3.5), is the total unit weight of the
soil backfill, and H is the height of the wall.
The earthquake force should be distributed as an inverted triangle over the height of the
wall. In accordance with MSBC 9th Edition, Section 1610.2, a load factor of 1.43 shall be
applied to the earthquake force for wall strength design.
Temporary surcharges should not be included when designing for earthquake loads.
Surcharge loads applied for extended periods of time shall be included in the total static
lateral soil pressure and their earthquake lateral force shall be computed and added to the
force determined above.
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
13
3.6.3 Perimeter Drains
• We recommend that free-draining material be placed within 3 feet of
the below grade
spaces, if any. To reduce the potential for dampness in below-ground
spaces, perimeter
walls of the proposed below-ground spaces, if any, should be damp-
proofed.
• We recommend that drains be provided behind the exterior of walls of
below-ground
spaces, and behind site retaining walls, if any. The drains should consist
of 6-inch
perforated PVC pipes installed with the slots facing down. Perimeter
drains should be
installed at the bottom of the wall in 18 inches of crushed stone wrapped
in a geotextile
fabric for separation and filtration. Site retaining walls may be designed
8
with weep holes
discharging near the bottom of the face of the walls.
• Groundwater collected by the wall drains could be discharged in a lower area if gravity
flow is possible. Alternatively, it should be discharged into the street drains. A permit
would be required for discharge into street drains.
3.7 Pavement Considerations
3.7.1 General
The subsurface conditions encountered at the site are generally suitable to support the
proposed driveways, parking lots, and sidewalks after preparation of the subgrade as
described in Section 4.1.
• We recommend entirely removing the topsoil from within the footprint of the proposed
driveways and parking lots.
• The subsoil should be removed in accordance with the recommendations in Sections 3.1.1
and 4.1.
• The existing fill should be improved in accordance with the recommendations in Section
4.1.
• Cobbles and boulders should be removed to at least 18 inches below the bottom of the
pavement.
3.7.2 Sidewalks
Sidewalks should be placed on a minimum of 12 inches of Structural Fill with less than 5
percent fines. To reduce the potential for heave caused by surface water penetrating under
the sidewalk, the joints between the sidewalk concrete sections should be sealed with a
waterproof compound. The sidewalks should be sloped away from the building or other
vertical surfaces to promote flow of water. To the extent possible, roof leaders should not
discharge onto sidewalk surfaces.
4.1 Subgrade Preparation
• The surficial topsoil, subsoil, existing fill, and other deleterious matter should be entirely
removed from within the proposed building footprint before the start of foundation work.
• Tree stumps, root balls, and roots larger than ½ inch in diameter should be removed and the
cavities filled with suitable material and compacted per Section 4.3 of this report.
• Topsoil, root balls, and other deleterious material should be entirely removed from within the
proposed paved areas.
• Cobbles and boulders should be removed at least 6 inches from beneath footings, and 24
inches beneath the bottom of proposed slabs and paved areas. The resulting excavations
should be backfilled with compacted Structural Fill under the building and with Ordinary Fill
under the subbase of paved areas.
• Due to the high susceptibility of the natural soil for disturbance under foot and vehicular
traffic, we recommend placing a minimum of 6 inches of Structural Fill at the bottom of the
excavation or 4 inches of lean concrete to serve as a working mat.
• The base of the footing excavations in granular soil should be compacted with a dynamic
vibratory compactor weighing at least 200 pounds and imparting a minimum of 4 kips of
force to the subgrade before placing the required 6 inches of Structural Fill.
• The subgrade of the slabs should be compacted using a vibratory roller compactor imparting
a minimum of 40 kips of force to the subgrade before placing Structural Fill.
9
• Where soft zones are revealed during the preparation of the subgrade, the soft materials or
buried organic soil should be removed and replaced with Structural Fill within the building
footprint and with Ordinary Fill beneath the subbase of paved areas.
• To reduce the potential of increasing lateral pressures on the retaining walls, fill placed within
3 feet of the walls, if any, should be compacted using a small plate compactor imparting a
maximum dynamic effort of 4 kips. The fill within 3 feet of the walls should be placed in
maximum 8-inch loose lifts.
• After the surficial topsoil is entirely removed and after the subsoil is removed from within
the proposed paved areas in accordance with the recommendations in Section 3.1.1, the
existing subsoil deeper than 18 inches beneath the bottom of the proposed pavement and/or
the existing fill should be improved by compacting the exposed surface with at least six (6)
passes of a vibratory roller compactor imparting a dynamic effort of at least 40 kips. Where
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
16
soft zones of soil are observed, the soft soil should be removed, and the grade should be
restored using Ordinary Fill to the bottom of the proposed subbase layer.
• Fill placed within the footprint of the proposed building should meet the gradation and
compaction requirements of Structural Fill shown in Section 4.3.
• Fill placed under the subbase of paved areas, should meet the gradation and compaction
requirements of Ordinary Fill shown in Section 4.3.
• Fill placed in the top 12 inches beneath sidewalks and exterior slabs should consist of
Structural Fill with less than 5 percent fines.
• When crushed stone is required in the drawings or it is used for the convenience of the
contractor, it should be wrapped in a geotextile fabric for separation. The geotextile fabric
should not be used under retaining walls as it promotes a plane of sliding.
• An LGCI geotechnical representative should observe the removal of the existing fill and the
subgrades of footings and slabs prior to fill and concrete placement to verify that the exposed
bearing materials are suitable for the design soil bearing pressure. If soft or loose pockets are
encountered in the footing excavations, the soft or loose materials should be removed, and
the bottom of the footing should be placed at a lower elevation on firm soil, or the resulting
excavation should be backfilled with Structural Fill or crushed stone wrapped in geotextile
for separation. The LGCI representative should also observe the improvement of the existing
subsoil and/or fill within the proposed paved areas.
4.4 Reuse of Onsite Materials
The subsoil is silty and cannot be used as Ordinary or Structural Fill. The subsoil can be used in
landscaped areas that do not support structures, pavements, sidewalks, or ramps. Based on our
field observations and the results of the grain-size analyses, we anticipate some of the natural
soil
may be used as Ordinary Fill.
The natural soil and subsoil free of organic matter may be amended/improved by blending with
10
crushed stone to produce Ordinary and Structural Fill.
Suitable imported material and amended/improved materials should be stockpiled separately
from unimproved onsite soils. Should reusable materials be encountered during excavation,
they
should be excavated and stockpiled separately for compliance testing.
Soils with 20 percent or greater fines content are generally very sensitive to moisture content
variations and are susceptible to frost. Such soils are very difficult to compact at moisture
contents that are much higher or much lower than the optimum moisture content determined
from the laboratory compaction test. Therefore, strict moisture control should be implemented
during compaction of onsite soils with fines contents of 20 percent or greater. The contractor
should be prepared to remove and replace such soils if pumping occurs.
All materials to be used as fill, including blended materials, should first be tested for compliance
with the applicable gradation specifications.
4.5 Groundwater Control Procedures
Based on the groundwater levels encountered in our explorations, we do not anticipate that
groundwater control procedures will be needed during the excavations to remove the topsoil
and
subsoil, and the existing fill, and in utility trenches.
We anticipate that filtered sump pumps installed in a series of sump pits located at least three
feet below the bottom of the proposed excavations may be sufficient to handle surface runoff
that
may enter the excavations during wet weather. Please note that the natural soil was fairly
permeable. Accordingly, the site contractor should be prepared to use multiple sump pumps
during wet weather.
The contractor should be permitted to employ whatever commonly accepted means and
practices
are necessary to maintain the groundwater level below the bottom of the excavations, and to
maintain a dry excavation during wet weather. Groundwater levels should be maintained at a
minimum of 1-foot below the bottom of excavations during construction. Placement of
reinforcing steel or concrete in standing water should not be permitted.
To reduce the potential for sinkholes developing over sump pump pits after the sump pumps
are
removed, the crushed stone placed in the sump pump pits should be wrapped in a geotextile
Geotechnical Report
Proposed Residential Development
Hyannis, Massachusetts
LGCI Project No. 2026-Rev. 2
19
fabric. Alternatively, the crushed stone should be entirely removed after the sump pump is no
longer in use and the sump pump pit should be restored with suitable backfill.
4.6 Temporary Excavations
All excavations to receive human traffic should be constructed in accordance with the OSHA
guidelines.
The site soils should generally be considered Type “C” and should have a maximum allowable
11
slope of 1.5 Horizontal to 1 Vertical (1.5H:1V) for excavations less than 20 feet deep. Deeper
excavations, if needed, should have shoring designed by a professional engineer.
The contractor is solely responsible for designing and constructing stable, temporary
excavations
and should shore, slope, or bench the sides of the excavations as required to maintain stability
of
the excavation sides and bottom and to protect existing structures.
Test Pits show poorly graded sand, some silt, down to 11-12’